Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2019, January - 2020, January - 2018, February - 2019, February - 2020, February - 2018, March - 2018, March - 2019, March - 2020, April - 2018, April - 2019, April - 2020, May - 2018, May - 2020, June - 2018, July - 2020, July - 2017, August - 2019, August - 2020, August - 2017, September - 2019, September - 2020, September - 2017, October - 2019, October - 2020, October - 2017, November - 2018, November - 2019, November - 2017, December - 2018, December - 2019, December - 2017,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1035
(OG)
140624-Dualization of Sherkot Hangu Section of Provincial Highway S-7 (24 Km), District Kohat and Hangu.
Hangu
PKHA
30-11--1 30-11--1 - 30-11--1 - 2759.858 1076.508 80 80 80 80 1156.508 1603.35 42% 42%
December - 2018
Pack-1 (6 Km) - embankment, in progress Km-1, 3, 4, 5, clearing/grubbing and NGC 90% completed. Pack-2 (6 Km) - Km-9, 10, 11 hillside cutting, RW in progress. Pack-3 (6 Km) - embankment in progress Km-16, 17, clearing/grubbing and NGC 80% completed. Pack-4 (6 Km) - clearing/grubbing Km-19, 20, embankment in progress. Pack-5 (4 bridges) - contractor machinery and staff mobilized on site. Design awaited for bridge pile from design consultant.
No Image
1035
(OG)
140624-Dualization of Sherkot Hangu Section of Provincial Highway S-7 (24 Km), District Kohat and Hangu.
Hangu
PKHA
30-11--1 30-11--1 - 30-11--1 - 2759.858 1076.508 80 80 80 40 1116.508 1603.35 42% 40%
November - 2018
Pack-1 (6 Km) - embankment, in progress Km-1, 3, 4, 5, clearing/grubbing and NGC 90% completed. Pack-2 (6 Km) - Km-9, 10, 11 hillside cutting, RW in progress. Pack-3 (6 Km) - embankment in progress Km-16, 17, clearing/grubbing and NGC 80% completed. Pack-4 (6 Km) - clearing/grubbing Km-19, 20, embankment in progress. Pack-5 (4 bridges) - contractor machinery and staff mobilized on site. Design awaited for bridge pile from design consultant.
No Image
1035
(OG)
140624-Dualization of Sherkot Hangu Section of Provincial Highway S-7 (24 Km), District Kohat and Hangu.
Hangu
PKHA
30-11--1 30-11--1 - 30-11--1 - 2759.858 1076.508 80 80 80 40 1116.508 1603.35 42% 40%
November - 2018
Pack-1 (6 Km) - embankment, in progress Km-1, 3, 4, 5, clearing/grubbing and NGC 90% completed. Pack-2 (6 Km) - Km-9, 10, 11 hillside cutting, RW in progress. Pack-3 (6 Km) - embankment in progress Km-16, 17, clearing/grubbing and NGC 80% completed. Pack-4 (6 Km) - clearing/grubbing Km-19, 20, embankment in progress. Pack-5 (4 bridges) - contractor machinery and staff mobilized on site. Design awaited for bridge pile from design consultant.
No Image
1035
(OG)
140624-Dualization of Sherkot Hangu Section of Provincial Highway S-7 (24 Km), District Kohat and Hangu.
Hangu
PKHA
30-11--1 30-11--1 - 30-11--1 - 2759.858 1076.508 80 80 80 80 1156.508 1603.35 42% 42%
April - 2019
Pack-1 (6 Km) - embankment, in progress Km-1, 3, 4, 5, clearing/grubbing and NGC 90% completed. Pack-2 (6 Km) - Km-9, 10, 11 hillside cutting, RW in progress. Pack-3 (6 Km) - embankment in progress Km-16, 17, clearing/grubbing and NGC 80% completed. Pack-4 (6 Km) - clearing/grubbing Km-19, 20, embankment in progress. Pack-5 (4 bridges) - contractor machinery and staff mobilized on site. Design awaited for bridge pile from design consultant. Work stopped due to paucity of funds
No Image
1035
(OG)
140624-Dualization of Sherkot Hangu Section of Provincial Highway S-7 (24 Km), District Kohat and Hangu.
