Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2018, January - 2019, January - 2020, January - 2021, February - 2018, February - 2019, February - 2020, February - 2021, March - 2018, March - 2019, March - 2020, March - 2021, April - 2021, April - 2018, April - 2019, April - 2020, May - 2021, May - 2018, May - 2020, June - 2018, July - 2020, July - 2017, August - 2019, August - 2020, August - 2017, September - 2019, September - 2020, September - 2017, October - 2017, October - 2019, October - 2020, November - 2017, November - 2018, November - 2019, December - 2018, December - 2019, December - 2020, December - 2017,

Showing Page Number : 1 of 4

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1033
(OG)
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 48.726 8.808 3 3 3 2 10.808 36.918 24% 22%
December - 2019
3/3 units -work in progress. 2. EW 70 % Structure Work 75 % Liability 30 M
No Image
1) Jhangi Khoja Banda Qazi UC Jhangi
2) Reconstruction of Pandu Thana road
3) Widening/carpeting of Boi-Pall-Mohri road
1033
(OG)
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 48.726 8.808 2 2 2 0 8.808 37.918 22% 18%
November - 2019
3/3 units -work in progress. 2. EW 70 % Structure Work 75 % Liability 30 M
No Image
1) Jhangi Khoja Banda Qazi UC Jhangi
2) Reconstruction of Pandu Thana road
3) Widening/carpeting of Boi-Pall-Mohri road
1033
(OG)
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 48.726 8.808 2 2 2 0 8.808 37.918 22% 18%
October - 2019
3/3 units -work in progress. 2. EW 70 % Structure Work 75 % Liability 30 M
No Image
1) Jhangi Khoja Banda Qazi UC Jhangi
2) Reconstruction of Pandu Thana road
3) Widening/carpeting of Boi-Pall-Mohri road
1033
(OG)
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 48.726 8.808 0 0 0 0 8.808 39.918 - 18%
September - 2019
Liability 30 m
No Image
1) Jhangi Khoja Banda Qazi UC Jhangi
2) Reconstruction of Pandu Thana road
3) Widening/carpeting of Boi-Pall-Mohri road
1033
(OG)
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 48.726 8.808 0 0 0 0 8.808 39.918 - 18%
August - 2019
2 units - 1 completed, 1 in progress.
No Image
1) Jhangi Khoja Banda Qazi UC Jhangi
2) Reconstruction of Pandu Thana road
3) Widening/carpeting of Boi-Pall-Mohri road
1033
(OG)
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 48.726 8.808 3 3 3 3 11.808 36.918 24% 24%
May - 2020
3/3 units -work in progress. 2. EW 70 % Structure Work 75 % Liability 30 M
No Image
1) Jhangi Khoja Banda Qazi UC Jhangi
2) Reconstruction of Pandu Thana road
3) Widening/carpeting of Boi-Pall-Mohri road
1033
(OG)
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 48.726 8.808 3 3 3 3 11.808 36.918 24% 24%
April - 2020
3/3 units -work in progress. 2. EW 70 % Structure Work 75 % Liability 30 M
No Image
1) Jhangi Khoja Banda Qazi UC Jhangi
2) Reconstruction of Pandu Thana road
3) Widening/carpeting of Boi-Pall-Mohri road
1033
(OG)
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 48.726 8.808 3 3 3 3 11.808 36.918 24% 24%
March - 2020
3/3 units -work in progress. 2. EW 70 % Structure Work 75 % Liability 30 M
No Image
1) Jhangi Khoja Banda Qazi UC Jhangi
2) Reconstruction of Pandu Thana road
3) Widening/carpeting of Boi-Pall-Mohri road
1033
(OG)
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 48.726 8.808 3 3 3 3 11.808 36.918 24% 24%
February - 2020
3/3 units -work in progress. 2. EW 70 % Structure Work 75 % Liability 30 M
No Image
1) Jhangi Khoja Banda Qazi UC Jhangi
2) Reconstruction of Pandu Thana road
3) Widening/carpeting of Boi-Pall-Mohri road
1033
(OG)
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 48.726 8.808 3 3 3 2 10.808 36.918 24% 22%
January - 2020
3/3 units -work in progress. 2. EW 70 % Structure Work 75 % Liability 30 M
No Image
1) Jhangi Khoja Banda Qazi UC Jhangi
2) Reconstruction of Pandu Thana road
3) Widening/carpeting of Boi-Pall-Mohri road
1033
(OG)
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa
Bannu
30-11--1 30-11--1 - 30-11--1 - 70.99 15.432 12 12 12 0.6 16.032 43.558 39% 23%
December - 2019
Length 1 Km - earth work 40% completed.
