Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1022 (OG) |
170566-Widening, Improvement and BT of Swari, Dewana Baba road (11 Km) including RCC Bridge at Tangu, District Buner. |
Buner PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 545.879 | 0 | 20 | 20 | 15 | 10 | 10 | 525.879 | 4% |
2% December - 2018 |
LOA has been issued to the constractors. |
No Image |
1022 (OG) |
170566-Widening, Improvement and BT of Swari, Dewana Baba road (11 Km) including RCC Bridge at Tangu, District Buner. |
Buner PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 545.879 | 0 | 20 | 20 | 15 | 10 | 10 | 525.879 | 4% |
2% November - 2018 |
LOA has been issued to the constractors. |
No Image |
1022 (OG) |
170566-Widening, Improvement and BT of Swari, Dewana Baba road (11 Km) including RCC Bridge at Tangu, District Buner. |
Buner PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 545.879 | 0 | 20 | 20 | 15 | 10 | 10 | 525.879 | 4% |
2% November - 2018 |
LOA has been issued to the constractors. |
No Image |
1022 (OG) |
170566-Widening, Improvement and BT of Swari, Dewana Baba road (11 Km) including RCC Bridge at Tangu, District Buner. |
Buner PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 545.879 | 0 | 20 | 20 | 17.5 | 17.5 | 17.5 | 525.879 | 4% |
3% April - 2019 |
Work order issued to contractor. Contractor mobilized at site. |
No Image |
1022 (OG) |
170566-Widening, Improvement and BT of Swari, Dewana Baba road (11 Km) including RCC Bridge at Tangu, District Buner. |
Buner PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 545.879 | 0 | 20 | 20 | 17.5 | 17.5 | 17.5 | 525.879 | 4% |
3% March - 2019 |
Work order issued to contractor. Contractor mobilized at site. |
No Image |
1022 (OG) |
170566-Widening, Improvement and BT of Swari, Dewana Baba road (11 Km) including RCC Bridge at Tangu, District Buner. |
Buner PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 545.879 | 0 | 20 | 20 | 17.5 | 17.5 | 17.5 | 525.879 | 4% |
3% March - 2019 |
Work order issued to contractor. Contractor mobilized at site. |
No Image |
1022 (OG) |
170566-Widening, Improvement and BT of Swari, Dewana Baba road (11 Km) including RCC Bridge at Tangu, District Buner. |
Buner PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 545.879 | 0 | 20 | 20 | 17.5 | 17.5 | 17.5 | 525.879 | 4% |
3% February - 2019 |
Work order issued. |
No Image |
1022 (OG) |
170566-Widening, Improvement and BT of Swari, Dewana Baba road (11 Km) including RCC Bridge at Tangu, District Buner. |
Buner PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 545.879 | 0 | 20 | 20 | 15 | 15 | 15 | 525.879 | 4% |
3% January - 2019 |
LOA has been issued to the constractors. |
No Image |
1022 (OG) |
140889-F/S, Construction & BT of Road i/c Bridge from Pir Qala to Major Qala and Shabqadar Bazar to Kangra, Charsadda (14 Km). |
Charsadda |
24-04-05 | - | - | 21-01-16 | - | 350.459 | 251.365 | 60 | 60 | 45 | 30 | 281.365 | 39.094 | 89% |
80% December - 2017 |
Length 10 Km - 4 Km asphalt completed. 2nd Revised PC-I/DCE for RS.401.200 m submitted to P&D. |
No Image |
1022 (OG) |
140889-F/S, Construction & BT of Road i/c Bridge from Pir Qala to Major Qala and Shabqadar Bazar to Kangra, Charsadda (14 Km). |
Charsadda |
24-04-05 | - | - | 21-01-16 | - | 350.459 | 251.365 | 60 | 60 | 21.3 | 0 | 251.365 | 39.094 | 89% |
72% September - 2017 |
Length 10 Km - 4 Km asphalt completed. |
No Image |
1022 (OG) |
140889-F/S, Construction & BT of Road i/c Bridge from Pir Qala to Major Qala and Shabqadar Bazar to Kangra, Charsadda (14 Km). |
Charsadda |
24-04-05 | - | - | 21-01-16 | - | 350.459 | 251.365 | 60 | 60 | 21.3 | 0 | 251.365 | 39.094 | 89% |
72% August - 2017 |
Length 10 Km - 4 Km asphalt completed. |
No Image |
1022 (OG) |