Hangu
PKHA
30-11--1 30-11--1 - 30-11--1 - 2759.858 1076.508 80 80 80 80 1156.508 1603.35 42% 42%
March - 2019
Pack-1 (6 Km) - embankment, in progress Km-1, 3, 4, 5, clearing/grubbing and NGC 90% completed. Pack-2 (6 Km) - Km-9, 10, 11 hillside cutting, RW in progress. Pack-3 (6 Km) - embankment in progress Km-16, 17, clearing/grubbing and NGC 80% completed. Pack-4 (6 Km) - clearing/grubbing Km-19, 20, embankment in progress. Pack-5 (4 bridges) - contractor machinery and staff mobilized on site. Design awaited for bridge pile from design consultant. Work stopped due to paucity of funds
No Image
1035
(OG)
140624-Dualization of Sherkot Hangu Section of Provincial Highway S-7 (24 Km), District Kohat and Hangu.
Hangu
PKHA
30-11--1 30-11--1 - 30-11--1 - 2759.858 1076.508 80 80 80 80 1156.508 1603.35 42% 42%
March - 2019
Pack-1 (6 Km) - embankment, in progress Km-1, 3, 4, 5, clearing/grubbing and NGC 90% completed. Pack-2 (6 Km) - Km-9, 10, 11 hillside cutting, RW in progress. Pack-3 (6 Km) - embankment in progress Km-16, 17, clearing/grubbing and NGC 80% completed. Pack-4 (6 Km) - clearing/grubbing Km-19, 20, embankment in progress. Pack-5 (4 bridges) - contractor machinery and staff mobilized on site. Design awaited for bridge pile from design consultant. Work stopped due to paucity of funds
No Image
1035
(OG)
140624-Dualization of Sherkot Hangu Section of Provincial Highway S-7 (24 Km), District Kohat and Hangu.
Hangu
PKHA
30-11--1 30-11--1 - 30-11--1 - 2759.858 1076.508 80 80 80 80 1156.508 1603.35 42% 42%
February - 2019
Pack-1 (6 Km) - embankment, in progress Km-1, 3, 4, 5, clearing/grubbing and NGC 90% completed. Pack-2 (6 Km) - Km-9, 10, 11 hillside cutting, RW in progress. Pack-3 (6 Km) - embankment in progress Km-16, 17, clearing/grubbing and NGC 80% completed. Pack-4 (6 Km) - clearing/grubbing Km-19, 20, embankment in progress. Pack-5 (4 bridges) - contractor machinery and staff mobilized on site. Design awaited for bridge pile from design consultant.
No Image
1035
(OG)
140624-Dualization of Sherkot Hangu Section of Provincial Highway S-7 (24 Km), District Kohat and Hangu.
Hangu
PKHA
30-11--1 30-11--1 - 30-11--1 - 2759.858 1076.508 80 80 80 80 1156.508 1603.35 42% 42%
January - 2019
Pack-1 (6 Km) - embankment, in progress Km-1, 3, 4, 5, clearing/grubbing and NGC 90% completed. Pack-2 (6 Km) - Km-9, 10, 11 hillside cutting, RW in progress. Pack-3 (6 Km) - embankment in progress Km-16, 17, clearing/grubbing and NGC 80% completed. Pack-4 (6 Km) - clearing/grubbing Km-19, 20, embankment in progress. Pack-5 (4 bridges) - contractor machinery and staff mobilized on site. Design awaited for bridge pile from design consultant.
No Image
1035
(OG)
140935-F/S, Design, Improvement & Widening of Road from Akora Khattak to Manai - Dooran - Tarkhel i/c link from Shahab Khel to Guldheri, Sawarkhel-Pitao to Kaka Sahib Eidgah, Khwar Miangan to Khawryan via Bagh Gali to Bus Adda, Kaka Sahib, Nowshera.
