Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2018, January - 2019, February - 2018, February - 2019, March - 2018, March - 2019, April - 2018, May - 2018, June - 2018, July - 2017, August - 2017, September - 2017, October - 2017, November - 2017, November - 2018, December - 2017, December - 2018,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1028
(OG)
150881-Construction of road from Sardheri to Dosehra road, Charsadda.
Charsadda
- 30-06-18 - 20-08-15 - 40.5 12.25 28 28 21 16.94 29.19 0.25 99% 72%
December - 2017
Length 5 Km - 3 Km asphalt completed.
No Image
1028
(OG)
150881-Construction of road from Sardheri to Dosehra road, Charsadda.
Charsadda
- 30-06-18 - 20-08-15 - 40.5 12.25 28 28 9.94 4.182 16.432 0.25 99% 41%
September - 2017
Length 5 Km - 3 Km asphalt completed.
No Image
1028
(OG)
150881-Construction of road from Sardheri to Dosehra road, Charsadda.
Charsadda
- 30-06-18 - 20-08-15 - 40.5 12.25 28 28 9.94 0 12.25 0.25 99% 30%
August - 2017
Length 5 Km - 3 Km asphalt completed.
No Image
1028
(OG)
150881-Construction of road from Sardheri to Dosehra road, Charsadda.
Charsadda
- 30-06-18 - 20-08-15 - 40.5 12.25 28 28 9.94 0 12.25 0.25 99% 30%
July - 2017
Length 5 Km - 3 Km asphalt completed.
No Image
1028
(OG)
150881-Construction of road from Sardheri to Dosehra road, Charsadda.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 40.5 12.25 28 28 21 9.94 22.19 0.25 99% 55%
November - 2017
Length 5 Km - 3 Km asphalt completed.
No Image
1028
(OG)
150881-Construction of road from Sardheri to Dosehra road, Charsadda.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 40.5 12.25 28 28 16.94 9.94 22.19 0.25 99% 55%
October - 2017
Length 5 Km - 3 Km asphalt completed.
No Image
1028
(OG)
150881-Construction of road from Sardheri to Dosehra road, Charsadda.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 40.5 12.25 28 26.904 26.904 26.904 39.154 0.25 99% 97%
June - 2018
Length 5 Km - 3 Km asphalt completed.
No Image
Sardheri to Dosehra road (5 km ) ( 12 ft )
1028
(OG)
150881-Construction of road from Sardheri to Dosehra road, Charsadda.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 40.5 12.25 28 28 28 21 33.25 0.25 99% 82%
May - 2018
Length 5 Km - 3 Km asphalt completed.
No Image
Sardheri to Dosehra road (5 km ) ( 12 ft )
1028
(OG)
150881-Construction of road from Sardheri to Dosehra road, Charsadda.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 40.5 12.25 28 28 28 21 33.25 0.25 99% 82%
April - 2018
Length 5 Km - 3 Km asphalt completed.
No Image
Sardheri to Dosehra road (5 km ) ( 12 ft )
1028
(OG)
150881-Construction of road from Sardheri to Dosehra road, Charsadda.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 40.5 12.25 28 28 21 17.195 29.445 0.25 99% 73%
March - 2018
Length 5 Km - 3 Km asphalt completed.
No Image
Sardheri to Dosehra road (5 km ) ( 12 ft )
1028
(OG)
150881-Construction of road from Sardheri to Dosehra road, Charsadda.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 40.5 12.25 28 28 21 16.94 29.19 0.25 99% 72%
February - 2018
Length 5 Km - 3 Km asphalt completed.
No Image
Sardheri to Dosehra road (5 km ) ( 12 ft )
1028
(OG)
150881-Construction of road from Sardheri to Dosehra road, Charsadda.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 40.5 12.25 28 28 21 16.94 29.19 0.25 99% 72%
January - 2018
Length 5 Km - 3 Km asphalt completed.
No Image
Charsadda
1028
(OG)
140829-Improvement of 25 Km leftover portion of Chukiyatan - Barawal - Shahi Road, District Dir Upper.