No Image
i) Kotka Sherdad (Matiullah), Bannu
ii) Reh: of B/T road village Biland Baist Khel
iii) RCC Bridge over Kackot River at Miran Shaha road Bannu
iv) Constn: / Reh: & B/T road from Kotka Imam Shah Mulagan to Kafish Khel Babu Jan Kilah
1033
(OG)
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa
Bannu
30-11--1 30-11--1 - 30-11--1 - 70.99 15.432 0 0 0 0 15.432 55.558 - 22%
November - 2019
Length 1 Km - earth work 40% completed.
No Image
i) Kotka Sherdad (Matiullah), Bannu
ii) Reh: of B/T road village Biland Baist Khel
iii) RCC Bridge over Kackot River at Miran Shaha road Bannu
iv) Constn: / Reh: & B/T road from Kotka Imam Shah Mulagan to Kafish Khel Babu Jan Kilah
1033
(OG)
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa
Bannu
30-11--1 30-11--1 - 30-11--1 - 70.99 15.432 0 0 0 0 15.432 55.558 - 22%
October - 2019
Length 1 Km - earth work 40% completed.
No Image
i) Kotka Sherdad (Matiullah), Bannu
ii) Reh: of B/T road village Biland Baist Khel
iii) RCC Bridge over Kackot River at Miran Shaha road Bannu
iv) Constn: / Reh: & B/T road from Kotka Imam Shah Mulagan to Kafish Khel Babu Jan Kilah
1033
(OG)
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa
Bannu
30-11--1 30-11--1 - 30-11--1 - 70.99 15.432 0 0 0 0 15.432 55.558 - 22%
September - 2019
Length 1 Km - earth work 40% completed.
No Image
i) Kotka Sherdad (Matiullah), Bannu
ii) Reh: of B/T road village Biland Baist Khel
iii) RCC Bridge over Kackot River at Miran Shaha road Bannu
iv) Constn: / Reh: & B/T road from Kotka Imam Shah Mulagan to Kafish Khel Babu Jan Kilah
1033
(OG)
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa
Bannu
30-11--1 30-11--1 - 30-11--1 - 70.99 15.432 0 0 0 0 15.432 55.558 - 22%
August - 2019
Length 1 Km - earth work 40% completed.
No Image
i) Kotka Sherdad (Matiullah), Bannu
ii) Reh: of B/T road village Biland Baist Khel
iii) RCC Bridge over Kackot River at Miran Shaha road Bannu
iv) Constn: / Reh: & B/T road from Kotka Imam Shah Mulagan to Kafish Khel Babu Jan Kilah
1033
(OG)
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa
Bannu
30-11--1 30-11--1 - 30-11--1 - 70.99 15.432 12 12 12 9.117 24.549 43.558 39% 35%
May - 2020
Length 1 Km - earth work 40% completed.
No Image
i) Kotka Sherdad (Matiullah), Bannu
ii) Reh: of B/T road village Biland Baist Khel
iii) RCC Bridge over Kackot River at Miran Shaha road Bannu
iv) Constn: / Reh: & B/T road from Kotka Imam Shah Mulagan to Kafish Khel Babu Jan Kilah
1033
(OG)
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa
Bannu
30-11--1 30-11--1 - 30-11--1 - 70.99 15.432 12 12 12 9.117 24.549 43.558 39% 35%
April - 2020
Length 1 Km - earth work 40% completed.
No Image
i) Kotka Sherdad (Matiullah), Bannu
ii) Reh: of B/T road village Biland Baist Khel
iii) RCC Bridge over Kackot River at Miran Shaha road Bannu
iv) Constn: / Reh: & B/T road from Kotka Imam Shah Mulagan to Kafish Khel Babu Jan Kilah
1033
(OG)
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa
Bannu
30-11--1 30-11--1 - 30-11--1 - 70.99 15.432 12 12 12 9.117 24.549 43.558 39% 35%
March - 2020
Length 1 Km - earth work 40% completed.
