Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1039 (OG) |
191134-140384-Reconstruction of 24 Nos. Levy Picquets from Khajori to Miranshah in NWA. (Revised) [MA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 159.12 | 120.132 | 25.637 | 25.637 | 10 | 7.924 | 128.056 | 13.351 | 92% |
80% December - 2020 |
35- Units
completed =18
Remaining in progress. |
No Image |
1039 (OG) |
191134-140384-Reconstruction of 24 Nos. Levy Picquets from Khajori to Miranshah in NWA. (Revised) [MA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 159.12 | 120.132 | 25.637 | 25.637 | 10 | 7.924 | 128.056 | 13.351 | 92% |
80% December - 2020 |
35- Units
completed =18
Remaining in progress. |
No Image |
1039 (OG) |
191134-140384-Reconstruction of 24 Nos. Levy Picquets from Khajori to Miranshah in NWA. (Revised) [MA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 159.12 | 120.132 | 25.637 | 25.637 | 10 | 6.696 | 126.828 | 13.351 | 92% |
80% October - 2020 |
35- Units
completed =18
Remaining in progress. |
No Image |
1039 (OG) |
191134-140384-Reconstruction of 24 Nos. Levy Picquets from Khajori to Miranshah in NWA. (Revised) [MA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 159.12 | 120.132 | 25.637 | 25.637 | 10 | 6.696 | 126.828 | 13.351 | 92% |
80% September - 2020 |
35- Units
completed =18
Remaining in progress. |
No Image |
1039 (OG) |
191134-140384-Reconstruction of 24 Nos. Levy Picquets from Khajori to Miranshah in NWA. (Revised) [MA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 159.12 | 120.132 | 25.637 | 25.637 | 6 | 0 | 120.132 | 13.351 | 92% |
75% August - 2020 |
35- Units
16- Units completed.
Remaining in progress. |
No Image |
1039 (OG) |
191134-140384-Reconstruction of 24 Nos. Levy Picquets from Khajori to Miranshah in NWA. (Revised) [MA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 159.12 | 120.132 | 25.637 | 20.197 | 20.197 | 11.553 | 131.685 | 13.351 | 92% |
83% May - 2021 |
35- Units
completed =18
Remaining in progress.
Cannot be completed due to dispute on 04 units./ |
No Image |
1 Gora Qabristan Miran Shah
2 Chashma Bridge Miran Shah
3 M. Alam Jan Shaheeh Cheshma
4 Chashma II Miran Shah
5 Qutab Khel I
6 Qutab Khel II (On top of Hill)
7 Isha I
8 Isha II
9 Tapi Pir Kala
10 Aman Ullah Shaheed
11 Nowrak I
12 Nawab
13 Sarwargai
14 Aslam Picqut
15 Eidak Bridge
16 Khadi BY Pass
17 Mirashom
18 Karam Kot
19 Machi Khel Bye Pass
20 Essory
21 Jamal Azmat
22 EEPI Mirali
23 Kajori Bridge
24 Levy Picquet GHK 1
25 Levy Picquet GHK 2
26 Levy Picquet GHK 3
27 Levy Picquet GHK 4
28 Levy Picquet Eidgah
29 Levy Picquet Danday Darpa Khel
30 01 No Boye Bridge
31 01 No Thall
32 Levy Picquet 1 (Spinwam upto Bobali)
33 Levy Picquet 2 (Spinwam upo Bobali)
34 Levy Picquet Kam Sarobi
35 Levy Picquet Sara Obbo Dangin | |||||||||||||||||||
1039 (OG) |
191134-140384-Reconstruction of 24 Nos. Levy Picquets from Khajori to Miranshah in NWA. (Revised) [MA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 159.12 | 120.132 | 25.637 | 20.197 | 20.197 | 11.553 | 131.685 | 13.351 | 92% |
83% April - 2021 |
35- Units
completed =18
Remaining in progress.