Dir Upper
PKHA
30-11--1 30-11--1 - 30-11--1 - 988.52 289.85 25 25 25 25 314.85 673.67 32% 32%
December - 2018
Length 25 Km. Pack-1 - earth work 6.2/8 Km completed. Pack- 2 - earth work 6.2/8 Km completed. Pack-3 and 4 - earth work started.
No Image
Package-1 (Barawal Bandi to Jan Bati)
Package-2 (Jan Bati to Shaltalo)
Package-3 (Shaltalo to Marawaro)
Package-4 (Marawaro to Shahi Top)
1028
(OG)
140829-Improvement of 25 Km leftover portion of Chukiyatan - Barawal - Shahi Road, District Dir Upper.
Dir Upper
PKHA
30-11--1 30-11--1 - 30-11--1 - 988.52 289.85 25 25 25 25 314.85 673.67 32% 32%
November - 2018
Length 25 Km. Pack-1 - earth work 6.2/8 Km completed. Pack- 2 - earth work 6.2/8 Km completed. Pack-3 and 4 - earth work started.
No Image
Package-1 (Barawal Bandi to Jan Bati)
Package-2 (Jan Bati to Shaltalo)
Package-3 (Shaltalo to Marawaro)
Package-4 (Marawaro to Shahi Top)
1028
(OG)
140829-Improvement of 25 Km leftover portion of Chukiyatan - Barawal - Shahi Road, District Dir Upper.
Dir Upper
PKHA
30-11--1 30-11--1 - 30-11--1 - 988.52 289.85 25 25 25 25 314.85 673.67 32% 32%
November - 2018
Length 25 Km. Pack-1 - earth work 6.2/8 Km completed. Pack- 2 - earth work 6.2/8 Km completed. Pack-3 and 4 - earth work started.
No Image
Package-1 (Barawal Bandi to Jan Bati)
Package-2 (Jan Bati to Shaltalo)
Package-3 (Shaltalo to Marawaro)
Package-4 (Marawaro to Shahi Top)
1028
(OG)
140829-Improvement of 25 Km leftover portion of Chukiyatan - Barawal - Shahi Road, District Dir Upper.
Dir Upper
PKHA
30-11--1 30-11--1 - 30-11--1 - 988.52 289.85 25 25 25 25 314.85 673.67 32% 32%
March - 2019
Length 25 Km. Pack-1 - earth work 6.2/8 Km completed. Pack- 2 - earth work 6.2/8 Km completed. Pack-3 and 4 - earth work started.
No Image
Package-1 (Barawal Bandi to Jan Bati)
Package-2 (Jan Bati to Shaltalo)
Package-3 (Shaltalo to Marawaro)
Package-4 (Marawaro to Shahi Top)
1028
(OG)
140829-Improvement of 25 Km leftover portion of Chukiyatan - Barawal - Shahi Road, District Dir Upper.
Dir Upper
PKHA
30-11--1 30-11--1 - 30-11--1 - 988.52 289.85 25 25 25 25 314.85 673.67 32% 32%
February - 2019
Length 25 Km. Pack-1 - earth work 6.2/8 Km completed. Pack- 2 - earth work 6.2/8 Km completed. Pack-3 and 4 - earth work started.
No Image
Package-1 (Barawal Bandi to Jan Bati)
Package-2 (Jan Bati to Shaltalo)
Package-3 (Shaltalo to Marawaro)
Package-4 (Marawaro to Shahi Top)
1028
(OG)
140829-Improvement of 25 Km leftover portion of Chukiyatan - Barawal - Shahi Road, District Dir Upper.
Dir Upper
PKHA
30-11--1 30-11--1 - 30-11--1 - 988.52 289.85 25 25 25 25 314.85 673.67 32% 32%
January - 2019
Length 25 Km. Pack-1 - earth work 6.2/8 Km completed. Pack- 2 - earth work 6.2/8 Km completed. Pack-3 and 4 - earth work started.
No Image
Package-1 (Barawal Bandi to Jan Bati)
Package-2 (Jan Bati to Shaltalo)
Package-3 (Shaltalo to Marawaro)
Package-4 (Marawaro to Shahi Top)
Pages : 1