No Image
i) Kotka Sherdad (Matiullah), Bannu
ii) Reh: of B/T road village Biland Baist Khel
iii) RCC Bridge over Kackot River at Miran Shaha road Bannu
iv) Constn: / Reh: & B/T road from Kotka Imam Shah Mulagan to Kafish Khel Babu Jan Kilah
1033
(OG)
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa
Bannu
30-11--1 30-11--1 - 30-11--1 - 70.99 15.432 12 12 12 9.117 24.549 43.558 39% 35%
February - 2020
Length 1 Km - earth work 40% completed.
No Image
i) Kotka Sherdad (Matiullah), Bannu
ii) Reh: of B/T road village Biland Baist Khel
iii) RCC Bridge over Kackot River at Miran Shaha road Bannu
iv) Constn: / Reh: & B/T road from Kotka Imam Shah Mulagan to Kafish Khel Babu Jan Kilah
1033
(OG)
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa
Bannu
30-11--1 30-11--1 - 30-11--1 - 70.99 15.432 12 12 12 9.117 24.549 43.558 39% 35%
January - 2020
Length 1 Km - earth work 40% completed.
No Image
i) Kotka Sherdad (Matiullah), Bannu
ii) Reh: of B/T road village Biland Baist Khel
iii) RCC Bridge over Kackot River at Miran Shaha road Bannu
iv) Constn: / Reh: & B/T road from Kotka Imam Shah Mulagan to Kafish Khel Babu Jan Kilah
1033
(OG)
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa
Battagram
30-11--1 30-11--1 - 30-11--1 - 20 8 3 3 3 0 8 9 55% 40%
December - 2019
Length 2 Km - 40% work completed. Liability 10 m
No Image
Thakot Banna road (29 Km), Battagram
1033
(OG)
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa
Battagram
30-11--1 30-11--1 - 30-11--1 - 20 8 2 2 2 0 8 10 50% 40%
November - 2019
Length 2 Km - 40% work completed. Liability 10 m
No Image
Thakot Banna road (29 Km), Battagram
1033
(OG)
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa
Battagram
30-11--1 30-11--1 - 30-11--1 - 20 8 2 2 2 0 8 10 50% 40%
October - 2019
Length 2 Km - 40% work completed. Liability 10 m
No Image
Thakot Banna road (29 Km), Battagram
1033
(OG)
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa
Battagram
30-11--1 30-11--1 - 30-11--1 - 20 8 0 0 0 0 8 12 - 40%
September - 2019
Length 2 Km - 40% work completed. Liability 10 m
No Image
Thakot Banna road (29 Km), Battagram
1033
(OG)
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa
Battagram
30-11--1 30-11--1 - 30-11--1 - 20 8 0 0 0 0 8 12 - 40%
August - 2019
Length 2 Km - 40% work completed.
No Image
Thakot Banna road (29 Km), Battagram
1033
(OG)
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa
Battagram
30-11--1 30-11--1 - 30-11--1 - 20 8 3 3 3 0 8 9 55% 40%
May - 2020
Length 2 Km - 40% work completed.
No Image
Thakot Banna road (29 Km), Battagram
1033
(OG)
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa
Battagram
30-11--1 30-11--1 - 30-11--1 - 20 8 3 3 3 0 8 9 55% 40%
April - 2020
Length 2 Km - 40% work completed.
No Image
Thakot Banna road (29 Km), Battagram
1033
(OG)
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa
Battagram
30-11--1 30-11--1 - 30-11--1 - 20 8 3 3 3 0 8 9 55% 40%
March - 2020
Length 2 Km - 40% work completed.
No Image
Thakot Banna road (29 Km), Battagram
1033
(OG)
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa
Battagram
30-11--1 30-11--1 - 30-11--1 - 20 8 3 3 3 0 8 9 55% 40%
February - 2020
Length 2 Km - 40% work completed.
No Image
Thakot Banna road (29 Km), Battagram
1033
(OG)
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa
Battagram
30-11--1 30-11--1 - 30-11--1 - 20 8 3 3 3 0 8 9 55% 40%
January - 2020
Length 2 Km - 40% work completed.
No Image
Thakot Banna road (29 Km), Battagram
1033
(OG)
160629-F/S, Design and Construction of Link road from Shabqadar Naguman (PKHA) to Shabqadar Battagram road (PKHA) via Attakai, District Charsadda.
Charsadda
- - - 23-12-16 - 206.95 76.996 70 110 75 4.48 81.476 59.954 71% 39%
December - 2017
Land paymnet made. Dispute resolved. Work re-started.