Cannot be completed due to dispute on 04 units./ |
No Image |
1 Gora Qabristan Miran Shah
2 Chashma Bridge Miran Shah
3 M. Alam Jan Shaheeh Cheshma
4 Chashma II Miran Shah
5 Qutab Khel I
6 Qutab Khel II (On top of Hill)
7 Isha I
8 Isha II
9 Tapi Pir Kala
10 Aman Ullah Shaheed
11 Nowrak I
12 Nawab
13 Sarwargai
14 Aslam Picqut
15 Eidak Bridge
16 Khadi BY Pass
17 Mirashom
18 Karam Kot
19 Machi Khel Bye Pass
20 Essory
21 Jamal Azmat
22 EEPI Mirali
23 Kajori Bridge
24 Levy Picquet GHK 1
25 Levy Picquet GHK 2
26 Levy Picquet GHK 3
27 Levy Picquet GHK 4
28 Levy Picquet Eidgah
29 Levy Picquet Danday Darpa Khel
30 01 No Boye Bridge
31 01 No Thall
32 Levy Picquet 1 (Spinwam upto Bobali)
33 Levy Picquet 2 (Spinwam upo Bobali)
34 Levy Picquet Kam Sarobi
35 Levy Picquet Sara Obbo Dangin | |||||||||||||||||||
1039 (OG) |
191134-140384-Reconstruction of 24 Nos. Levy Picquets from Khajori to Miranshah in NWA. (Revised) [MA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 159.12 | 120.132 | 25.637 | 20.197 | 20.197 | 10.458 | 130.59 | 13.351 | 92% |
82% March - 2021 |
35- Units
completed =18
Remaining in progress. |
No Image |
1 Gora Qabristan Miran Shah
2 Chashma Bridge Miran Shah
3 M. Alam Jan Shaheeh Cheshma
4 Chashma II Miran Shah
5 Qutab Khel I
6 Qutab Khel II (On top of Hill)
7 Isha I
8 Isha II
9 Tapi Pir Kala
10 Aman Ullah Shaheed
11 Nowrak I
12 Nawab
13 Sarwargai
14 Aslam Picqut
15 Eidak Bridge
16 Khadi BY Pass
17 Mirashom
18 Karam Kot
19 Machi Khel Bye Pass
20 Essory
21 Jamal Azmat
22 EEPI Mirali
23 Kajori Bridge
24 Levy Picquet GHK 1
25 Levy Picquet GHK 2
26 Levy Picquet GHK 3
27 Levy Picquet GHK 4
28 Levy Picquet Eidgah
29 Levy Picquet Danday Darpa Khel
30 01 No Boye Bridge
31 01 No Thall
32 Levy Picquet 1 (Spinwam upto Bobali)
33 Levy Picquet 2 (Spinwam upo Bobali)
34 Levy Picquet Kam Sarobi
35 Levy Picquet Sara Obbo Dangin | |||||||||||||||||||
1039 (OG) |
191134-140384-Reconstruction of 24 Nos. Levy Picquets from Khajori to Miranshah in NWA. (Revised) [MA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 159.12 | 120.132 | 25.637 | 20.197 | 20.197 | 10.458 | 130.59 | 13.351 | 92% |
82% February - 2021 |
35- Units
completed =18
Remaining in progress. |
No Image |
1 Gora Qabristan Miran Shah
2 Chashma Bridge Miran Shah
3 M. Alam Jan Shaheeh Cheshma
4 Chashma II Miran Shah
5 Qutab Khel I
6 Qutab Khel II (On top of Hill)
7 Isha I
8 Isha II
9 Tapi Pir Kala
10 Aman Ullah Shaheed
11 Nowrak I
12 Nawab
13 Sarwargai
14 Aslam Picqut
15 Eidak Bridge
16 Khadi BY Pass
17 Mirashom
18 Karam Kot
19 Machi Khel Bye Pass
20 Essory
21 Jamal Azmat
22 EEPI Mirali
23 Kajori Bridge
24 Levy Picquet GHK 1
25 Levy Picquet GHK 2
26 Levy Picquet GHK 3
27 Levy Picquet GHK 4
28 Levy Picquet Eidgah
29 Levy Picquet Danday Darpa Khel
30 01 No Boye Bridge
31 01 No Thall
32 Levy Picquet 1 (Spinwam upto Bobali)
33 Levy Picquet 2 (Spinwam upo Bobali)
34 Levy Picquet Kam Sarobi
35 Levy Picquet Sara Obbo Dangin | |||||||||||||||||||
1039 (OG) |
191134-140384-Reconstruction of 24 Nos. Levy Picquets from Khajori to Miranshah in NWA. (Revised) [MA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 159.12 | 120.132 | 25.637 | 20.197 | 20.197 | 10.458 | 130.59 | 13.351 | 92% |
82% January - 2021 |
35- Units
completed =18
Remaining in progress. |
No Image |
1 Gora Qabristan Miran Shah
2 Chashma Bridge Miran Shah
3 M. Alam Jan Shaheeh Cheshma
4 Chashma II Miran Shah
5 Qutab Khel I
6 Qutab Khel II (On top of Hill)
7 Isha I
8 Isha II
9 Tapi Pir Kala
10 Aman Ullah Shaheed
