Progressive Review for the month(s) of : January - 2019, January - 2020, January - 2021, January - 2018, February - 2019, February - 2020, February - 2021, February - 2018, March - 2018, March - 2019, March - 2020, March - 2021, April - 2018, April - 2019, April - 2020, April - 2021, May - 2018, May - 2020, May - 2021, June - 2018, July - 2020, July - 2017, August - 2019, August - 2020, August - 2017, September - 2019, September - 2020, September - 2017, October - 2019, October - 2020, October - 2017, November - 2018, November - 2019, November - 2017, December - 2018, December - 2019, December - 2020, December - 2017,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1040
(New)
170629-Widening & Improvement of Tarnawa Kohala Bala Road (35 Km) District Haripur.
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 Line Deptt 2100 0 5 5 0 0 0 2095 0% -
December - 2018
Approved for Rs.2232 m in PDWP on 29/11/2018. AA awaited.
No Image
1040
(New)
170629-Widening & Improvement of Tarnawa Kohala Bala Road (35 Km) District Haripur.
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 Line Deptt 2100 0 5 5 0 0 0 2095 0% -
November - 2018
PC-I for Rs. 2100 M approved. AA Awaited.
No Image
1040
(New)
170629-Widening & Improvement of Tarnawa Kohala Bala Road (35 Km) District Haripur.
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 Line Deptt 2100 0 5 5 0 0 0 2095 0% -
November - 2018
PC-I for Rs. 2100 M approved. AA Awaited.
No Image
1040
(New)
170629-Widening & Improvement of Tarnawa Kohala Bala Road (35 Km) District Haripur.
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 - 2232 0 5 5 0 0 0 2227 0% -
April - 2019
Work order issued.
No Image
1040
(New)
170629-Widening & Improvement of Tarnawa Kohala Bala Road (35 Km) District Haripur.
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 - 2232 0 5 5 0 0 0 2227 0% -
March - 2019
Work order issued
No Image
1040
(New)
170629-Widening & Improvement of Tarnawa Kohala Bala Road (35 Km) District Haripur.
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 - 2232 0 5 5 0 0 0 2227 0% -
March - 2019
Work order issued
No Image
1040
(New)
170629-Widening & Improvement of Tarnawa Kohala Bala Road (35 Km) District Haripur.
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 - 2232 0 5 5 0 0 0 2227 0% -
February - 2019
Financial Bid opened . Evaluation in progress.
No Image
1040
(New)
170629-Widening & Improvement of Tarnawa Kohala Bala Road (35 Km) District Haripur.
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 Line Deptt 2232 0 5 5 0 0 0 2227 0% -
January - 2019
Tender called on 04/02/2019. Technical Bid uner process.
No Image
1040
(OG)
191136-180340 - Construction of Levies piquets in District North Waziristan. [MA]
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 45.021 16.021 34 34 10 7.723 23.744 0 100% 53%
December - 2020
07- Units 03 units disputed. 04- Units in progress.
No Image
1040
(OG)
191136-180340 - Construction of Levies piquets in District North Waziristan. [MA]
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 45.021 16.021 34 34 10 7.723 23.744 0 100% 53%
December - 2020
07- Units 03 units disputed. 04- Units in progress.
No Image
1040
(OG)
191136-180340 - Construction of Levies piquets in District North Waziristan. [MA]
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 45.021 16.021 34 34 10 5.366 21.387 0 100% 48%
October - 2020
07- Units 03 units disputed. 04- Units in progress.
No Image
1040
(OG)
191136-180340 - Construction of Levies piquets in District North Waziristan. [MA]
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 45.021 16.021 34 34 10 5.366 21.387 0 100% 48%
September - 2020
07- Units 03 units disputed. 04- Units in progress.
No Image
1040
(OG)
191136-180340 - Construction of Levies piquets in District North Waziristan. [MA]
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 45.021 16.021 34 34 10 0 16.021 0 100% 36%
August - 2020
07- Units 03 units disputed. 04- Units in progress.
