Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2018, January - 2019, January - 2020, January - 2021, February - 2021, February - 2018, February - 2019, February - 2020, March - 2021, March - 2018, March - 2019, March - 2020, April - 2021, April - 2018, April - 2019, April - 2020, May - 2021, May - 2018, May - 2020, June - 2018, July - 2020, July - 2017, August - 2019, August - 2020, August - 2017, September - 2017, September - 2019, September - 2020, October - 2017, October - 2019, October - 2020, November - 2017, November - 2018, November - 2019, December - 2017, December - 2018, December - 2019, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1039
(OG)
191134-140384-Reconstruction of 24 Nos. Levy Picquets from Khajori to Miranshah in NWA. (Revised) [MA]
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 159.12 120.132 25.637 25.637 10 7.924 128.056 13.351 92% 80%
December - 2020
35- Units completed =18 Remaining in progress.
No Image
1039
(OG)
191134-140384-Reconstruction of 24 Nos. Levy Picquets from Khajori to Miranshah in NWA. (Revised) [MA]
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 159.12 120.132 25.637 25.637 10 7.924 128.056 13.351 92% 80%
December - 2020
35- Units completed =18 Remaining in progress.
No Image
1039
(OG)
191134-140384-Reconstruction of 24 Nos. Levy Picquets from Khajori to Miranshah in NWA. (Revised) [MA]
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 159.12 120.132 25.637 25.637 10 6.696 126.828 13.351 92% 80%
October - 2020
35- Units completed =18 Remaining in progress.
No Image
1039
(OG)
191134-140384-Reconstruction of 24 Nos. Levy Picquets from Khajori to Miranshah in NWA. (Revised) [MA]
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 159.12 120.132 25.637 25.637 10 6.696 126.828 13.351 92% 80%
September - 2020
35- Units completed =18 Remaining in progress.
No Image
1039
(OG)
191134-140384-Reconstruction of 24 Nos. Levy Picquets from Khajori to Miranshah in NWA. (Revised) [MA]
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 159.12 120.132 25.637 25.637 6 0 120.132 13.351 92% 75%
August - 2020
35- Units 16- Units completed. Remaining in progress.
No Image
1039
(OG)
191134-140384-Reconstruction of 24 Nos. Levy Picquets from Khajori to Miranshah in NWA. (Revised) [MA]
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 159.12 120.132 25.637 20.197 20.197 11.553 131.685 13.351 92% 83%
May - 2021
35- Units completed =18 Remaining in progress. Cannot be completed due to dispute on 04 units./
No Image
1 Gora Qabristan Miran Shah  
2 Chashma Bridge Miran Shah
3 M. Alam Jan Shaheeh Cheshma
4 Chashma II Miran Shah
5 Qutab Khel I
6 Qutab Khel II (On top of  Hill)
7 Isha I
8 Isha II
9 Tapi Pir Kala
10 Aman Ullah Shaheed
11 Nowrak I
12 Nawab
13 Sarwargai
14 Aslam Picqut
15 Eidak Bridge
16 Khadi BY Pass
17 Mirashom
18 Karam Kot
19 Machi Khel Bye Pass
20 Essory
21 Jamal Azmat
22 EEPI Mirali
23 Kajori Bridge
24 Levy Picquet GHK 1
25 Levy Picquet GHK 2
26 Levy Picquet GHK 3
27 Levy Picquet GHK 4
28 Levy Picquet Eidgah
29 Levy Picquet Danday Darpa Khel
30 01 No Boye Bridge
31 01 No Thall
32 Levy Picquet 1 (Spinwam upto Bobali)
33 Levy Picquet 2 (Spinwam upo Bobali)
34 Levy Picquet Kam Sarobi
35 Levy Picquet Sara Obbo Dangin
1039
(OG)
191134-140384-Reconstruction of 24 Nos. Levy Picquets from Khajori to Miranshah in NWA. (Revised) [MA]