140889-F/S, Construction & BT of Road i/c Bridge from Pir Qala to Major Qala and Shabqadar Bazar to Kangra, Charsadda (14 Km). |
Charsadda |
24-04-05 | - | - | 21-01-16 | - | 350.459 | 251.365 | 60 | 60 | 21.3 | 0 | 251.365 | 39.094 | 89% |
72% July - 2017 |
Length 10 Km - 4 Km asphalt completed. |
No Image |
1022 (OG) |
140889-F/S, Construction & BT of Road i/c Bridge from Pir Qala to Major Qala and Shabqadar Bazar to Kangra, Charsadda (14 Km). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 350.459 | 251.365 | 60 | 60 | 30 | 30 | 281.365 | 39.094 | 89% |
80% November - 2017 |
Length 10 Km - 4 Km asphalt completed. 2nd Revised PC-I/DCE for RS.401.200 m submitted to P&D. |
No Image |
1022 (OG) |
140889-F/S, Construction & BT of Road i/c Bridge from Pir Qala to Major Qala and Shabqadar Bazar to Kangra, Charsadda (14 Km). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 350.459 | 251.365 | 60 | 60 | 21.3 | 0 | 251.365 | 39.094 | 89% |
72% October - 2017 |
Length 10 Km - 4 Km asphalt completed. |
No Image |
1022 (OG) |
140889-F/S, Construction & BT of Road i/c Bridge from Pir Qala to Major Qala and Shabqadar Bazar to Kangra, Charsadda (14 Km). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 401.195 | 251.375 | 60 | 67.683 | 67.683 | 67.683 | 319.058 | 89.82 | 78% |
80% June - 2018 |
Length 10 Km (width 12 ft) - 4 Km asphalt completed. |
No Image |
1. Kangra Road (6 Km) width 12 ft
2. Byapss road from Pir Kally to Major Kally (Length - 6 Km width 18 ft ) | |||||||||||||||||||
1022 (OG) |
140889-F/S, Construction & BT of Road i/c Bridge from Pir Qala to Major Qala and Shabqadar Bazar to Kangra, Charsadda (14 Km). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 401.195 | 251.375 | 60 | 70.373 | 70.373 | 67.683 | 319.058 | 89.82 | 78% |
80% May - 2018 |
Length 10 Km (width 12 ft) - 4 Km asphalt completed. |
No Image |
1. Kangra Road (6 Km) width 12 ft
2. Byapss road from Pir Kally to Major Kally (Length - 6 Km width 18 ft ) | |||||||||||||||||||
1022 (OG) |
140889-F/S, Construction & BT of Road i/c Bridge from Pir Qala to Major Qala and Shabqadar Bazar to Kangra, Charsadda (14 Km). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 401.195 | 251.375 | 60 | 70.373 | 70.373 | 67.683 | 319.058 | 89.82 | 78% |
80% April - 2018 |
Length 10 Km (width 12 ft) - 4 Km asphalt completed. |
No Image |
1. Kangra Road (6 Km) width 12 ft
2. Byapss road from Pir Kally to Major Kally (Length - 6 Km width 18 ft ) | |||||||||||||||||||
1022 (OG) |
140889-F/S, Construction & BT of Road i/c Bridge from Pir Qala to Major Qala and Shabqadar Bazar to Kangra, Charsadda (14 Km). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 401.195 | 251.375 | 60 | 67.663 | 67.683 | 67.683 | 319.058 | 89.82 | 78% |
80% March - 2018 |
Length 10 Km (width 12 ft) - 4 Km asphalt completed. |
No Image |
1. Kangra Road (6 Km) width 12 ft
2. Byapss road from Pir Kally to Major Kally (Length - 6 Km width 18 ft ) | |||||||||||||||||||
1022 (OG) |
140889-F/S, Construction & BT of Road i/c Bridge from Pir Qala to Major Qala and Shabqadar Bazar to Kangra, Charsadda (14 Km). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 401.195 | 251.375 | 60 | 67.663 | 67.683 | 67.683 | 319.058 | 89.82 | 78% |
80% February - 2018 |
Length 10 Km (width 12 ft) - 4 Km asphalt completed. |
ADP's Images |
1. Kangra Road (6 Km) width 12 ft
2. Byapss road from Pir Kally to Major Kally (Length - 6 Km width 18 ft ) | |||||||||||||||||||
1022 (OG) |
140889-F/S, Construction & BT of Road i/c Bridge from Pir Qala to Major Qala and Shabqadar Bazar to Kangra, Charsadda (14 Km). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 401.195 | 251.365 | 60 | 67.663 | 67.683 | 30 | 281.365 | 89.83 | 78% |
70% January - 2018 |