No Image
1040
(OG)
191136-180340 - Construction of Levies piquets in District North Waziristan. [MA]
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 45.021 16.021 34 25.99 25.99 7.723 23.744 0 100% 53%
May - 2021
07- Units 03 units disputed. 04- Units in progress. Cannot be completed due to dispute on 03 units./
No Image
1 Levy Picquet Shan Khura
2 Levy Picquet Babari Adda
3 Levy Picquet Ahmad Khel
4 01 No Levy Picquet at Ghulam Khan
5 Hassan Khel Titi Maddda
6 Hassan Khel Patti Khel
7 Hassan Khel Dir Noomi
1040
(OG)
191136-180340 - Construction of Levies piquets in District North Waziristan. [MA]
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 45.021 16.021 34 25.99 25.99 7.723 23.744 0 100% 53%
April - 2021
07- Units 03 units disputed. 04- Units in progress. Cannot be completed due to dispute on 03 units./
No Image
1 Levy Picquet Shan Khura
2 Levy Picquet Babari Adda
3 Levy Picquet Ahmad Khel
4 01 No Levy Picquet at Ghulam Khan
5 Hassan Khel Titi Maddda
6 Hassan Khel Patti Khel
7 Hassan Khel Dir Noomi
1040
(OG)
191136-180340 - Construction of Levies piquets in District North Waziristan. [MA]
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 45.021 16.021 34 25.99 25.99 7.723 23.744 0 100% 53%
March - 2021
07- Units 03 units disputed. 04- Units in progress.
No Image
1 Levy Picquet Shan Khura
2 Levy Picquet Babari Adda
3 Levy Picquet Ahmad Khel
4 01 No Levy Picquet at Ghulam Khan
5 Hassan Khel Titi Maddda
6 Hassan Khel Patti Khel
7 Hassan Khel Dir Noomi
1040
(OG)
191136-180340 - Construction of Levies piquets in District North Waziristan. [MA]
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 45.021 16.021 34 25.99 25.99 7.723 23.744 0 100% 53%
February - 2021
07- Units 03 units disputed. 04- Units in progress.
No Image
1 Levy Picquet Shan Khura
2 Levy Picquet Babari Adda
3 Levy Picquet Ahmad Khel
4 01 No Levy Picquet at Ghulam Khan
5 Hassan Khel Titi Maddda
6 Hassan Khel Patti Khel
7 Hassan Khel Dir Noomi
1040
(OG)
191136-180340 - Construction of Levies piquets in District North Waziristan. [MA]
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 45.021 16.021 34 25.99 25.99 7.723 23.744 0 100% 53%
January - 2021
07- Units 03 units disputed. 04- Units in progress.
No Image
1 Levy Picquet Shan Khura
2 Levy Picquet Babari Adda
3 Levy Picquet Ahmad Khel
4 01 No Levy Picquet at Ghulam Khan
5 Hassan Khel Titi Maddda
6 Hassan Khel Patti Khel
7 Hassan Khel Dir Noomi
1040
(OG)
191136-180340 - Construction of Levies piquets in District North Waziristan. [MA]
North Wazirstan
30-11--1 30-11--1 - 30-11--1 - 45.021 16.021 34 0 0 0 16.021 0 100% 36%
July - 2020
07- Units 03 units disputed. 04- Units in progress.
No Image
1040
(OG)
140992-F/S, Design & Rehabilitation / Widening of Road from GT Road to Khushal Khan Khattak Mazar, Akora Khattak, Nowshera.
Nowshera
HW
11-03-15 - - 19-11-14 - 124.99 118.494 30 3.35 3.35 0 118.494 0 100% 95%
December - 2017
Length 8.3 Km - 8.3 Km completed. Revised PC-I/DCE deferred in PDWP. Summary approved. DCE submitted to P&D deptt. Will be discussed in next PDWP.