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 159.12 120.132 25.637 20.197 20.197 11.553 131.685 13.351 92% 83%
April - 2021
35- Units completed =18 Remaining in progress. Cannot be completed due to dispute on 04 units./
No Image
1 Gora Qabristan Miran Shah  
2 Chashma Bridge Miran Shah
3 M. Alam Jan Shaheeh Cheshma
4 Chashma II Miran Shah
5 Qutab Khel I
6 Qutab Khel II (On top of  Hill)
7 Isha I
8 Isha II
9 Tapi Pir Kala
10 Aman Ullah Shaheed
11 Nowrak I
12 Nawab
13 Sarwargai
14 Aslam Picqut
15 Eidak Bridge
16 Khadi BY Pass
17 Mirashom
18 Karam Kot
19 Machi Khel Bye Pass
20 Essory
21 Jamal Azmat
22 EEPI Mirali
23 Kajori Bridge
24 Levy Picquet GHK 1
25 Levy Picquet GHK 2
26 Levy Picquet GHK 3
27 Levy Picquet GHK 4
28 Levy Picquet Eidgah
29 Levy Picquet Danday Darpa Khel
30 01 No Boye Bridge
31 01 No Thall
32 Levy Picquet 1 (Spinwam upto Bobali)
33 Levy Picquet 2 (Spinwam upo Bobali)
34 Levy Picquet Kam Sarobi
35 Levy Picquet Sara Obbo Dangin
1039
(OG)
191134-140384-Reconstruction of 24 Nos. Levy Picquets from Khajori to Miranshah in NWA. (Revised) [MA]
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 159.12 120.132 25.637 20.197 20.197 10.458 130.59 13.351 92% 82%
March - 2021
35- Units completed =18 Remaining in progress.
No Image
1 Gora Qabristan Miran Shah  
2 Chashma Bridge Miran Shah
3 M. Alam Jan Shaheeh Cheshma
4 Chashma II Miran Shah
5 Qutab Khel I
6 Qutab Khel II (On top of  Hill)
7 Isha I
8 Isha II
9 Tapi Pir Kala
10 Aman Ullah Shaheed
11 Nowrak I
12 Nawab
13 Sarwargai
14 Aslam Picqut
15 Eidak Bridge
16 Khadi BY Pass
17 Mirashom
18 Karam Kot
19 Machi Khel Bye Pass
20 Essory
21 Jamal Azmat
22 EEPI Mirali
23 Kajori Bridge
24 Levy Picquet GHK 1
25 Levy Picquet GHK 2
26 Levy Picquet GHK 3
27 Levy Picquet GHK 4
28 Levy Picquet Eidgah
29 Levy Picquet Danday Darpa Khel
30 01 No Boye Bridge
31 01 No Thall
32 Levy Picquet 1 (Spinwam upto Bobali)
33 Levy Picquet 2 (Spinwam upo Bobali)
34 Levy Picquet Kam Sarobi
35 Levy Picquet Sara Obbo Dangin
1039
(OG)
191134-140384-Reconstruction of 24 Nos. Levy Picquets from Khajori to Miranshah in NWA. (Revised) [MA]
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 159.12 120.132 25.637 20.197 20.197 10.458 130.59 13.351 92% 82%
February - 2021
35- Units completed =18 Remaining in progress.
No Image
1 Gora Qabristan Miran Shah  
2 Chashma Bridge Miran Shah
3 M. Alam Jan Shaheeh Cheshma
4 Chashma II Miran Shah
5 Qutab Khel I
6 Qutab Khel II (On top of  Hill)
7 Isha I
8 Isha II
9 Tapi Pir Kala
10 Aman Ullah Shaheed
11 Nowrak I
12 Nawab
13 Sarwargai
14 Aslam Picqut
15 Eidak Bridge
16 Khadi BY Pass
17 Mirashom
18 Karam Kot
19 Machi Khel Bye Pass
20 Essory
21 Jamal Azmat
22 EEPI Mirali
23 Kajori Bridge
24 Levy Picquet GHK 1
25 Levy Picquet GHK 2
26 Levy Picquet GHK 3
27 Levy Picquet GHK 4
28 Levy Picquet Eidgah
29 Levy Picquet Danday Darpa Khel
30 01 No Boye Bridge
31 01 No Thall
32 Levy Picquet 1 (Spinwam upto Bobali)
33 Levy Picquet 2 (Spinwam upo Bobali)
34 Levy Picquet Kam Sarobi
35 Levy Picquet Sara Obbo Dangin
1039
(OG)
191134-140384-Reconstruction of 24 Nos. Levy Picquets from Khajori to Miranshah in NWA. (Revised) [MA]
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 159.12 120.132 25.637 20.197 20.197 10.458 130.59 13.351 92% 82%
January - 2021
35- Units completed =18 Remaining in progress.