Nowshera
HW
13-05-15 - - 26-09-17 - 1009.995 426.892 164.997 215.855 215.856 173.129 600.021 418.106 59% 59%
December - 2017
Original Scope (Length 27 Km) - 27 Km completed. Revised scope in progress.
No Image
1035
(OG)
140935-F/S, Design, Improvement & Widening of Road from Akora Khattak to Manai - Dooran - Tarkhel i/c link from Shahab Khel to Guldheri, Sawarkhel-Pitao to Kaka Sahib Eidgah, Khwar Miangan to Khawryan via Bagh Gali to Bus Adda, Kaka Sahib, Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 1009.995 426.892 164.997 180.855 89.762 89.762 516.654 418.106 59% 51%
November - 2017
Original Scope (Length 27 Km) - 27 Km completed. Revised scope in progress.
No Image
1035
(OG)
140935-F/S, Design, Improvement & Widening of Road from Akora Khattak to Manai - Dooran - Tarkhel i/c link from Shahab Khel to Guldheri, Sawarkhel-Pitao to Kaka Sahib Eidgah, Khwar Miangan to Khawryan via Bagh Gali to Bus Adda, Kaka Sahib, Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 1009.995 426.892 164.997 164.997 75.432 73.954 500.846 418.106 59% 50%
October - 2017
Original Scope (Length 27 Km) - 27 Km completed. Revised scope in progress.
No Image
1035
(OG)
140935-F/S, Design, Improvement & Widening of Road from Akora Khattak to Manai - Dooran - Tarkhel i/c link from Shahab Khel to Guldheri, Sawarkhel-Pitao to Kaka Sahib Eidgah, Khwar Miangan to Khawryan via Bagh Gali to Bus Adda, Kaka Sahib, Nowshera.
Nowshera
HW
13-05-15 - - 02-03-17 - 1010.279 426.892 164.997 164.997 58.574 35.77 462.662 418.39 59% 46%
September - 2017
Length 27 Km - earth work 100%, sub base 15 Km, WBM 15 Km, WC 12 Km, structure work 95%, PCC road 6 Km completed.
No Image
1035
(OG)
140935-F/S, Design, Improvement & Widening of Road from Akora Khattak to Manai - Dooran - Tarkhel i/c link from Shahab Khel to Guldheri, Sawarkhel-Pitao to Kaka Sahib Eidgah, Khwar Miangan to Khawryan via Bagh Gali to Bus Adda, Kaka Sahib, Nowshera.
Nowshera
HW
13-05-15 - - 02-03-17 - 910.279 426.892 164.997 164.997 58.574 8.331 435.223 318.39 65% 48%
August - 2017
Length 27 Km - earth work 100%, sub base 15 Km, WBM 15 Km, WC 12 Km, structure work 95%, PCC road 6 Km completed. Revised PC-I/DCE for Rs.1010 m submitted to SOR on 18/08/2017.
No Image
1035
(OG)
140935-F/S, Design, Improvement & Widening of Road from Akora Khattak to Manai - Dooran - Tarkhel i/c link from Shahab Khel to Guldheri, Sawarkhel-Pitao to Kaka Sahib Eidgah, Khwar Miangan to Khawryan via Bagh Gali to Bus Adda, Kaka Sahib, Nowshera.
Nowshera
HW
13-05-15 - - 02-03-17 - 910.279 426.892 164.997 164.997 58.574 0 426.892 318.39 65% 47%
July - 2017
Length 27 Km - earth work 100%, sub base 15 Km, WBM 15 Km, WC 12 Km, structure work 95%, PCC road 6 Km completed. Revised PC-I/DCE for Rs.1010 m submitted to CE Center.