No Image
1040
(OG)
140992-F/S, Design & Rehabilitation / Widening of Road from GT Road to Khushal Khan Khattak Mazar, Akora Khattak, Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 124.99 118.494 30 19.35 0 0 118.494 0 100% 95%
November - 2017
Length 8.3 Km - 8.3 Km completed. Revised PC-I/DCE deferred in PDWP. Summary submitted to CA
No Image
1040
(OG)
140992-F/S, Design & Rehabilitation / Widening of Road from GT Road to Khushal Khan Khattak Mazar, Akora Khattak, Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 124.99 118.494 30 30 0 0 118.494 0 100% 95%
October - 2017
Length 8.3 Km - 8.3 Km completed. Revised PC-I/DCE deferred in PDWP.
No Image
1040
(OG)
140992-F/S, Design & Rehabilitation / Widening of Road from GT Road to Khushal Khan Khattak Mazar, Akora Khattak, Nowshera.
Nowshera
HW
11-03-15 - - 19-11-14 - 124.99 118.494 30 30 10.65 0 118.494 0 100% 95%
September - 2017
Length 8.3 Km - 8 Km completed. Revised PC-I/DCE deferred.
No Image
1040
(OG)
140992-F/S, Design & Rehabilitation / Widening of Road from GT Road to Khushal Khan Khattak Mazar, Akora Khattak, Nowshera.
Nowshera
HW
11-03-15 - - 19-11-14 - 124.99 118.494 30 30 10.65 0 118.494 0 100% 95%
August - 2017
Length 8.3 Km - 8 Km completed. Revised PC-I/DCE for Rs.200 m submitted to SOR on 18/08/2017.
No Image
1040
(OG)
140992-F/S, Design & Rehabilitation / Widening of Road from GT Road to Khushal Khan Khattak Mazar, Akora Khattak, Nowshera.
Nowshera
HW
11-03-15 - - 19-11-14 - 124.99 118.494 30 30 10.65 0 118.494 0 100% 95%
July - 2017
Length 8.3 Km - 8 Km completed.
No Image
1040
(OG)
140992-F/S, Design & Rehabilitation / Widening of Road from GT Road to Khushal Khan Khattak Mazar, Akora Khattak, Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 200 118.494 30 4.577 4.577 0 118.494 51.506 74% 59%
June - 2018
Length 8.3 Km - 8.3 Km completed. Summary approved. Additional scope - tender called on 09/04/2018.
No Image
Nowshera
1040
(OG)
140992-F/S, Design & Rehabilitation / Widening of Road from GT Road to Khushal Khan Khattak Mazar, Akora Khattak, Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 200 118.494 30 4.577 4.577 0 118.494 51.506 74% 59%
May - 2018
Length 8.3 Km - 8.3 Km completed. Summary approved. Additional scope - tender called on 09/04/2018.
No Image
Nowshera
1040
(OG)
140992-F/S, Design & Rehabilitation / Widening of Road from GT Road to Khushal Khan Khattak Mazar, Akora Khattak, Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 200 118.494 30 4.577 4.577 0 118.494 51.506 74% 59%
April - 2018
Length 8.3 Km - 8.3 Km completed. Summary approved. Additional scope - tender called on 09/04/2018.
No Image
Nowshera
1040
(OG)
140992-F/S, Design & Rehabilitation / Widening of Road from GT Road to Khushal Khan Khattak Mazar, Akora Khattak, Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 200 118.494 30 4.57 4.57 0 118.494 51.506 74% 59%
March - 2018
Length 8.3 Km - 8.3 Km completed. Summary approved. Additional scope - tender called on 09/04/2018.
No Image
Nowshera
1040
(OG)
140992-F/S, Design & Rehabilitation / Widening of Road from GT Road to Khushal Khan Khattak Mazar, Akora Khattak, Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 124.99 118.494 30 11.887 11.887 0 118.494 0 100% 95%
February - 2018
Length 8.3 Km - 8.3 Km completed. Summary approved. Revised PC-I/DCE for Rs.200 m submitted to SOR on 08/02/2018.