No Image
1 Gora Qabristan Miran Shah  
2 Chashma Bridge Miran Shah
3 M. Alam Jan Shaheeh Cheshma
4 Chashma II Miran Shah
5 Qutab Khel I
6 Qutab Khel II (On top of  Hill)
7 Isha I
8 Isha II
9 Tapi Pir Kala
10 Aman Ullah Shaheed
11 Nowrak I
12 Nawab
13 Sarwargai
14 Aslam Picqut
15 Eidak Bridge
16 Khadi BY Pass
17 Mirashom
18 Karam Kot
19 Machi Khel Bye Pass
20 Essory
21 Jamal Azmat
22 EEPI Mirali
23 Kajori Bridge
24 Levy Picquet GHK 1
25 Levy Picquet GHK 2
26 Levy Picquet GHK 3
27 Levy Picquet GHK 4
28 Levy Picquet Eidgah
29 Levy Picquet Danday Darpa Khel
30 01 No Boye Bridge
31 01 No Thall
32 Levy Picquet 1 (Spinwam upto Bobali)
33 Levy Picquet 2 (Spinwam upo Bobali)
34 Levy Picquet Kam Sarobi
35 Levy Picquet Sara Obbo Dangin
1039
(OG)
191134-140384-Reconstruction of 24 Nos. Levy Picquets from Khajori to Miranshah in NWA. (Revised) [MA]
North Wazirstan
30-11--1 30-11--1 - 30-11--1 - 159.12 120.132 25.637 0 0 0 120.132 13.351 92% 75%
July - 2020
35- Units 16- Units completed. Remaining in progress.
No Image
1039
(OG)
140940-F/S, Design & Construction of RCC Bridge on Kabul River at Kashti Pul, Nowshera Cantt.
Nowshera
HW
- - - 15-09-17 - 369.986 33.934 37.406 28.055 27.055 9.436 43.37 298.646 19% 12%
December - 2017
Contract agreement sanctioned by CA. FWO mobilized. Piling/bore, girder in progress.
No Image
1039
(OG)
140940-F/S, Design & Construction of RCC Bridge on Kabul River at Kashti Pul, Nowshera Cantt.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 369.986 33.934 37.406 28.055 13.279 9.436 43.37 298.646 19% 12%
November - 2017
Contract agreement sanctioned by CA. FWO mobilized. Piling/bore, girder in progress.
No Image
1039
(OG)
140940-F/S, Design & Construction of RCC Bridge on Kabul River at Kashti Pul, Nowshera Cantt.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 369.986 33.934 37.406 37.406 13.279 0 33.934 298.646 19% 9%
October - 2017
Contract agreement sanctioned by CA. FWO mobilized. Piling/bore, girder in progress.
No Image
1039
(OG)
140940-F/S, Design & Construction of RCC Bridge on Kabul River at Kashti Pul, Nowshera Cantt.
Nowshera
HW
- - - 28-01-15 - 370 33.934 37.406 37.406 13.279 0 33.934 298.66 19% 9%
September - 2017
Contract agreement sanctioned by CA. FWO mobilized. Piling/bore, girder in progress.
No Image
1039
(OG)
140940-F/S, Design & Construction of RCC Bridge on Kabul River at Kashti Pul, Nowshera Cantt.
Nowshera
HW
- - - 28-01-15 - 166.812 33.934 37.406 37.406 13.279 0 33.934 95.472 43% 20%
August - 2017
Contract agreement sanctioned by CA. FWO mobilized. Piling/bore, girder casting in progress. Revised PC-I/DCE for Rs.370 m submitted to SOR on 18/07/2017.
No Image
1039
(OG)
140940-F/S, Design & Construction of RCC Bridge on Kabul River at Kashti Pul, Nowshera Cantt.