11 Nowrak I
12 Nawab
13 Sarwargai
14 Aslam Picqut
15 Eidak Bridge
16 Khadi BY Pass
17 Mirashom
18 Karam Kot
19 Machi Khel Bye Pass
20 Essory
21 Jamal Azmat
22 EEPI Mirali
23 Kajori Bridge
24 Levy Picquet GHK 1
25 Levy Picquet GHK 2
26 Levy Picquet GHK 3
27 Levy Picquet GHK 4
28 Levy Picquet Eidgah
29 Levy Picquet Danday Darpa Khel
30 01 No Boye Bridge
31 01 No Thall
32 Levy Picquet 1 (Spinwam upto Bobali)
33 Levy Picquet 2 (Spinwam upo Bobali)
34 Levy Picquet Kam Sarobi
35 Levy Picquet Sara Obbo Dangin | |||||||||||||||||||
1039 (OG) |
191134-140384-Reconstruction of 24 Nos. Levy Picquets from Khajori to Miranshah in NWA. (Revised) [MA] |
North Wazirstan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 159.12 | 120.132 | 25.637 | 0 | 0 | 0 | 120.132 | 13.351 | 92% |
75% July - 2020 |
35- Units
16- Units completed.
Remaining in progress. |
No Image |
1039 (OG) |
140940-F/S, Design & Construction of RCC Bridge on Kabul River at Kashti Pul, Nowshera Cantt. |
Nowshera HW |
- | - | - | 15-09-17 | - | 369.986 | 33.934 | 37.406 | 28.055 | 27.055 | 9.436 | 43.37 | 298.646 | 19% |
12% December - 2017 |
Contract agreement sanctioned by CA. FWO mobilized. Piling/bore, girder in progress. |
No Image |
1039 (OG) |
140940-F/S, Design & Construction of RCC Bridge on Kabul River at Kashti Pul, Nowshera Cantt. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 369.986 | 33.934 | 37.406 | 28.055 | 13.279 | 9.436 | 43.37 | 298.646 | 19% |
12% November - 2017 |
Contract agreement sanctioned by CA. FWO mobilized. Piling/bore, girder in progress. |
No Image |
1039 (OG) |
140940-F/S, Design & Construction of RCC Bridge on Kabul River at Kashti Pul, Nowshera Cantt. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 369.986 | 33.934 | 37.406 | 37.406 | 13.279 | 0 | 33.934 | 298.646 | 19% |
9% October - 2017 |
Contract agreement sanctioned by CA. FWO mobilized. Piling/bore, girder in progress. |
No Image |
1039 (OG) |
140940-F/S, Design & Construction of RCC Bridge on Kabul River at Kashti Pul, Nowshera Cantt. |
Nowshera HW |
- | - | - | 28-01-15 | - | 370 | 33.934 | 37.406 | 37.406 | 13.279 | 0 | 33.934 | 298.66 | 19% |
9% September - 2017 |
Contract agreement sanctioned by CA. FWO mobilized. Piling/bore, girder in progress. |
No Image |
1039 (OG) |
140940-F/S, Design & Construction of RCC Bridge on Kabul River at Kashti Pul, Nowshera Cantt. |
Nowshera HW |
- | - | - | 28-01-15 | - | 166.812 | 33.934 | 37.406 | 37.406 | 13.279 | 0 | 33.934 | 95.472 | 43% |
20% August - 2017 |
Contract agreement sanctioned by CA. FWO mobilized. Piling/bore, girder casting in progress. Revised PC-I/DCE for Rs.370 m submitted to SOR on 18/07/2017. |
No Image |
1039 (OG) |
140940-F/S, Design & Construction of RCC Bridge on Kabul River at Kashti Pul, Nowshera Cantt. |
Nowshera HW |
- | - | - | 28-01-15 | - | 166.812 | 33.934 | 37.406 | 37.406 | 13.279 | 0 | 33.934 | 95.472 | 43% |
20% July - 2017 |
Contract agreement sanctioned by CA. FWO mobilized. Piling/bore, girder casting in progress. Revised PC-I/DCE for Rs.370 m submitted to SOR on 18/07/2017. |
No Image |
1039 (OG) |
140940-F/S, Design & Construction of RCC Bridge on Kabul River at Kashti Pul, Nowshera Cantt. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 369.986 | 33.933 | 37.406 | 91.782 | 91.782 | 80.505 | 114.438 | 298.647 | 19% |
31% June - 2018 |
Contract agreement sanctioned by CA. FWO mobilized. 60% work completed. |
No Image |
Nowshera | |||||||||||||||||||
1039 (OG) |
