Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1038 (OG) |
191124-160177-Reconstruction, Rehabilitation and Provision of missing Facilities, Logistics and Equipments in existing Levies Lines & Construction of Levies Barracks in NWA. [MA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 80.145 | 69.365 | 11.765 | 11.765 | 6 | 2.737 | 72.102 | 0 | 100% |
90% October - 2020 |
03- Units
Work in progress. |
No Image |
1- Tehsil Miranshah. Reconstn/Rehab
2- Rehab: Leavey Line Mirali
3- Provision of logistics Equipments | |||||||||||||||||||
1038 (OG) |
191124-160177-Reconstruction, Rehabilitation and Provision of missing Facilities, Logistics and Equipments in existing Levies Lines & Construction of Levies Barracks in NWA. [MA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 80.145 | 69.365 | 11.765 | 11.765 | 6 | 2.737 | 72.102 | 0 | 100% |
90% September - 2020 |
03- Units
Work in progress. |
No Image |
1- Tehsil Miranshah. Reconstn/Rehab
2- Rehab: Leavey Line Mirali
3- Provision of logistics Equipments | |||||||||||||||||||
1038 (OG) |
191124-160177-Reconstruction, Rehabilitation and Provision of missing Facilities, Logistics and Equipments in existing Levies Lines & Construction of Levies Barracks in NWA. [MA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 80.145 | 69.365 | 11.765 | 11.765 | 6 | 0 | 69.365 | 0 | 100% |
87% August - 2020 |
03- Units
Work in progress. |
No Image |
1- Tehsil Miranshah. Reconstn/Rehab
2- Rehab: Leavey Line Mirali
3- Provision of logistics Equipments | |||||||||||||||||||
1038 (OG) |
191124-160177-Reconstruction, Rehabilitation and Provision of missing Facilities, Logistics and Equipments in existing Levies Lines & Construction of Levies Barracks in NWA. [MA] |
North Wazirstan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 80.145 | 69.365 | 11.765 | 0 | 0 | 0 | 69.365 | 0 | 100% |
87% July - 2020 |
03- Units
Work in progress. |
No Image |
1- Tehsil Miranshah. Reconstn/Rehab
2- Rehab: Leavey Line Mirali
3- Provision of logistics Equipments | |||||||||||||||||||
1038 (OG) |
140939-F/S & Construction of (a) Bakhtai-Kottli Khurd-Kottli Kalan road i/c Bridges (b) road from Cherat road to Spinkhak Village, Nowshera. |
Nowshera HW |
16-03-15 | - | - | 26-09-17 | - | 400 | 182.999 | 100 | 25 | 25 | 21.898 | 204.897 | 117.001 | 71% |
51% December - 2017 |
Length 6.7 Km - completed (original scope). Revised scope - work started. |
No Image |
1038 (OG) |
140939-F/S & Construction of (a) Bakhtai-Kottli Khurd-Kottli Kalan road i/c Bridges (b) road from Cherat road to Spinkhak Village, Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 182.999 | 100 | 85 | 20.5 | 17.398 | 200.397 | 117.001 | 71% |
50% November - 2017 |
Length 6.7 Km - completed (original scope). Revised scope tender approval under process. |
No Image |
1038 (OG) |
140939-F/S & Construction of (a) Bakhtai-Kottli Khurd-Kottli Kalan road i/c Bridges (b) road from Cherat road to Spinkhak Village, Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 182.999 | 100 | 100 | 20.5 | 20.5 | 203.499 | 117.001 | 71% |
51% October - 2017 |
Length 6.7 Km - completed (original scope). Revised scope tender approval under process. |
No Image |
1038 (OG) |
140939-F/S & Construction of (a) Bakhtai-Kottli Khurd-Kottli Kalan road i/c Bridges (b) road from Cherat road to Spinkhak Village, Nowshera. |
Nowshera HW |
16-03-15 | - | - | 19-11-14 | - | 400 | 182.999 | 100 | 100 | 35.5 | 4.185 | 187.184 | 117.001 | 71% |
47% September - 2017 |
Length 6.7 Km - earth work 100%, sub base 6.5 Km, WBM 6.5 Km, WC 6.5 Km, structure work 90% completed. Bridge (80 mtr) completed. Tender floated for additional work, opening on 01/11/2017. |
No Image |
1038 (OG) |
140939-F/S & Construction of (a) Bakhtai-Kottli Khurd-Kottli Kalan road i/c Bridges (b) road from Cherat road to Spinkhak Village, Nowshera. |
Nowshera HW |
16-03-15 | - | - | 19-11-14 | - | 199.992 | 182.999 | 100 | 100 | 35.5 | 4.185 | 187.184 | 0 | 100% |
94% August - 2017 |
Length 6.7 Km - earth work 100%, sub base 6.5 Km, WBM 6.5 Km, WC 6.5 Km, structure work 90% completed. Bridge (80 mtr) completed. Revised PC-I/DCE for Rs.400 m submitted to SOR on 01/08/2017. |
No Image |
1038 (OG) |
140939-F/S & Construction of (a) Bakhtai-Kottli Khurd-Kottli Kalan road i/c Bridges (b) road from Cherat road to Spinkhak Village, Nowshera. |
Nowshera HW |
