Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2019, January - 2020, January - 2021, January - 2018, February - 2019, February - 2020, February - 2021, February - 2018, March - 2018, March - 2019, March - 2020, March - 2021, April - 2018, April - 2019, April - 2020, April - 2021, May - 2018, May - 2020, May - 2021, June - 2018, July - 2020, July - 2017, August - 2019, August - 2020, August - 2017, September - 2019, September - 2020, September - 2017, October - 2019, October - 2020, October - 2017, November - 2018, November - 2019, November - 2017, December - 2018, December - 2019, December - 2020, December - 2017,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1046
(OG)
191131-170016-Construction / Maintenance & Rehabilitation of Levis / Khassadar Picquets in Bajaur Agency. [MA]
Bajaur
30-11--1 30-11--1 - 30-11--1 - 88.655 42.655 41 10 10 0 42.655 5 94% 48%
December - 2020
16- Units Completed and handed over =09 Land not available =6 Land dispute=1
No Image
1046
(OG)
191131-170016-Construction / Maintenance & Rehabilitation of Levis / Khassadar Picquets in Bajaur Agency. [MA]
Bajaur
30-11--1 30-11--1 - 30-11--1 - 88.655 42.655 41 10 10 0 42.655 5 94% 48%
December - 2020
16- Units Completed and handed over =09 Land not available =6 Land dispute=1
No Image
1046
(OG)
191131-170016-Construction / Maintenance & Rehabilitation of Levis / Khassadar Picquets in Bajaur Agency. [MA]
Bajaur
30-11--1 30-11--1 - 30-11--1 - 88.655 42.655 41 41 0 0 42.655 5 94% 48%
October - 2020
16- Units Completed =07 Work in finishing=2 Land not available =6 Land dispute=1
No Image
1046
(OG)
191131-170016-Construction / Maintenance & Rehabilitation of Levis / Khassadar Picquets in Bajaur Agency. [MA]
Bajaur
30-11--1 30-11--1 - 30-11--1 - 88.655 42.655 41 41 0 0 42.655 5 94% 48%
September - 2020
16- Units Completed =07 Work in finishing=2 Land not available =6 Land dispute=1
No Image
1046
(OG)
191131-170016-Construction / Maintenance & Rehabilitation of Levis / Khassadar Picquets in Bajaur Agency. [MA]
Bajaur
30-11--1 30-11--1 - 30-11--1 - 88.655 47.655 41 41 0 0 47.655 0 - -
August - 2020
No Image
1046
(OG)
191131-170016-Construction / Maintenance & Rehabilitation of Levis / Khassadar Picquets in Bajaur Agency. [MA]
Bajaur
30-11--1 30-11--1 - 30-11--1 - 88.655 47.655 41 0 0 0 47.655 0
July - 2020
No Image
1046
(OG)
191131-170016-Construction / Maintenance & Rehabilitation of Levis / Khassadar Picquets in Bajaur Agency. [MA]
Bajaur
30-11--1 30-11--1 - 30-11--1 - 88.655 42.655 41 30.312 30.312 8.371 51.026 5 94% 58%
May - 2021
16- Units 1. FInishing 2. H/O 3. Roofing 4. Land not avaible 5. Land not avaible 6. Roof laid 7. Land not avaible 8. Land not avaible 9. S/Str in progress 10. H/O 11. H/O 12. H/O 13. H/O 14. H/O 15. H/O 16. H/O
No Image
1 Khasadar Picquet at Skindaro Hayati
2 Khasadar Picquet at Batwar Salarzai
3 Khasadar Picquet at Khar Bazar
4 Khasadar Picquet at Hayati GO Kandow
5 Khasadar Picquet  at Khan Dheri
6Khasadar Picquet at Ghakhi Nakhtar
7 Khasadar Picquet at Mukha Khawar Mamud
8 Khasadar Picquet at Loe Kharki
9 Khasadar Picquet at Hilal Khel
10 Khasadar Picquet at Jangazai Mamund
11 Khasadar Picquet at Raghagan Bazar
12 Khasadar Picquet at Mir Khan ARang
13 Khasadar Picquet Tawheed Abad
14 Khasadar Picquet Seri Sar Sharbati
15 Khasadar Picquet Pashat Salarzai
16 Khasadar Picquet Tarkho Mamund
1046
(OG)
191131-170016-Construction / Maintenance & Rehabilitation of Levis / Khassadar Picquets in Bajaur Agency. [MA]
Bajaur
30-11--1 30-11--1 - 30-11--1 - 88.655 42.655 41 30.312 30.312 6.345 49 5 94% 55%
