Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1028 (OG) |
150881-Construction of road from Sardheri to Dosehra road, Charsadda. |
Charsadda |
- | 30-06-18 | - | 20-08-15 | - | 40.5 | 12.25 | 28 | 28 | 21 | 16.94 | 29.19 | 0.25 | 99% |
72% December - 2017 |
Length 5 Km - 3 Km asphalt completed. |
No Image |
1028 (OG) |
150881-Construction of road from Sardheri to Dosehra road, Charsadda. |
Charsadda |
- | 30-06-18 | - | 20-08-15 | - | 40.5 | 12.25 | 28 | 28 | 9.94 | 4.182 | 16.432 | 0.25 | 99% |
41% September - 2017 |
Length 5 Km - 3 Km asphalt completed. |
No Image |
1028 (OG) |
150881-Construction of road from Sardheri to Dosehra road, Charsadda. |
Charsadda |
- | 30-06-18 | - | 20-08-15 | - | 40.5 | 12.25 | 28 | 28 | 9.94 | 0 | 12.25 | 0.25 | 99% |
30% August - 2017 |
Length 5 Km - 3 Km asphalt completed. |
No Image |
1028 (OG) |
150881-Construction of road from Sardheri to Dosehra road, Charsadda. |
Charsadda |
- | 30-06-18 | - | 20-08-15 | - | 40.5 | 12.25 | 28 | 28 | 9.94 | 0 | 12.25 | 0.25 | 99% |
30% July - 2017 |
Length 5 Km - 3 Km asphalt completed. |
No Image |
1028 (OG) |
150881-Construction of road from Sardheri to Dosehra road, Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 40.5 | 12.25 | 28 | 28 | 21 | 9.94 | 22.19 | 0.25 | 99% |
55% November - 2017 |
Length 5 Km - 3 Km asphalt completed. |
No Image |
1028 (OG) |
150881-Construction of road from Sardheri to Dosehra road, Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 40.5 | 12.25 | 28 | 28 | 16.94 | 9.94 | 22.19 | 0.25 | 99% |
55% October - 2017 |
Length 5 Km - 3 Km asphalt completed. |
No Image |
1028 (OG) |
150881-Construction of road from Sardheri to Dosehra road, Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 40.5 | 12.25 | 28 | 26.904 | 26.904 | 26.904 | 39.154 | 0.25 | 99% |
97% June - 2018 |
Length 5 Km - 3 Km asphalt completed. |
No Image |
Sardheri to Dosehra road (5 km ) ( 12 ft ) | |||||||||||||||||||
1028 (OG) |
150881-Construction of road from Sardheri to Dosehra road, Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 40.5 | 12.25 | 28 | 28 | 28 | 21 | 33.25 | 0.25 | 99% |
82% May - 2018 |
Length 5 Km - 3 Km asphalt completed. |
No Image |
Sardheri to Dosehra road (5 km ) ( 12 ft ) | |||||||||||||||||||
1028 (OG) |
150881-Construction of road from Sardheri to Dosehra road, Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 40.5 | 12.25 | 28 | 28 | 28 | 21 | 33.25 | 0.25 | 99% |
82% April - 2018 |
Length 5 Km - 3 Km asphalt completed. |
No Image |
Sardheri to Dosehra road (5 km ) ( 12 ft ) | |||||||||||||||||||
1028 (OG) |
150881-Construction of road from Sardheri to Dosehra road, Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 40.5 | 12.25 | 28 | 28 | 21 | 17.195 | 29.445 | 0.25 | 99% |
73% March - 2018 |
Length 5 Km - 3 Km asphalt completed. |
No Image |
Sardheri to Dosehra road (5 km ) ( 12 ft ) | |||||||||||||||||||
1028 (OG) |
150881-Construction of road from Sardheri to Dosehra road, Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 40.5 | 12.25 | 28 | 28 | 21 | 16.94 | 29.19 | 0.25 | 99% |
72% February - 2018 |
Length 5 Km - 3 Km asphalt completed. |
No Image |
Sardheri to Dosehra road (5 km ) ( 12 ft ) | |||||||||||||||||||
1028 (OG) |
150881-Construction of road from Sardheri to Dosehra road, Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 40.5 | 12.25 | 28 | 28 | 21 | 16.94 | 29.19 | 0.25 | 99% |
72% January - 2018 |
Length 5 Km - 3 Km asphalt completed. |
No Image |
Charsadda | |||||||||||||||||||
1028 (OG) |
140829-Improvement of 25 Km leftover portion of Chukiyatan - Barawal - Shahi Road, District Dir Upper. |
Dir Upper PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 988.52 | 289.85 | 25 | 25 | 25 | 25 | 314.85 | 673.67 | 32% |
32% December - 2018 |
Length 25 Km. Pack-1 - earth work 6.2/8 Km completed. Pack- 2 - earth work 6.2/8 Km completed. Pack-3 and 4 - earth work started. |
No Image |
Package-1 (Barawal Bandi to Jan Bati)
Package-2 (Jan Bati to Shaltalo)
Package-3 (Shaltalo to Marawaro)
Package-4 (Marawaro to Shahi Top) | |||||||||||||||||||
1028 (OG) |
140829-Improvement of 25 Km leftover portion of Chukiyatan - Barawal - Shahi Road, District Dir Upper. |
Dir Upper PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 988.52 | 289.85 | 25 | 25 | 25 | 25 | 314.85 | 673.67 | 32% |