16-03-15 | - | - | 19-11-14 | - | 199.992 | 182.999 | 100 | 100 | 35.5 | 0 | 182.999 | 0 | 100% |
92% July - 2017 |
Length 6.7 Km - earth work 100%, sub base 6.5 Km, WBM 6.5 Km, WC 6.5 Km, structure work 90% completed. Bridge (80 mtr) completed. Revised PC-I/DCE for Rs.400 m submitted to SOR on 01/08/2017. |
No Image |
1038 (OG) |
140939-F/S & Construction of (a) Bakhtai-Kottli Khurd-Kottli Kalan road i/c Bridges (b) road from Cherat road to Spinkhak Village, Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 183.001 | 100 | 37.836 | 37.836 | 37.836 | 220.837 | 116.999 | 71% |
55% June - 2018 |
Length 6.7 Km - completed (original scope). Revised scope - work started. |
No Image |
Nowshera | |||||||||||||||||||
1038 (OG) |
140939-F/S & Construction of (a) Bakhtai-Kottli Khurd-Kottli Kalan road i/c Bridges (b) road from Cherat road to Spinkhak Village, Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 183.001 | 100 | 37.836 | 37.836 | 37.836 | 220.837 | 116.999 | 71% |
55% May - 2018 |
Length 6.7 Km - completed (original scope). Revised scope - work started. |
No Image |
Nowshera | |||||||||||||||||||
1038 (OG) |
140939-F/S & Construction of (a) Bakhtai-Kottli Khurd-Kottli Kalan road i/c Bridges (b) road from Cherat road to Spinkhak Village, Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 183.001 | 100 | 37.836 | 37.836 | 35.483 | 218.484 | 116.999 | 71% |
55% April - 2018 |
Length 6.7 Km - completed (original scope). Revised scope - work started. |
No Image |
Nowshera | |||||||||||||||||||
1038 (OG) |
140939-F/S & Construction of (a) Bakhtai-Kottli Khurd-Kottli Kalan road i/c Bridges (b) road from Cherat road to Spinkhak Village, Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 183.001 | 100 | 37.83 | 37.83 | 35.483 | 218.484 | 116.999 | 71% |
55% March - 2018 |
Length 6.7 Km - completed (original scope). Revised scope - work started. |
No Image |
Nowshera | |||||||||||||||||||
1038 (OG) |
140939-F/S & Construction of (a) Bakhtai-Kottli Khurd-Kottli Kalan road i/c Bridges (b) road from Cherat road to Spinkhak Village, Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 183.001 | 100 | 59.146 | 59.146 | 22.161 | 205.162 | 116.999 | 71% |
51% February - 2018 |
Length 6.7 Km - completed (original scope). Revised scope - work started. |
No Image |
Nowshera | |||||||||||||||||||
1038 (OG) |
140939-F/S & Construction of (a) Bakhtai-Kottli Khurd-Kottli Kalan road i/c Bridges (b) road from Cherat road to Spinkhak Village, Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 182.999 | 100 | 59.146 | 59.146 | 22.161 | 205.16 | 117.001 | 71% |
51% January - 2018 |
Length 6.7 Km - completed (original scope). Revised scope - work started. |
No Image |
1038 (OG) |
180162-Special Repair & Maintenance of identified Provincial Highways through Perofrmance Based Maintenance (PBM) Pilot Project under Provincial Roads Improvement Project (ADB Assisted) |
Provincial PRIP |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1250 | 0 | 10 | 0.0005 | 0.0005 | 0 | 0 | 0 | - |
- December - 2019 |
Pc-I /Dce submitted to PDWP Rs. 1250 M . Approval Awaited. |
No Image |
1038 (OG) |
180162-Special Repair & Maintenance of identified Provincial Highways through Perofrmance Based Maintenance (PBM) Pilot Project under Provincial Roads Improvement Project (ADB Assisted) |
Provincial PRIP |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1250 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- November - 2019 |
Pc-I /Dce submitted to PDWP Rs. 1250 M . Approval Awaited. |
No Image |
1038 (OG) |
180162-Special Repair & Maintenance of identified Provincial Highways through Perofrmance Based Maintenance (PBM) Pilot Project under Provincial Roads Improvement Project (ADB Assisted) |
Provincial PRIP |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1250 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- October - 2019 |
Pc-I /Dce submitted to PDWP Rs. 1250 M . Approval Awaited. |
No Image |
1038 (OG) |
180162-Special Repair & Maintenance of identified Provincial Highways through Perofrmance Based Maintenance (PBM) Pilot Project under Provincial Roads Improvement Project (ADB Assisted) |
Provincial PRIP |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1250 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- September - 2019 |
Approved (4 roads ) . TORs preparation for contractor in progress |
No Image |
1038 (OG) |