April - 2021
16- Units Completed and handed over =09 Land not available =6 Land dispute=1
No Image
1 Khasadar Picquet at Skindaro Hayati
2 Khasadar Picquet at Batwar Salarzai
3 Khasadar Picquet at Khar Bazar
4 Khasadar Picquet at Hayati GO Kandow
5 Khasadar Picquet  at Khan Dheri
6Khasadar Picquet at Ghakhi Nakhtar
7 Khasadar Picquet at Mukha Khawar Mamud
8 Khasadar Picquet at Loe Kharki
9 Khasadar Picquet at Hilal Khel
10 Khasadar Picquet at Jangazai Mamund
11 Khasadar Picquet at Raghagan Bazar
12 Khasadar Picquet at Mir Khan ARang
13 Khasadar Picquet Tawheed Abad
14 Khasadar Picquet Seri Sar Sharbati
15 Khasadar Picquet Pashat Salarzai
16 Khasadar Picquet Tarkho Mamund
1046
(OG)
191131-170016-Construction / Maintenance & Rehabilitation of Levis / Khassadar Picquets in Bajaur Agency. [MA]
Bajaur
30-11--1 30-11--1 - 30-11--1 - 88.655 42.655 41 10 10 2.65 45.305 5 94% 51%
March - 2021
16- Units Completed and handed over =09 Land not available =6 Land dispute=1
No Image
1 Khasadar Picquet at Skindaro Hayati
2 Khasadar Picquet at Batwar Salarzai
3 Khasadar Picquet at Khar Bazar
4 Khasadar Picquet at Hayati GO Kandow
5 Khasadar Picquet  at Khan Dheri
6Khasadar Picquet at Ghakhi Nakhtar
7 Khasadar Picquet at Mukha Khawar Mamud
8 Khasadar Picquet at Loe Kharki
9 Khasadar Picquet at Hilal Khel
10 Khasadar Picquet at Jangazai Mamund
11 Khasadar Picquet at Raghagan Bazar
12 Khasadar Picquet at Mir Khan ARang
13 Khasadar Picquet Tawheed Abad
14 Khasadar Picquet Seri Sar Sharbati
15 Khasadar Picquet Pashat Salarzai
16 Khasadar Picquet Tarkho Mamund
1046
(OG)
191131-170016-Construction / Maintenance & Rehabilitation of Levis / Khassadar Picquets in Bajaur Agency. [MA]
Bajaur
30-11--1 30-11--1 - 30-11--1 - 88.655 42.655 41 10 10 0 42.655 5 94% 48%
February - 2021
16- Units Completed and handed over =09 Land not available =6 Land dispute=1
No Image
1 Khasadar Picquet at Skindaro Hayati
2 Khasadar Picquet at Batwar Salarzai
3 Khasadar Picquet at Khar Bazar
4 Khasadar Picquet at Hayati GO Kandow
5 Khasadar Picquet  at Khan Dheri
6Khasadar Picquet at Ghakhi Nakhtar
7 Khasadar Picquet at Mukha Khawar Mamud
8 Khasadar Picquet at Loe Kharki
9 Khasadar Picquet at Hilal Khel
10 Khasadar Picquet at Jangazai Mamund
11 Khasadar Picquet at Raghagan Bazar
12 Khasadar Picquet at Mir Khan ARang
13 Khasadar Picquet Tawheed Abad
14 Khasadar Picquet Seri Sar Sharbati
15 Khasadar Picquet Pashat Salarzai
16 Khasadar Picquet Tarkho Mamund
1046
(OG)
191131-170016-Construction / Maintenance & Rehabilitation of Levis / Khassadar Picquets in Bajaur Agency. [MA]
Bajaur
30-11--1 30-11--1 - 30-11--1 - 88.655 42.655 41 10 10 0 42.655 5 94% 48%
January - 2021
16- Units Completed and handed over =09 Land not available =6 Land dispute=1
No Image
1 Khasadar Picquet at Skindaro Hayati
2 Khasadar Picquet at Batwar Salarzai
3 Khasadar Picquet at Khar Bazar
4 Khasadar Picquet at Hayati GO Kandow
5 Khasadar Picquet  at Khan Dheri
6Khasadar Picquet at Ghakhi Nakhtar
7 Khasadar Picquet at Mukha Khawar Mamud
8 Khasadar Picquet at Loe Kharki
9 Khasadar Picquet at Hilal Khel
10 Khasadar Picquet at Jangazai Mamund
11 Khasadar Picquet at Raghagan Bazar
12 Khasadar Picquet at Mir Khan ARang
13 Khasadar Picquet Tawheed Abad
14 Khasadar Picquet Seri Sar Sharbati
15 Khasadar Picquet Pashat Salarzai
16 Khasadar Picquet Tarkho Mamund
1046
(OG)
160403-Construction of Social Welfare Complex at Nowshera
Nowshera
30-11--1 30-11--1 - 30-11--1 - 89.802 17.5 14 14 3.5 0 17.5 58.302 35% 19%
December - 2019
1) Block C - Roof laid 2) Block B - Shuttering in progress.