No Image
1033
(OG)
160629-F/S, Design and Construction of Link road from Shabqadar Naguman (PKHA) to Shabqadar Battagram road (PKHA) via Attakai, District Charsadda.
Charsadda
- - - 23-12-16 - 206.95 76.996 70 70 24.85 0 76.996 59.954 71% 37%
September - 2017
Land paymnet made. Dispute resolved . Work re-started.
No Image
1033
(OG)
160629-F/S, Design and Construction of Link road from Shabqadar Naguman (PKHA) to Shabqadar Battagram road (PKHA) via Attakai, District Charsadda.
Charsadda
- - - 23-12-16 - 206.95 76.996 70 70 0 0 76.996 59.954 71% 37%
August - 2017
Land paymnet made. Work stopped due to land dispute.
No Image
1033
(OG)
160629-F/S, Design and Construction of Link road from Shabqadar Naguman (PKHA) to Shabqadar Battagram road (PKHA) via Attakai, District Charsadda.
Charsadda
- - - 23-12-16 - 206.95 76.996 70 70 0 0 76.996 59.954 71% 37%
July - 2017
Land paymnet made. Work stopped due to land dispute.
No Image
1033
(OG)
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa
Charsadda
30-11--1 30-11--1 - 30-11--1 - 226.041 110.359 18.682 18.682 18.682 18.682 129.041 97 57% 57%
December - 2019
Completed (Package-1 (length - 5 Km (12 ft). Shifting of site involved in other packages.
No Image
Package-I: 06 No. Different roads (4.95 Km)
Package-II: 07 No. Different roads (6.10 Km)
Package-III:  various roads in Distt Charsadda
Package-IV: various roads in Distt Charsadda
1033
(OG)
160629-F/S, Design and Construction of Link road from Shabqadar Naguman (PKHA) to Shabqadar Battagram road (PKHA) via Attakai, District Charsadda.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 206.95 76.996 70 110 75 3.5 80.496 59.954 71% 39%
November - 2017
Land paymnet made. Dispute resolved. Work re-started.
No Image
1033
(OG)
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa
Charsadda
30-11--1 30-11--1 - 30-11--1 - 226.041 110.359 4.5 4.5 4.5 4.5 114.859 111.182 51% 51%
November - 2019
Completed (Package-1 (length - 5 Km (12 ft). Shifting of site involved in other packages. Demand Rs. 30 M
No Image
Package-I: 06 No. Different roads (4.95 Km)
Package-II: 07 No. Different roads (6.10 Km)
Package-III:  various roads in Distt Charsadda
Package-IV: various roads in Distt Charsadda
1033
(OG)
160629-F/S, Design and Construction of Link road from Shabqadar Naguman (PKHA) to Shabqadar Battagram road (PKHA) via Attakai, District Charsadda.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 206.95 76.996 70 99.85 99.85 0 76.996 59.954 71% 37%
October - 2017
Land paymnet made. Dispute resolved. Work re-started.
No Image
1033
(OG)
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa
Charsadda
30-11--1 30-11--1 - 30-11--1 - 226.041 110.359 4.5 4.5 4.5 4.5 114.859 111.182 51% 51%
October - 2019
Completed (Package-1 (length - 5 Km (12 ft). Shifting of site involved in other packages. Demand Rs. 30 M
No Image
Package-I: 06 No. Different roads (4.95 Km)
Package-II: 07 No. Different roads (6.10 Km)
Package-III:  various roads in Distt Charsadda
Package-IV: various roads in Distt Charsadda
1033
(OG)
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa
Charsadda
30-11--1 30-11--1 - 30-11--1 - 226.041 110.359 1.5 1.5 1.5 1.5 111.859 114.182 49% 49%
September - 2019
Completed (Package-1 (length - 5 Km (12 ft). Shifting of site involved in other packages. 2nd Rev AA issued.
No Image
Package-I: 06 No. Different roads (4.95 Km)
Package-II: 07 No. Different roads (6.10 Km)
Package-III:  various roads in Distt Charsadda
Package-IV: various roads in Distt Charsadda
1033
(OG)
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa
Charsadda
30-11--1 30-11--1 - 30-11--1 - 226.041 110.359 0 0 0 0 110.359 115.682 - 49%
August - 2019
Completed (Package-1 (length - 5 Km (12 ft). Shifting of site involved in other packages. 2nd Rev AA issued.