No Image
1035
(OG)
140935-F/S, Design, Improvement & Widening of Road from Akora Khattak to Manai - Dooran - Tarkhel i/c link from Shahab Khel to Guldheri, Sawarkhel-Pitao to Kaka Sahib Eidgah, Khwar Miangan to Khawryan via Bagh Gali to Bus Adda, Kaka Sahib, Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 1009.995 426.892 164.997 295.253 295.253 295.253 722.145 418.106 59% 71%
June - 2018
Original scope - 27 Km completed. Revised scope in progress.
No Image
Nowshera
1035
(OG)
140935-F/S, Design, Improvement & Widening of Road from Akora Khattak to Manai - Dooran - Tarkhel i/c link from Shahab Khel to Guldheri, Sawarkhel-Pitao to Kaka Sahib Eidgah, Khwar Miangan to Khawryan via Bagh Gali to Bus Adda, Kaka Sahib, Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 1009.995 426.892 164.997 295.253 295.253 295.253 722.145 418.106 59% 71%
May - 2018
Original scope - 27 Km completed. Revised scope in progress.
No Image
Nowshera
1035
(OG)
140935-F/S, Design, Improvement & Widening of Road from Akora Khattak to Manai - Dooran - Tarkhel i/c link from Shahab Khel to Guldheri, Sawarkhel-Pitao to Kaka Sahib Eidgah, Khwar Miangan to Khawryan via Bagh Gali to Bus Adda, Kaka Sahib, Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 1009.995 426.892 164.997 295.253 295.253 295.253 722.145 418.106 59% 71%
April - 2018
Original scope - 27 Km completed. Revised scope in progress.
No Image
Nowshera
1035
(OG)
140935-F/S, Design, Improvement & Widening of Road from Akora Khattak to Manai - Dooran - Tarkhel i/c link from Shahab Khel to Guldheri, Sawarkhel-Pitao to Kaka Sahib Eidgah, Khwar Miangan to Khawryan via Bagh Gali to Bus Adda, Kaka Sahib, Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 1009.995 426.892 164.997 295.25 295.25 280.143 707.035 418.106 59% 70%
March - 2018
Original scope - 27 Km completed. Revised scope in progress.
No Image
Nowshera
1035
(OG)
140935-F/S, Design, Improvement & Widening of Road from Akora Khattak to Manai - Dooran - Tarkhel i/c link from Shahab Khel to Guldheri, Sawarkhel-Pitao to Kaka Sahib Eidgah, Khwar Miangan to Khawryan via Bagh Gali to Bus Adda, Kaka Sahib, Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 1009.995 426.892 164.997 302.563 302.563 272.852 699.744 418.106 59% 69%
February - 2018
Original scope - 27 Km completed. Revised scope in progress.
No Image
Nowshera
1035
(OG)
140935-F/S, Design, Improvement & Widening of Road from Akora Khattak to Manai - Dooran - Tarkhel i/c link from Shahab Khel to Guldheri, Sawarkhel-Pitao to Kaka Sahib Eidgah, Khwar Miangan to Khawryan via Bagh Gali to Bus Adda, Kaka Sahib, Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 1009.995 426.892 164.997 302.563 302.563 213.645 640.537 418.106 59% 63%
January - 2018
Original scope - 27 Km completed. Revised scope in progress.
No Image
1035
(OG)
170521-F/S & Dualization of Mardan-Swabi Road (ADB Assisted)
Provincial
PRIP
30-11--1 30-11--1 - 30-11--1 - 8213 10 3400 3400 610.712 610.712 620.712 4803 42% 8%
December - 2019
Loan effective on 25-06-2019. Procuremnet of contractor and consultant in finalized.
No Image
1035
(OG)
170521-F/S & Dualization of Mardan-Swabi Road (ADB Assisted)
Provincial
PRIP
30-11--1 30-11--1 - 30-11--1 - 1337 10 10 2.4995 2.4995 0 10 1317 1% 1%
December - 2019
Loan effective on 25-06-2019. Procuremnet of contractor and consultant in finalized. Contractor Mobilized.