Length 10 Km - 4 Km asphalt completed. |
No Image |
PK-22 Charsadda | |||||||||||||||||||
1022 (New) |
190511-F/S and detailed design of Peshawar - D.I.Khan Motorway.(320 Km). |
D.I.Khan PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 320 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- December - 2019 |
PC-II approved. (M/S Pavron).
F/S in progress. |
No Image |
1022 (New) |
190511-F/S and detailed design of Peshawar - D.I.Khan Motorway.(320 Km). |
D.I.Khan PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 320 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- November - 2019 |
PC-II approved. (M/S Pavron).
F/S in progress. |
No Image |
1022 (New) |
190511-F/S and detailed design of Peshawar - D.I.Khan Motorway.(320 Km). |
D.I.Khan PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 320 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- October - 2019 |
PC-II approved. (M/S Pavron).
F/S in progress. |
No Image |
1022 (New) |
190511-F/S and detailed design of Peshawar - D.I.Khan Motorway.(320 Km). |
D.I.Khan PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 320 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- September - 2019 |
RFP for FS and design invited. Financial opening on 14/10/2019. of consultnats |
No Image |
1022 (New) |
190511-F/S and detailed design of Peshawar - D.I.Khan Motorway.(320 Km). |
D.I.Khan PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 320 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- August - 2019 |
RFP for FS and design invited on 22/09/2019. |
No Image |
1022 (New) |
190511-F/S and detailed design of Peshawar - D.I.Khan Motorway.(320 Km). |
D.I.Khan PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 320 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- May - 2020 |
PC-II approved. (M/S Pavron).
F/S in progress. Survey work in progress. |
No Image |
1022 (New) |
190511-F/S and detailed design of Peshawar - D.I.Khan Motorway.(320 Km). |
D.I.Khan PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 320 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- April - 2020 |
PC-II approved. (M/S Pavron).
F/S in progress. Survey work in progress. |
No Image |
1022 (New) |
190511-F/S and detailed design of Peshawar - D.I.Khan Motorway.(320 Km). |
D.I.Khan PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 320 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- March - 2020 |
PC-II approved. (M/S Pavron).
F/S in progress. Survey work in progress. |
No Image |
1022 (New) |
190511-F/S and detailed design of Peshawar - D.I.Khan Motorway.(320 Km). |
D.I.Khan PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 320 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- February - 2020 |
PC-II approved. (M/S Pavron).
F/S in progress. Survey work in progress. |
No Image |
1022 (New) |
190511-F/S and detailed design of Peshawar - D.I.Khan Motorway.(320 Km). |
D.I.Khan PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 320 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- January - 2020 |
PC-II approved. (M/S Pavron).
F/S in progress. Survey work in progress. |
No Image |
1022 (OG) |
140132-Re-Construction of District Jail Swat. |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 707 | 420.683 | 150 | 150 | 131.25 | 99.508 | 520.191 | 136.317 | 81% |
74% December - 2020 |
Main building - Plaster work completed.
Jail portion completion in December 2020.
Residential Portion completion - June 2021. |
No Image |
District Jail Swat | |||||||||||||||||||
1022 (OG) |
140132-Re-Construction of District Jail Swat. |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 707 | 420.683 | 150 | 150 | 131.25 | 99.508 | 520.191 | 136.317 | 81% |
74% December - 2020 |
Main building - Plaster work completed.