140940-F/S, Design & Construction of RCC Bridge on Kabul River at Kashti Pul, Nowshera Cantt. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 369.986 | 33.933 | 37.406 | 91.782 | 91.782 | 79.294 | 113.227 | 298.647 | 19% |
31% May - 2018 |
Contract agreement sanctioned by CA. FWO mobilized. 60% work completed. |
No Image |
Nowshera | |||||||||||||||||||
1039 (OG) |
140940-F/S, Design & Construction of RCC Bridge on Kabul River at Kashti Pul, Nowshera Cantt. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 369.986 | 33.933 | 37.406 | 91.782 | 91.782 | 79.294 | 113.227 | 298.647 | 19% |
31% April - 2018 |
Contract agreement sanctioned by CA. FWO mobilized. 60% work completed. |
No Image |
Nowshera | |||||||||||||||||||
1039 (OG) |
140940-F/S, Design & Construction of RCC Bridge on Kabul River at Kashti Pul, Nowshera Cantt. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 369.986 | 33.933 | 37.406 | 91.782 | 91.782 | 67.311 | 101.244 | 298.647 | 19% |
27% March - 2018 |
Contract agreement sanctioned by CA. FWO mobilized. 60% work completed. |
No Image |
Nowshera | |||||||||||||||||||
1039 (OG) |
140940-F/S, Design & Construction of RCC Bridge on Kabul River at Kashti Pul, Nowshera Cantt. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 369.986 | 33.933 | 37.406 | 54.092 | 54.092 | 11.456 | 45.389 | 298.647 | 19% |
12% February - 2018 |
Contract agreement sanctioned by CA. FWO mobilized. 60% work completed. |
No Image |
Nowshera | |||||||||||||||||||
1039 (OG) |
140940-F/S, Design & Construction of RCC Bridge on Kabul River at Kashti Pul, Nowshera Cantt. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 369.986 | 33.934 | 37.406 | 54.092 | 54.092 | 9.436 | 43.37 | 298.646 | 19% |
12% January - 2018 |
Contract agreement sanctioned by CA. FWO mobilized. 60% work completed. |
No Image |
1039 (OG) |
160248-Project Implementation Unit (PIU) ADB Assisted "Provincial Road Rehabilitation Project". |
Peshawar PRIP |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59.318 | 18.525 | 5 | 5 | 3.75 | 0 | 18.525 | 35.793 | 40% |
31% April - 2019 |
PIU setup, staff deputed. |
No Image |
1039 (OG) |
160248-Project Implementation Unit (PIU) ADB Assisted "Provincial Road Rehabilitation Project". |
Peshawar PRIP |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59.318 | 18.525 | 5 | 5 | 3.75 | 0 | 18.525 | 35.793 | 40% |
31% March - 2019 |
PIU setup, staff deputed. |
No Image |
1039 (OG) |
160248-Project Implementation Unit (PIU) ADB Assisted "Provincial Road Rehabilitation Project". |
Peshawar PRIP |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59.318 | 18.525 | 5 | 5 | 3.75 | 0 | 18.525 | 35.793 | 40% |
31% March - 2019 |
PIU setup, staff deputed. |
No Image |
1039 (OG) |
160248-Project Implementation Unit (PIU) ADB Assisted "Provincial Road Rehabilitation Project". |
Peshawar PRIP |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59.318 | 18.525 | 5 | 5 | 3.75 | 0 | 18.525 | 35.793 | 40% |
31% February - 2019 |
PIU setup, staff deputed. |
No Image |
1039 (OG) |
160248-Project Implementation Unit (PIU) ADB Assisted "Provincial Road Rehabilitation Project". |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59.318 | 18.525 | 5 | 5 | 3.75 | 0 | 18.525 | 35.793 | 40% |
31% November - 2018 |
PIU setup, staff deputed. Revised AA approved. |
No Image |
1039 (OG) |
160248-Project Implementation Unit (PIU) ADB Assisted "Provincial Road Rehabilitation Project". |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59.318 | 18.525 | 5 | 5 | 3.75 | 0 | 18.525 | 35.793 | 40% |