No Image
Nowshera
1046
(OG)
160403-Construction of Social Welfare Complex at Nowshera
Nowshera
30-11--1 30-11--1 - 30-11--1 - 89.802 17.5 14 14 3.5 0 17.5 58.302 35% 19%
November - 2019
1) Block C - Roof laid 2) Block B - Shuttering in progress.
No Image
Nowshera
1046
(OG)
160403-Construction of Social Welfare Complex at Nowshera
Nowshera
30-11--1 30-11--1 - 30-11--1 - 89.802 17.5 14 14 3.5 0 17.5 58.302 35% 19%
October - 2019
1) Block C - Roof laid 2) Block B - Shuttering in progress.
No Image
Nowshera
1046
(OG)
160403-Construction of Social Welfare Complex at Nowshera
Nowshera
30-11--1 30-11--1 - 30-11--1 - 89.802 17.5 14 14 0 0 17.5 58.302 35% 19%
September - 2019
1) Block C - Roof laid 2) Block B - Shuttering in progress.
No Image
Nowshera
1046
(OG)
160403-Construction of Social Welfare Complex at Nowshera
Nowshera
30-11--1 30-11--1 - 30-11--1 - 89.802 17.5 14 14 0 0 17.5 58.302 35% 19%
August - 2019
1) Block C - Roof laid 2) Block B - Shuttering in progress.
No Image
Nowshera
1046
(OG)
160403-Construction of Social Welfare Complex at Nowshera
Nowshera
30-11--1 30-11--1 - 30-11--1 - 89.802 17.5 14 14 14 10.037 27.537 58.302 35% 31%
May - 2020
1) Block A+B+C+D+E+F plastering. 2. FF Plastering in progress B/W in progress.
No Image
Nowshera
1046
(OG)
160403-Construction of Social Welfare Complex at Nowshera
Nowshera
30-11--1 30-11--1 - 30-11--1 - 89.802 17.5 14 14 3.5 3.5 21 58.302 35% 23%
April - 2020
1) Block A+B+C+D+E+F plastering. 2. FF Plastering in progress B/W in progress.
No Image
Nowshera
1046
(OG)
160403-Construction of Social Welfare Complex at Nowshera
Nowshera
30-11--1 30-11--1 - 30-11--1 - 89.802 17.5 14 14 3.5 3.5 21 58.302 35% 23%
March - 2020
1) Block A+B+C+D+E+F plastering. 2. FF Plastering in progress B/W in progress.
No Image
Nowshera
1046
(OG)
160403-Construction of Social Welfare Complex at Nowshera
Nowshera
30-11--1 30-11--1 - 30-11--1 - 89.802 17.5 14 14 3.5 3.5 21 58.302 35% 23%
February - 2020
1) Block A+B+C+D+E+F plastering. 2. FF Plastering in progress B/W in progress.
No Image
Nowshera
1046
(OG)
160403-Construction of Social Welfare Complex at Nowshera
Nowshera
30-11--1 30-11--1 - 30-11--1 - 89.802 17.5 14 14 3.5 3.5 21 58.302 35% 23%
January - 2020
1) Block A+B+C+D+E+F plastering. 2. FF Plastering in progress B/W in progress.
No Image
Nowshera
1046
(OG)
150810-Construction / pavement of roads / streets in UC’s Kheshgi Bala, Kheshgi Payan, Aman Garh and Gandheri, Nowshera.