Nowshera
HW
- - - 28-01-15 - 166.812 33.934 37.406 37.406 13.279 0 33.934 95.472 43% 20%
July - 2017
Contract agreement sanctioned by CA. FWO mobilized. Piling/bore, girder casting in progress. Revised PC-I/DCE for Rs.370 m submitted to SOR on 18/07/2017.
No Image
1039
(OG)
140940-F/S, Design & Construction of RCC Bridge on Kabul River at Kashti Pul, Nowshera Cantt.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 369.986 33.933 37.406 91.782 91.782 80.505 114.438 298.647 19% 31%
June - 2018
Contract agreement sanctioned by CA. FWO mobilized. 60% work completed.
No Image
Nowshera
1039
(OG)
140940-F/S, Design & Construction of RCC Bridge on Kabul River at Kashti Pul, Nowshera Cantt.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 369.986 33.933 37.406 91.782 91.782 79.294 113.227 298.647 19% 31%
May - 2018
Contract agreement sanctioned by CA. FWO mobilized. 60% work completed.
No Image
Nowshera
1039
(OG)
140940-F/S, Design & Construction of RCC Bridge on Kabul River at Kashti Pul, Nowshera Cantt.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 369.986 33.933 37.406 91.782 91.782 79.294 113.227 298.647 19% 31%
April - 2018
Contract agreement sanctioned by CA. FWO mobilized. 60% work completed.
No Image
Nowshera
1039
(OG)
140940-F/S, Design & Construction of RCC Bridge on Kabul River at Kashti Pul, Nowshera Cantt.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 369.986 33.933 37.406 91.782 91.782 67.311 101.244 298.647 19% 27%
March - 2018
Contract agreement sanctioned by CA. FWO mobilized. 60% work completed.
No Image
Nowshera
1039
(OG)
140940-F/S, Design & Construction of RCC Bridge on Kabul River at Kashti Pul, Nowshera Cantt.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 369.986 33.933 37.406 54.092 54.092 11.456 45.389 298.647 19% 12%
February - 2018
Contract agreement sanctioned by CA. FWO mobilized. 60% work completed.
No Image
Nowshera
1039
(OG)
140940-F/S, Design & Construction of RCC Bridge on Kabul River at Kashti Pul, Nowshera Cantt.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 369.986 33.934 37.406 54.092 54.092 9.436 43.37 298.646 19% 12%
January - 2018
Contract agreement sanctioned by CA. FWO mobilized. 60% work completed.
No Image
1039
(OG)
160248-Project Implementation Unit (PIU) ADB Assisted "Provincial Road Rehabilitation Project".
Peshawar
PRIP
30-11--1 30-11--1 - 30-11--1 - 59.318 18.525 5 5 3.75 0 18.525 35.793 40% 31%
April - 2019
PIU setup, staff deputed.
No Image
1039
(OG)
160248-Project Implementation Unit (PIU) ADB Assisted "Provincial Road Rehabilitation Project".
Peshawar
PRIP
30-11--1 30-11--1 - 30-11--1 - 59.318 18.525 5 5 3.75 0 18.525 35.793 40% 31%
March - 2019
PIU setup, staff deputed.
No Image
1039
(OG)
160248-Project Implementation Unit (PIU) ADB Assisted "Provincial Road Rehabilitation Project".
Peshawar
PRIP
30-11--1 30-11--1 - 30-11--1 - 59.318 18.525 5 5 3.75 0 18.525 35.793 40% 31%
March - 2019
PIU setup, staff deputed.
No Image
1039
(OG)
160248-Project Implementation Unit (PIU) ADB Assisted "Provincial Road Rehabilitation Project".
Peshawar
PRIP
30-11--1 30-11--1 - 30-11--1 - 59.318 18.525 5 5 3.75 0 18.525 35.793 40% 31%
February - 2019
PIU setup, staff deputed.
No Image
1039
(OG)
160248-Project Implementation Unit (PIU) ADB Assisted "Provincial Road Rehabilitation Project".
Provincial
PKHA
30-11--1 30-11--1 - 30-11--1 - 59.318 18.525 5 5 3.75 0 18.525 35.793 40% 31%
November - 2018
PIU setup, staff deputed. Revised AA approved.