No Image
1035
(OG)
170521-F/S & Dualization of Mardan-Swabi Road (ADB Assisted)
Provincial
PRIP
30-11--1 30-11--1 - 30-11--1 - 8213 10 3400 3400 610.712 610.712 620.712 4803 42% 8%
November - 2019
Loan effective on 25-06-2019. Procuremnet of contractor and consultant in finalized.
No Image
1035
(OG)
170521-F/S & Dualization of Mardan-Swabi Road (ADB Assisted)
Provincial
PRIP
30-11--1 30-11--1 - 30-11--1 - 1337 10 10 10 2.5 0 10 1317 1% 1%
November - 2019
Loan effective on 25-06-2019. Procuremnet of contractor and consultant in finalized. Contractor Mobilized.
No Image
1035
(OG)
170521-F/S & Dualization of Mardan-Swabi Road (ADB Assisted)
Provincial
PRIP
30-11--1 30-11--1 - 30-11--1 - 8213 10 3400 3400 610.712 610.712 620.712 4803 42% 8%
October - 2019
Loan effective on 25-06-2019. Procuremnet of contractor and consultant in finalized.
No Image
1035
(OG)
170521-F/S & Dualization of Mardan-Swabi Road (ADB Assisted)
Provincial
PRIP
30-11--1 30-11--1 - 30-11--1 - 1337 10 10 10 2.5 0 10 1317 1% 1%
October - 2019
Loan effective on 25-06-2019. Procuremnet of contractor and consultant in finalized. Contractor Mobilized.
No Image
1035
(OG)
170521-F/S & Dualization of Mardan-Swabi Road (ADB Assisted)
Provincial
PRIP
30-11--1 30-11--1 - 30-11--1 - 8213 10 3400 3400 0 0 10 4803 42% 0%
September - 2019
Loan effective on 25-06-2019. Procuremnet of contractor and consultant in finalized.
No Image
1035
(OG)
170521-F/S & Dualization of Mardan-Swabi Road (ADB Assisted)
Provincial
PRIP
30-11--1 30-11--1 - 30-11--1 - 1337 10 10 10 2.5 0 10 1317 1% 1%
September - 2019
Loan effective on 25-06-2019. Procuremnet of contractor and consultant in finalized.
No Image
1035
(OG)
170521-F/S & Dualization of Mardan-Swabi Road (ADB Assisted)
Provincial
PRIP
30-11--1 30-11--1 - 30-11--1 - 1337 10 10 10 2.5 0 10 1317 1% 1%
August - 2019
Loan effective on 25-06-2019. Procuremnet of contractor and consultant in finalized.
No Image
1035
(OG)
170521-F/S & Dualization of Mardan-Swabi Road (ADB Assisted)
Provincial
PRIP
30-11--1 30-11--1 - 30-11--1 - 8213 10 3400 3400 0 0 10 4803 42% 0%
August - 2019
Loan effective on 25-06-2019. Procuremnet of contractor and consultant in finalized.
No Image
1035
(OG)
170521-F/S & Dualization of Mardan-Swabi Road (ADB Assisted)
Provincial
PRIP
30-11--1 30-11--1 - 30-11--1 - 8213 10 3400 3400 610.712 610.712 620.712 4803 42% 8%
May - 2020
Loan effective on 25-06-2019. Procuremnet of contractor and consultant in finalized.
No Image
1035
(OG)
170521-F/S & Dualization of Mardan-Swabi Road (ADB Assisted)
Provincial
PRIP
30-11--1 30-11--1 - 30-11--1 - 1337 10 10 2.4995 2.4995 0 10 1317 1% 1%
May - 2020
Loan effective on 25-06-2019. Procuremnet of contractor and consultant in finalized. Contractor Mobilized.
No Image
1035
(OG)
170521-F/S & Dualization of Mardan-Swabi Road (ADB Assisted)
Provincial
PRIP
30-11--1 30-11--1 - 30-11--1 - 8213 10 3400 3400 610.712 610.712 620.712 4803 42% 8%
April - 2020
Loan effective on 25-06-2019. Procuremnet of contractor and consultant in finalized.