32% November - 2018 |
Length 25 Km. Pack-1 - earth work 6.2/8 Km completed. Pack- 2 - earth work 6.2/8 Km completed. Pack-3 and 4 - earth work started. |
No Image |
Package-1 (Barawal Bandi to Jan Bati)
Package-2 (Jan Bati to Shaltalo)
Package-3 (Shaltalo to Marawaro)
Package-4 (Marawaro to Shahi Top) | |||||||||||||||||||
1028 (OG) |
140829-Improvement of 25 Km leftover portion of Chukiyatan - Barawal - Shahi Road, District Dir Upper. |
Dir Upper PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 988.52 | 289.85 | 25 | 25 | 25 | 25 | 314.85 | 673.67 | 32% |
32% November - 2018 |
Length 25 Km. Pack-1 - earth work 6.2/8 Km completed. Pack- 2 - earth work 6.2/8 Km completed. Pack-3 and 4 - earth work started. |
No Image |
Package-1 (Barawal Bandi to Jan Bati)
Package-2 (Jan Bati to Shaltalo)
Package-3 (Shaltalo to Marawaro)
Package-4 (Marawaro to Shahi Top) | |||||||||||||||||||
1028 (OG) |
140829-Improvement of 25 Km leftover portion of Chukiyatan - Barawal - Shahi Road, District Dir Upper. |
Dir Upper PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 988.52 | 289.85 | 25 | 25 | 25 | 25 | 314.85 | 673.67 | 32% |
32% April - 2019 |
Length 25 Km. Pack-1 - earth work 6.2/8 Km completed. Pack- 2 - earth work 6.2/8 Km completed. Pack-3 and 4 - earth work started. |
No Image |
Package-1 (Barawal Bandi to Jan Bati)
Package-2 (Jan Bati to Shaltalo)
Package-3 (Shaltalo to Marawaro)
Package-4 (Marawaro to Shahi Top) | |||||||||||||||||||
1028 (OG) |
140829-Improvement of 25 Km leftover portion of Chukiyatan - Barawal - Shahi Road, District Dir Upper. |
Dir Upper PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 988.52 | 289.85 | 25 | 25 | 25 | 25 | 314.85 | 673.67 | 32% |
32% March - 2019 |
Length 25 Km. Pack-1 - earth work 6.2/8 Km completed. Pack- 2 - earth work 6.2/8 Km completed. Pack-3 and 4 - earth work started. |
No Image |
Package-1 (Barawal Bandi to Jan Bati)
Package-2 (Jan Bati to Shaltalo)
Package-3 (Shaltalo to Marawaro)
Package-4 (Marawaro to Shahi Top) | |||||||||||||||||||
1028 (OG) |
140829-Improvement of 25 Km leftover portion of Chukiyatan - Barawal - Shahi Road, District Dir Upper. |
Dir Upper PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 988.52 | 289.85 | 25 | 25 | 25 | 25 | 314.85 | 673.67 | 32% |
32% March - 2019 |
Length 25 Km. Pack-1 - earth work 6.2/8 Km completed. Pack- 2 - earth work 6.2/8 Km completed. Pack-3 and 4 - earth work started. |
No Image |
Package-1 (Barawal Bandi to Jan Bati)
Package-2 (Jan Bati to Shaltalo)
Package-3 (Shaltalo to Marawaro)
Package-4 (Marawaro to Shahi Top) | |||||||||||||||||||
1028 (OG) |
140829-Improvement of 25 Km leftover portion of Chukiyatan - Barawal - Shahi Road, District Dir Upper. |
Dir Upper PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 988.52 | 289.85 | 25 | 25 | 25 | 25 | 314.85 | 673.67 | 32% |
32% February - 2019 |
Length 25 Km. Pack-1 - earth work 6.2/8 Km completed. Pack- 2 - earth work 6.2/8 Km completed. Pack-3 and 4 - earth work started. |
No Image |
Package-1 (Barawal Bandi to Jan Bati)
Package-2 (Jan Bati to Shaltalo)
Package-3 (Shaltalo to Marawaro)
Package-4 (Marawaro to Shahi Top) | |||||||||||||||||||
1028 (OG) |
140829-Improvement of 25 Km leftover portion of Chukiyatan - Barawal - Shahi Road, District Dir Upper. |
Dir Upper PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 988.52 | 289.85 | 25 | 25 | 25 | 25 | 314.85 | 673.67 | 32% |
32% January - 2019 |
Length 25 Km. Pack-1 - earth work 6.2/8 Km completed. Pack- 2 - earth work 6.2/8 Km completed. Pack-3 and 4 - earth work started. |
No Image |
Package-1 (Barawal Bandi to Jan Bati)
Package-2 (Jan Bati to Shaltalo)
Package-3 (Shaltalo to Marawaro)
Package-4 (Marawaro to Shahi Top) | |||||||||||||||||||
1028 (New) |
200032-Security Enhancement of Central prison, Mardan |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 68.813 | 0 | 0.001 | 0.001 | 0 | 0 | 0 | 68.812 | 0% |
- December - 2020 |
Tendering in progress. |
No Image |
1028 (New) |
200032-Security Enhancement of Central prison, Mardan |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 68.813 | 0 | 0.001 | 0.001 | 0 | 0 | 0 | 68.812 | 0% |
- December - 2020 |
Tendering in progress. |
No Image |
1028 (New) |
200032-Security Enhancement of Central prison, Mardan |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 68.813 | 0 | 0.001 | 0.001 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