Nowshera
HW
01-05-16 - - 23-12-16 - 350 175.272 100 85.5 85.5 47.281 222.553 74.728 79% 64%
December - 2017
Length 15 Km - structure work, street pavement in progress. Revised PC-I/DCE for Rs.550 m submitted to P&D. Pre-PDWP held.
No Image
1046
(OG)
150810-Construction / pavement of roads / streets in UC?s Kheshgi Bala, Kheshgi Payan, Aman Garh and Gandheri, Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 350 175.272 100 85.5 34.48 34.48 209.752 74.728 79% 60%
November - 2017
Length 15 Km - structure work, street pavement in progress. Revised PC-I/DCE for Rs.550 m submitted to SOR on 17/11/2017.
No Image
1046
(OG)
150810-Construction / pavement of roads / streets in UC?s Kheshgi Bala, Kheshgi Payan, Aman Garh and Gandheri, Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 350 175.272 100 100 35.5 15.5 190.772 74.728 79% 55%
October - 2017
Length 15 Km - structure work, street pavement in progress.
No Image
1046
(OG)
150810-Construction / pavement of roads / streets in UC’s Kheshgi Bala, Kheshgi Payan, Aman Garh and Gandheri, Nowshera.
Nowshera
HW
01-05-16 - - 23-12-16 - 350 175.272 100 100 35.5 10.016 185.288 74.728 79% 53%
September - 2017
Length 15 Km - structure work, street pavement in progress.
No Image
1046
(OG)
150810-Construction / pavement of roads / streets in UC’s Kheshgi Bala, Kheshgi Payan, Aman Garh and Gandheri, Nowshera.
Nowshera
HW
01-05-16 - - 23-12-16 - 350 175.272 100 100 35.5 10.016 185.288 74.728 79% 53%
August - 2017
Length 15 Km - structure work, street pavement in progress.
No Image
1046
(OG)
150810-Construction / pavement of roads / streets in UC’s Kheshgi Bala, Kheshgi Payan, Aman Garh and Gandheri, Nowshera.
Nowshera
HW
01-05-16 - - 23-12-16 - 350 175.272 100 100 35.5 0 175.272 74.728 79% 50%
July - 2017
Length 15 Km - structure work, street pavement in progress. Revised PC-I/DCE submitted to SE.
No Image
1046
(OG)
150810-Construction / pavement of roads / streets in UC?s Kheshgi Bala, Kheshgi Payan, Aman Garh and Gandheri, Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 549.577 175.272 100 92.031 92.031 92.031 267.303 274.305 50% 49%
June - 2018
Length 15 Km - structure work, street pavement in progress.
No Image
1) Kheshgi Payan
2) Kheshgi Bala
3) Aman Garh
4) Gandheri
5) UC Aman Garh and Gandheri
6) UC Kheshgi Payan & Bala
7) UC Kheshgi Payan
8) Kheshgi Bala UC Aman Garh UC Gandheri
1046
(OG)
150810-Construction / pavement of roads / streets in UC?s Kheshgi Bala, Kheshgi Payan, Aman Garh and Gandheri, Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 549.577 175.272 100 100 92.031 92.031 267.303 274.305 50% 49%
May - 2018
Length 15 Km - structure work, street pavement in progress.
No Image
1) Kheshgi Payan
2) Kheshgi Bala
3) Aman Garh
4) Gandheri
5) UC Aman Garh and Gandheri
6) UC Kheshgi Payan & Bala
7) UC Kheshgi Payan
8) Kheshgi Bala UC Aman Garh UC Gandheri
1046
(OG)
150810-Construction / pavement of roads / streets in UC?s Kheshgi Bala, Kheshgi Payan, Aman Garh and Gandheri, Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 549.577 175.272 100 100 92.031 92.031 267.303 274.305 50% 49%
April - 2018
Length 15 Km - structure work, street pavement in progress.
No Image
1) Kheshgi Payan
2) Kheshgi Bala
3) Aman Garh
4) Gandheri
5) UC Aman Garh and Gandheri
6) UC Kheshgi Payan & Bala
7) UC Kheshgi Payan
8) Kheshgi Bala UC Aman Garh UC Gandheri
1046
(OG)
150810-Construction / pavement of roads / streets in UC?s Kheshgi Bala, Kheshgi Payan, Aman Garh and Gandheri, Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 549.577 175.272 100 100 92.03 87.829 263.101 274.305 50% 48%
March - 2018
Length 15 Km - structure work, street pavement in progress.