No Image
1035
(OG)
170521-F/S & Dualization of Mardan-Swabi Road (ADB Assisted)
Provincial
PRIP
30-11--1 30-11--1 - 30-11--1 - 1337 10 10 2.4995 2.4995 0 10 1317 1% 1%
April - 2020
Loan effective on 25-06-2019. Procuremnet of contractor and consultant in finalized. Contractor Mobilized.
No Image
1035
(OG)
170521-F/S & Dualization of Mardan-Swabi Road (ADB Assisted)
Provincial
PRIP
30-11--1 30-11--1 - 30-11--1 - 8213 10 3400 3400 610.712 610.712 620.712 4803 42% 8%
March - 2020
Loan effective on 25-06-2019. Procuremnet of contractor and consultant in finalized.
No Image
1035
(OG)
170521-F/S & Dualization of Mardan-Swabi Road (ADB Assisted)
Provincial
PRIP
30-11--1 30-11--1 - 30-11--1 - 1337 10 10 2.4995 2.4995 0 10 1317 1% 1%
March - 2020
Loan effective on 25-06-2019. Procuremnet of contractor and consultant in finalized. Contractor Mobilized.
No Image
1035
(OG)
170521-F/S & Dualization of Mardan-Swabi Road (ADB Assisted)
Provincial
PRIP
30-11--1 30-11--1 - 30-11--1 - 8213 10 3400 3400 610.712 610.712 620.712 4803 42% 8%
February - 2020
Loan effective on 25-06-2019. Procuremnet of contractor and consultant in finalized.
No Image
1035
(OG)
170521-F/S & Dualization of Mardan-Swabi Road (ADB Assisted)
Provincial
PRIP
30-11--1 30-11--1 - 30-11--1 - 1337 10 10 2.4995 2.4995 0 10 1317 1% 1%
February - 2020
Loan effective on 25-06-2019. Procuremnet of contractor and consultant in finalized. Contractor Mobilized.
No Image
1035
(OG)
170521-F/S & Dualization of Mardan-Swabi Road (ADB Assisted)
Provincial
PRIP
30-11--1 30-11--1 - 30-11--1 - 8213 10 3400 3400 610.712 610.712 620.712 4803 42% 8%
January - 2020
Loan effective on 25-06-2019. Procuremnet of contractor and consultant in finalized.
No Image
1035
(OG)
170521-F/S & Dualization of Mardan-Swabi Road (ADB Assisted)
Provincial
PRIP
30-11--1 30-11--1 - 30-11--1 - 1337 10 10 2.4995 2.4995 0 10 1317 1% 1%
January - 2020
Loan effective on 25-06-2019. Procuremnet of contractor and consultant in finalized. Contractor Mobilized.
No Image
1035
(OG)
191156-180100 - Construction of Levies/Khassadrs Barracks & Levy Line in District South Waziristan. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 30.043 15 15 15 6 1.462 16.462 0.043 100% 55%
October - 2020
02- Units 1- Main building upto DPC level, Bore completed. 2- Roof level.
No Image
1035
(OG)
191156-180100 - Construction of Levies/Khassadrs Barracks & Levy Line in District South Waziristan. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 30.043 15 15 15 6 1.462 16.462 0.043 100% 55%
September - 2020
02- Units 1- Main building upto DPC level, Bore completed. 2- Roof level.
No Image
1035
(OG)
191156-180100 - Construction of Levies/Khassadrs Barracks & Levy Line in District South Waziristan. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 30.043 15 15 15 0 0 15 0.043 100% 50%
August - 2020
02- Units 1- Main building upto DPC level, Bore completed. 2- Roof level.
No Image
1035
(OG)
191156-180100 - Construction of Levies/Khassadrs Barracks & Levy Line in District South Waziristan. [MA]
South Wazirstan
30-11--1 30-11--1 - 30-11--1 - 30.043 15.043 15 0 0 0 15.043 0
July - 2020
No Image
Pages : 1