DDWP held on 13/10/20. AA awaited. |
No Image |
1028 (New) |
200032-Security Enhancement of Central prison, Mardan |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 68.813 | 0 | 0.001 | 0.001 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
No Image | |
1028 (New) |
200032-Security Enhancement of Central prison, Mardan |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 68.813 | 0 | 0.001 | 0.001 | 0 | 0 | 0 | 0 | - |
- August - 2020 |
No Image | |
1028 (New) |
200032-Security Enhancement of Central prison, Mardan |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 68.813 | 0 | 0.001 | 0 | 0 | 0 | 0 | 0 |
- July - 2020 |
No Image | ||
1028 (New) |
200032-Security Enhancement of Central prison, Mardan |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 68.813 | 0 | 0.001 | 5 | 5 | 0 | 0 | 68.812 | 0% |
- May - 2021 |
Tendering in progress. |
No Image |
1028 (New) |
200032-Security Enhancement of Central prison, Mardan |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 68.813 | 0 | 0.001 | 0.001 | 0 | 0 | 0 | 68.812 | 0% |
- April - 2021 |
Tendering in progress. |
No Image |
1028 (New) |
200032-Security Enhancement of Central prison, Mardan |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 68.813 | 0 | 0.001 | 0.001 | 0 | 0 | 0 | 68.812 | 0% |
- March - 2021 |
Tendering in progress. |
No Image |
1028 (New) |
200032-Security Enhancement of Central prison, Mardan |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 68.813 | 0 | 0.001 | 0.001 | 0 | 0 | 0 | 68.812 | 0% |
- February - 2021 |
Tendering in progress. |
No Image |
1028 (New) |
200032-Security Enhancement of Central prison, Mardan |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 68.813 | 0 | 0.001 | 0.001 | 0 | 0 | 0 | 68.812 | 0% |
- January - 2021 |
Tendering in progress. |
No Image |
1028 (OG) |
130510-Feasibiilty Study, Detailed Designing and Supervision of various roads of C&W Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 7.473 | 20 | 0 | 0 | 0 | 7.473 | 0 | - |
- December - 2019 |
PC-II approved. |
No Image |
1028 (OG) |
130510-Feasibiilty Study, Detailed Designing and Supervision of various roads of C&W Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 7.473 | 20 | 20 | 0 | 0 | 7.473 | 0 | - |
- November - 2019 |
PC-II approved. |
No Image |
1028 (OG) |
130510-Feasibiilty Study, Detailed Designing and Supervision of various roads of C&W Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 7.473 | 20 | 20 | 0 | 0 | 7.473 | 0 | - |
- October - 2019 |
PC-II approved. |
No Image |
1028 (OG) |
130510-Feasibiilty Study, Detailed Designing and Supervision of various roads of C&W Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 7.473 | 20 | 20 | 0 | 0 | 7.473 | 0 | - |
- September - 2019 |
PC-II approved. |
No Image |
1028 (OG) |
130510-Feasibiilty Study, Detailed Designing and Supervision of various roads of C&W Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 7.473 | 20 | 20 | 5 | 0 | 7.473 | 0 | - |
- August - 2019 |
PC-II approved. |
No Image |
1028 (OG) |
130510-Feasibiilty Study, Detailed Designing and Supervision of various roads of C&W Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 7.473 | 20 | 0 | 0 | 0 | 7.473 | 0 | - |
- May - 2020 |
PC-II approved. |
No Image |
1028 (OG) |
130510-Feasibiilty Study, Detailed Designing and Supervision of various roads of C&W Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 7.473 | 20 | 0 | 0 | 0 | 7.473 | 0 | - |
- April - 2020 |
PC-II approved. |
No Image |
1028 (OG) |
130510-Feasibiilty Study, Detailed Designing and Supervision of various roads of C&W Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 7.473 | 20 | 0 | 0 | 0 | 7.473 | 0 | - |
- March - 2020 |
PC-II approved. |
No Image |
1028 (OG) |
130510-Feasibiilty Study, Detailed Designing and Supervision of various roads of C&W Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 7.473 | 20 | 0 | 0 | 0 | 7.473 | 0 | - |
- February - 2020 |
PC-II approved. |
No Image |
1028 (OG) |
130510-Feasibiilty Study, Detailed Designing and Supervision of various roads of C&W Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 7.473 | 20 | 0 | 0 | 0 | 7.473 | 0 | - |
- January - 2020 |
PC-II approved. |
No Image |
Pages : 1 |