No Image
1) Kheshgi Payan
2) Kheshgi Bala
3) Aman Garh
4) Gandheri
5) UC Aman Garh and Gandheri
6) UC Kheshgi Payan & Bala
7) UC Kheshgi Payan
8) Kheshgi Bala UC Aman Garh UC Gandheri
1046
(OG)
150810-Construction / pavement of roads / streets in UC?s Kheshgi Bala, Kheshgi Payan, Aman Garh and Gandheri, Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 549.577 175.272 100 104.341 104.341 71.767 247.039 274.305 50% 45%
February - 2018
Length 15 Km - structure work, street pavement in progress.
No Image
1) Kheshgi Payan
2) Kheshgi Bala
3) Aman Garh
4) Gandheri
5) UC Aman Garh and Gandheri
6) UC Kheshgi Payan & Bala
7) UC Kheshgi Payan
8) Kheshgi Bala UC Aman Garh UC Gandheri
1046
(OG)
150810-Construction / pavement of roads / streets in UC?s Kheshgi Bala, Kheshgi Payan, Aman Garh and Gandheri, Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 549.577 175.272 100 104.341 104.341 58.998 234.27 274.305 50% 43%
January - 2018
Length 15 Km - structure work, street pavement in progress.
No Image
1) Kheshgi Payan 2) Kheshgi Bala 3) Aman Garh 4) Gandheri 5) UC Aman Garh and Gandheri 6) UC Kheshgi Payan & Bala 7) UC Kheshgi Payan 8) Kheshgi Bala UC Aman Garh UC Gandheri
1046
(OG)
130510-Feasibility Study, Detailed Designing and Supervision of various roads of C&W Khyber Pakhtunkhwa.
Provincial
30-11--1 30-11--1 - 30-11--1 - 100 2.473 10 10 5.001 0 2.473 0 - -
December - 2018
PC-II approved.
No Image
1046
(OG)
130510-Feasibility Study, Detailed Designing and Supervision of various roads of C&W Khyber Pakhtunkhwa.
Provincial
30-11--1 30-11--1 - 30-11--1 - 100 2.473 10 10 5.001 0 2.473 0 - -
November - 2018
PC-II approved.
No Image
1046
(OG)
130510-Feasibility Study, Detailed Designing and Supervision of various roads of C&W Khyber Pakhtunkhwa.
Provincial
30-11--1 30-11--1 - 30-11--1 - 100 2.473 10 10 5.001 0 2.473 0 - -
November - 2018
PC-II approved.
No Image
1046
(OG)
130510-Feasibility Study, Detailed Designing and Supervision of various roads of C&W Khyber Pakhtunkhwa.
Provincial
30-11--1 30-11--1 - 30-11--1 - 100 2.473 10 5 0.0005 0 2.473 0 - -
April - 2019
PC-II approved.
No Image
1046
(OG)
130510-Feasibility Study, Detailed Designing and Supervision of various roads of C&W Khyber Pakhtunkhwa.
Provincial
30-11--1 30-11--1 - 30-11--1 - 100 2.473 10 5 0.0005 0 2.473 0 - -
March - 2019
PC-II approved.
No Image
1046
(OG)
130510-Feasibility Study, Detailed Designing and Supervision of various roads of C&W Khyber Pakhtunkhwa.
Provincial
30-11--1 30-11--1 - 30-11--1 - 100 2.473 10 5 0.0005 0 2.473 0 - -
March - 2019
PC-II approved.
No Image
1046
(OG)
130510-Feasibility Study, Detailed Designing and Supervision of various roads of C&W Khyber Pakhtunkhwa.
Provincial
30-11--1 30-11--1 - 30-11--1 - 100 2.473 10 5 0.0005 0 2.473 0 - -
February - 2019
PC-II approved.
No Image
1046
(OG)
130510-Feasibility Study, Detailed Designing and Supervision of various roads of C&W Khyber Pakhtunkhwa.
Provincial
30-11--1 30-11--1 - 30-11--1 - 100 2.473 10 10 5.001 0 2.473 0 - -
January - 2019
PC-II approved.
No Image
Pages : 1