No Image
1039
(OG)
160248-Project Implementation Unit (PIU) ADB Assisted "Provincial Road Rehabilitation Project".
Provincial
PKHA
30-11--1 30-11--1 - 30-11--1 - 59.318 18.525 5 5 3.75 0 18.525 35.793 40% 31%
November - 2018
PIU setup, staff deputed. Revised AA approved.
No Image
1039
(OG)
160248-Project Implementation Unit (PIU) ADB Assisted "Provincial Road Rehabilitation Project".
Provincial
PRIP
30-11--1 30-11--1 - 30-11--1 - 59.318 18.525 5 5 3.75 0 18.525 35.793 40% 31%
December - 2018
PIU setup, staff deputed. Revised AA approved.
No Image
1039
(New)
180462-F/S for Khyber Pakhtunkhwa Roads Network (Master Plan).
Provincial
PRIP
30-11--1 30-11--1 - 30-11--1 Line Deptt 20 0 10 10 0 0 0 0 - -
December - 2019
Placed on agenda of steering committee
No Image
1039
(New)
180462-F/S for Khyber Pakhtunkhwa Roads Network (Master Plan).
Provincial
PRIP
30-11--1 30-11--1 - 30-11--1 Line Deptt 20 0 10 10 0 0 0 0 - -
November - 2019
Placed on agenda of steering committee
No Image
1039
(New)
180462-F/S for Khyber Pakhtunkhwa Roads Network (Master Plan).
Provincial
PRIP
30-11--1 30-11--1 - 30-11--1 Line Deptt 20 0 10 10 0 0 0 0 - -
October - 2019
Placed on agenda of steering committee
No Image
1039
(New)
180462-F/S for Khyber Pakhtunkhwa Roads Network (Master Plan).
Provincial
PRIP
30-11--1 30-11--1 - 30-11--1 Line Deptt 20 0 10 10 0 0 0 0 - -
September - 2019
Placed on agenda of steering committee
No Image
1039
(New)
180462-F/S for Khyber Pakhtunkhwa Roads Network (Master Plan).
Provincial
PRIP
30-11--1 30-11--1 - 30-11--1 Line Deptt 20 0 10 10 0 0 0 0 - -
August - 2019
Placed on agenda of steering committee
No Image
1039
(New)
180462-F/S for Khyber Pakhtunkhwa Roads Network (Master Plan).
Provincial
PRIP
30-11--1 30-11--1 - 30-11--1 Line Deptt 20 0 10 10 0 0 0 0 - -
May - 2020
Placed on agenda of steering committee
No Image
1039
(New)
180462-F/S for Khyber Pakhtunkhwa Roads Network (Master Plan).
Provincial
PRIP
30-11--1 30-11--1 - 30-11--1 Line Deptt 20 0 10 10 0 0 0 0 - -
April - 2020
Placed on agenda of steering committee
No Image
1039
(New)
180462-F/S for Khyber Pakhtunkhwa Roads Network (Master Plan).
Provincial
PRIP
30-11--1 30-11--1 - 30-11--1 Line Deptt 20 0 10 10 0 0 0 0 - -
March - 2020
Placed on agenda of steering committee
No Image
1039
(New)
180462-F/S for Khyber Pakhtunkhwa Roads Network (Master Plan).
Provincial
PRIP
30-11--1 30-11--1 - 30-11--1 Line Deptt 20 0 10 10 0 0 0 0 - -
February - 2020
Placed on agenda of steering committee
No Image
1039
(OG)
160248-Project Implementation Unit (PIU) ADB Assisted "Provincial Road Rehabilitation Project".
Provincial
PRIP
30-11--1 30-11--1 - 30-11--1 - 59.318 18.525 5 5 3.75 0 18.525 35.793 40% 31%
January - 2019
PIU setup, staff deputed.
No Image
1039
(New)
180462-F/S for Khyber Pakhtunkhwa Roads Network (Master Plan).
Provincial
PRIP
30-11--1 30-11--1 - 30-11--1 Line Deptt 20 0 10 10 0 0 0 0 - -
January - 2020
Placed on agenda of steering committee
No Image
Pages : 1