No Image
Package-I: 06 No. Different roads (4.95 Km)
Package-II: 07 No. Different roads (6.10 Km)
Package-III:  various roads in Distt Charsadda
Package-IV: various roads in Distt Charsadda
1033
(OG)
160629-F/S, Design and Construction of Link road from Shabqadar Naguman (PKHA) to Shabqadar Battagram road (PKHA) via Attakai, District Charsadda.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 206.95 76.598 70 25.627 25.627 25.627 102.225 60.352 71% 49%
June - 2018
Length 2.4 Km (width 24 ft) - land payment made. Dispute resolved. Work in progress.
No Image
Charsadda
1033
(OG)
160629-F/S, Design and Construction of Link road from Shabqadar Naguman (PKHA) to Shabqadar Battagram road (PKHA) via Attakai, District Charsadda.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 206.95 76.598 70 120.373 120.373 92.163 168.761 60.352 71% 82%
May - 2018
Length 2.4 Km (width 24 ft) - land payment made. Dispute resolved. Work in progress.
No Image
Charsadda
1033
(OG)
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa
Charsadda
30-11--1 30-11--1 - 30-11--1 - 226.041 110.359 39.875 39.875 39.875 39.857 150.216 75.807 66% 66%
May - 2020
Completed (Package-1 (length - 5 Km (12 ft). Shifting of site involved in other packages.
No Image
Package-I: 06 No. Different roads (4.95 Km)
Package-II: 07 No. Different roads (6.10 Km)
Package-III:  various roads in Distt Charsadda
Package-IV: various roads in Distt Charsadda
1033
(OG)
160629-F/S, Design and Construction of Link road from Shabqadar Naguman (PKHA) to Shabqadar Battagram road (PKHA) via Attakai, District Charsadda.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 206.95 76.598 70 120.373 120.373 92.163 168.761 60.352 71% 82%
April - 2018
Length 2.4 Km (width 24 ft) - land payment made. Dispute resolved. Work in progress.
No Image
Charsadda
1033
(OG)
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa
Charsadda
30-11--1 30-11--1 - 30-11--1 - 226.041 110.359 39.875 39.875 39.875 39.857 150.216 75.807 66% 66%
April - 2020
Completed (Package-1 (length - 5 Km (12 ft). Shifting of site involved in other packages.
No Image
Package-I: 06 No. Different roads (4.95 Km)
Package-II: 07 No. Different roads (6.10 Km)
Package-III:  various roads in Distt Charsadda
Package-IV: various roads in Distt Charsadda
1033
(OG)
160629-F/S, Design and Construction of Link road from Shabqadar Naguman (PKHA) to Shabqadar Battagram road (PKHA) via Attakai, District Charsadda.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 206.95 76.598 70 120.373 120.373 92.163 168.761 60.352 71% 82%
March - 2018
Length 2.4 Km (width 24 ft) - land payment made. Dispute resolved. Work in progress.
No Image
Charsadda
1033
(OG)
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa
Charsadda
30-11--1 30-11--1 - 30-11--1 - 226.041 110.359 39.875 39.875 39.875 39.857 150.216 75.807 66% 66%
March - 2020
Completed (Package-1 (length - 5 Km (12 ft). Shifting of site involved in other packages.
No Image
Package-I: 06 No. Different roads (4.95 Km)
Package-II: 07 No. Different roads (6.10 Km)
Package-III:  various roads in Distt Charsadda
Package-IV: various roads in Distt Charsadda
1033
(OG)
160629-F/S, Design and Construction of Link road from Shabqadar Naguman (PKHA) to Shabqadar Battagram road (PKHA) via Attakai, District Charsadda.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 206.95 76.996 70 117.683 117.683 14.923 91.919 59.954 71% 44%
February - 2018
Length 2.4 km (width 24 ft ) Land paymnet made. Dispute resolved. Work in progress.
No Image
Charsadda
1033
(OG)
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa
Charsadda
30-11--1 30-11--1 - 30-11--1 - 226.041 110.359 39.875 39.875 39.875 39.857 150.216 75.807 66% 66%
February - 2020
Completed (Package-1 (length - 5 Km (12 ft). Shifting of site involved in other packages.
No Image
Package-I: 06 No. Different roads (4.95 Km)
Package-II: 07 No. Different roads (6.10 Km)
Package-III:  various roads in Distt Charsadda
Package-IV: various roads in Distt Charsadda
Pages : 1 2 3 4