No Image
Nowshera
1040
(OG)
140992-F/S, Design & Rehabilitation / Widening of Road from GT Road to Khushal Khan Khattak Mazar, Akora Khattak, Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 124.99 118.494 30 11.887 11.887 0 118.494 0 100% 95%
January - 2018
Length 8.3 Km - 8.3 Km completed. Summary approved. Revised PC-I/DCE for Rs.200 m submitted to SOR on 08/02/2018.
No Image
1040
(New)
180589-Feasibility Study on Khyber Pakhtunkhwa Rural Roads Improvement & Rehabilitation Project (JICA Assisted) (Phase-II).
Provincial
PMU
30-11--1 30-11--1 - 30-11--1 Line Deptt 10 0 5 5 0 0 0 0 - -
December - 2019
List of schemes submitted to JICA mission.
No Image
1040
(New)
180589-Feasibility Study on Khyber Pakhtunkhwa Rural Roads Improvement & Rehabilitation Project (JICA Assisted) (Phase-II).
Provincial
PMU
30-11--1 30-11--1 - 30-11--1 Line Deptt 10 0 5 5 0 0 0 0 - -
November - 2019
List of schemes submitted to JICA mission.
No Image
1040
(New)
180589-Feasibility Study on Khyber Pakhtunkhwa Rural Roads Improvement & Rehabilitation Project (JICA Assisted) (Phase-II).
Provincial
PMU
30-11--1 30-11--1 - 30-11--1 Line Deptt 10 0 5 5 0 0 0 0 - -
October - 2019
List of schemes submitted to JICA mission.
No Image
1040
(New)
180589-Feasibility Study on Khyber Pakhtunkhwa Rural Roads Improvement & Rehabilitation Project (JICA Assisted) (Phase-II).
Provincial
PMU
30-11--1 30-11--1 - 30-11--1 Line Deptt 10 0 5 5 0 0 0 0 - -
September - 2019
List of schemes submitted to JICA mission.
No Image
1040
(New)
180589-Feasibility Study on Khyber Pakhtunkhwa Rural Roads Improvement & Rehabilitation Project (JICA Assisted) (Phase-II).
Provincial
PMU
30-11--1 30-11--1 - 30-11--1 Line Deptt 10 0 5 5 0 0 0 0 - -
August - 2019
List of schemes submitted to JICA mission.
No Image
1040
(New)
180589-Feasibility Study on Khyber Pakhtunkhwa Rural Roads Improvement & Rehabilitation Project (JICA Assisted) (Phase-II).
Provincial
PMU
30-11--1 30-11--1 - 30-11--1 Line Deptt 10 0 5 5 0 0 0 0 - -
May - 2020
List of schemes submitted to JICA mission.
No Image
1040
(New)
180589-Feasibility Study on Khyber Pakhtunkhwa Rural Roads Improvement & Rehabilitation Project (JICA Assisted) (Phase-II).
Provincial
PMU
30-11--1 30-11--1 - 30-11--1 Line Deptt 10 0 5 5 0 0 0 0 - -
April - 2020
List of schemes submitted to JICA mission.
No Image
1040
(New)
180589-Feasibility Study on Khyber Pakhtunkhwa Rural Roads Improvement & Rehabilitation Project (JICA Assisted) (Phase-II).
Provincial
PMU
30-11--1 30-11--1 - 30-11--1 Line Deptt 10 0 5 5 0 0 0 0 - -
March - 2020
List of schemes submitted to JICA mission.
No Image
1040
(New)
180589-Feasibility Study on Khyber Pakhtunkhwa Rural Roads Improvement & Rehabilitation Project (JICA Assisted) (Phase-II).
Provincial
PMU
30-11--1 30-11--1 - 30-11--1 Line Deptt 10 0 5 5 0 0 0 0 - -
February - 2020
List of schemes submitted to JICA mission.
No Image
1040
(New)
180589-Feasibility Study on Khyber Pakhtunkhwa Rural Roads Improvement & Rehabilitation Project (JICA Assisted) (Phase-II).
Provincial
PMU
30-11--1 30-11--1 - 30-11--1 Line Deptt 10 0 5 5 0 0 0 0 - -
January - 2020
List of schemes submitted to JICA mission.
No Image