180162-Special Repair & Maintenance of identified Provincial Highways through Perofrmance Based Maintenance (PBM) Pilot Project under Provincial Roads Improvement Project (ADB Assisted) |
Provincial PRIP |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1250 | 0 | 10 | 10 | 2.5 | 0 | 0 | 0 | - |
- August - 2019 |
Approved (4 roads ) . TORs preparation for contractor in progress |
No Image |
1038 (OG) |
180162-Special Repair & Maintenance of identified Provincial Highways through Perofrmance Based Maintenance (PBM) Pilot Project under Provincial Roads Improvement Project (ADB Assisted) |
Provincial PRIP |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1250 | 0 | 10 | 0.0005 | 0.0005 | 0 | 0 | 0 | - |
- May - 2020 |
Pc-I /Dce submitted to PDWP Rs. 1250 M . Approval Awaited. |
No Image |
1038 (OG) |
180162-Special Repair & Maintenance of identified Provincial Highways through Perofrmance Based Maintenance (PBM) Pilot Project under Provincial Roads Improvement Project (ADB Assisted) |
Provincial PRIP |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1250 | 0 | 10 | 0.0005 | 0.0005 | 0 | 0 | 0 | - |
- April - 2020 |
Pc-I /Dce submitted to PDWP Rs. 1250 M . Approval Awaited. |
No Image |
1038 (OG) |
180162-Special Repair & Maintenance of identified Provincial Highways through Perofrmance Based Maintenance (PBM) Pilot Project under Provincial Roads Improvement Project (ADB Assisted) |
Provincial PRIP |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1250 | 0 | 10 | 0.0005 | 0.0005 | 0 | 0 | 0 | - |
- March - 2020 |
Pc-I /Dce submitted to PDWP Rs. 1250 M . Approval Awaited. |
No Image |
1038 (OG) |
180162-Special Repair & Maintenance of identified Provincial Highways through Perofrmance Based Maintenance (PBM) Pilot Project under Provincial Roads Improvement Project (ADB Assisted) |
Provincial PRIP |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1250 | 0 | 10 | 0.0005 | 0.0005 | 0 | 0 | 0 | - |
- February - 2020 |
Pc-I /Dce submitted to PDWP Rs. 1250 M . Approval Awaited. |
No Image |
1038 (OG) |
180162-Special Repair & Maintenance of identified Provincial Highways through Perofrmance Based Maintenance (PBM) Pilot Project under Provincial Roads Improvement Project (ADB Assisted) |
Provincial PRIP |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1250 | 0 | 10 | 0.0005 | 0.0005 | 0 | 0 | 0 | - |
- January - 2020 |
Pc-I /Dce submitted to PDWP Rs. 1250 M . Approval Awaited. |
No Image |
1038 (OG) |
160193-Project Directorate for Swat Expressway. |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 67.401 | 58.143 | 10 | 10 | 7.5 | 2.5 | 60.643 | 0 | 100% |
90% December - 2018 |
Project directorate setup. |
No Image |
1038 (OG) |
160193-Project Directorate for Swat Expressway. |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 67.401 | 58.143 | 10 | 10 | 7.5 | 2.5 | 60.643 | 0 | 100% |
90% November - 2018 |
Project directorate setup. |
No Image |
1038 (OG) |
160193-Project Directorate for Swat Expressway. |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 67.401 | 58.143 | 10 | 10 | 7.5 | 2.5 | 60.643 | 0 | 100% |
90% November - 2018 |
Project directorate setup. |
No Image |
1038 (OG) |
160193-Project Directorate for Swat Expressway. |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 123.611 | 58.143 | 10 | 10 | 8.75 | 8.75 | 66.893 | 55.468 | 55% |
54% April - 2019 |
Project directorate setup. Demand Rs.60 m. |
No Image |
1038 (OG) |
160193-Project Directorate for Swat Expressway. |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 123.611 | 58.143 | 10 | 10 | 8.75 | 8.75 | 66.893 | 55.468 | 55% |
54% March - 2019 |
Project directorate setup. Demand Rs.60 m. |
No Image |
1038 (OG) |
160193-Project Directorate for Swat Expressway. |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 123.611 | 58.143 | 10 | 10 | 8.75 | 8.75 | 66.893 | 55.468 | 55% |
54% March - 2019 |
Project directorate setup. Demand Rs.60 m. |
No Image |
1038 (OG) |
160193-Project Directorate for Swat Expressway. |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 123.611 | 58.143 | 10 | 10 | 8.75 | 8.75 | 66.893 | 55.468 | 55% |
54% February - 2019 |
Project directorate setup. Demand Rs. 60 M |
No Image |
1038 (OG) |
160193-Project Directorate for Swat Expressway. |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 67.401 | 58.143 | 10 | 10 | 7.5 | 5 | 63.143 | 0 | 100% |
94% January - 2019 |
Project directorate setup. |
No Image |
Pages : 1 |