31% November - 2018 |
PIU setup, staff deputed. Revised AA approved. |
No Image |
1039 (OG) |
160248-Project Implementation Unit (PIU) ADB Assisted "Provincial Road Rehabilitation Project". |
Provincial PRIP |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59.318 | 18.525 | 5 | 5 | 3.75 | 0 | 18.525 | 35.793 | 40% |
31% December - 2018 |
PIU setup, staff deputed. Revised AA approved. |
No Image |
1039 (New) |
180462-F/S for Khyber Pakhtunkhwa Roads Network (Master Plan). |
Provincial PRIP |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 20 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- December - 2019 |
Placed on agenda of steering committee |
No Image |
1039 (New) |
180462-F/S for Khyber Pakhtunkhwa Roads Network (Master Plan). |
Provincial PRIP |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 20 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- November - 2019 |
Placed on agenda of steering committee |
No Image |
1039 (New) |
180462-F/S for Khyber Pakhtunkhwa Roads Network (Master Plan). |
Provincial PRIP |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 20 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- October - 2019 |
Placed on agenda of steering committee |
No Image |
1039 (New) |
180462-F/S for Khyber Pakhtunkhwa Roads Network (Master Plan). |
Provincial PRIP |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 20 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- September - 2019 |
Placed on agenda of steering committee |
No Image |
1039 (New) |
180462-F/S for Khyber Pakhtunkhwa Roads Network (Master Plan). |
Provincial PRIP |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 20 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- August - 2019 |
Placed on agenda of steering committee |
No Image |
1039 (New) |
180462-F/S for Khyber Pakhtunkhwa Roads Network (Master Plan). |
Provincial PRIP |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 20 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- May - 2020 |
Placed on agenda of steering committee |
No Image |
1039 (New) |
180462-F/S for Khyber Pakhtunkhwa Roads Network (Master Plan). |
Provincial PRIP |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 20 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- April - 2020 |
Placed on agenda of steering committee |
No Image |
1039 (New) |
180462-F/S for Khyber Pakhtunkhwa Roads Network (Master Plan). |
Provincial PRIP |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 20 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- March - 2020 |
Placed on agenda of steering committee |
No Image |
1039 (New) |
180462-F/S for Khyber Pakhtunkhwa Roads Network (Master Plan). |
Provincial PRIP |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 20 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- February - 2020 |
Placed on agenda of steering committee |
No Image |
1039 (OG) |
160248-Project Implementation Unit (PIU) ADB Assisted "Provincial Road Rehabilitation Project". |
Provincial PRIP |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59.318 | 18.525 | 5 | 5 | 3.75 | 0 | 18.525 | 35.793 | 40% |
31% January - 2019 |
PIU setup, staff deputed. |
No Image |
1039 (New) |
180462-F/S for Khyber Pakhtunkhwa Roads Network (Master Plan). |
Provincial PRIP |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 20 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- January - 2020 |
Placed on agenda of steering committee |
No Image |
Pages : 1 |