Jail portion completion in December 2020.
Residential Portion completion - June 2021. |
No Image |
District Jail Swat | |||||||||||||||||||
1022 (OG) |
140132-Re-Construction of District Jail Swat. |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 707 | 420.683 | 150 | 150 | 112.5 | 37.499 | 458.182 | 136.317 | 81% |
65% October - 2020 |
Main building - Plaster work completed.
Jail portion completion in December 2020.
Residential Portion completion - June 2021. |
No Image |
District Jail Swat | |||||||||||||||||||
1022 (OG) |
140132-Re-Construction of District Jail Swat. |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 707 | 420.683 | 150 | 150 | 37.5 | 36.985 | 457.668 | 136.317 | 81% |
65% September - 2020 |
Main building - Plaster work completed.
Jail portion completion in December 2020.
Residential Portion completion - June 2021. |
No Image |
District Jail Swat | |||||||||||||||||||
1022 (OG) |
140132-Re-Construction of District Jail Swat. |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 707 | 420.683 | 150 | 150 | 37.5 | 0 | 420.683 | 136.317 | 81% |
60% August - 2020 |
Main building - Plaster work completed.
Flooring |
No Image |
District Jail Swat | |||||||||||||||||||
1022 (OG) |
140132-Re-Construction of District Jail Swat. |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 707 | 420.683 | 150 | 0 | 0 | 0 | 420.683 | 136.317 | 81% |
60% July - 2020 |
Main building - Plaster work completed.
Flooring |
No Image |
District Jail Swat | |||||||||||||||||||
1022 (OG) |
140132-Re-Construction of District Jail Swat. |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 707 | 334.399 | 150 | 190 | 190 | 109.626 | 444.025 | 222.601 | 69% |
63% May - 2021 |
Adminstration Block - Completed
Hospital Block - Completed
Head Wardan Office - Completed
Juvenile prisoners Block - Completed
Female prionser Block - Completed
Presioner Cock House - Completed
Class-12 prsioners Barrack - Completed
Under trail prsioners Barrack - Completed
Convicted Prionsers Barrack - F/F slab laid
Condemned prisoners Barrack - G/F in progress
Staff residence apartment Block-I - plastering in progress
Staff residence apartment Block-II - F/F slab laid
Mosque Super Strcture in progress
Main Enterance/ Reception - 95% completed
Dev: work in progress |
No Image |
1. Civil Package-I
2. Civil Package-II
3. Consultancy
4. UET Peshawar
5. WAPDA | |||||||||||||||||||
1022 (OG) |
140132-Re-Construction of District Jail Swat. |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 707 | 334.399 | 150 | 190 | 190 | 109.626 | 444.025 | 222.601 | 69% |
63% April - 2021 |
Adminstration Block - Completed
Hospital Block - Completed
Head Wardan Office - Completed
Juvenile prisoners Block - Completed
Female prionser Block - Completed
Presioner Cock House - Completed
Class-12 prsioners Barrack - Completed
Under trail prsioners Barrack - Completed
Convicted Prionsers Barrack - F/F slab laid
Condemned prisoners Barrack - G/F in progress
Staff residence apartment Block-I - plastering in progress
Staff residence apartment Block-II - F/F slab laid
Mosque Super Strcture in progress
Main Enterance/ Reception - 95% completed
Dev: work in progress |
No Image |
1. Civil Package-I
2. Civil Package-II
3. Consultancy
4. UET Peshawar
5. WAPDA | |||||||||||||||||||
1022 (OG) |
140132-Re-Construction of District Jail Swat. |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 707 | 334.399 | 150 | 190 | 190 | 109.626 | 444.025 | 222.601 | 69% |
63% March - 2021 |
Adminstration Block - Completed
Hospital Block - Completed
Head Wardan Office - Completed
Juvenile prisoners Block - Completed
Female prionser Block - Completed
Presioner Cock House - Completed
Class-12 prsioners Barrack - Completed
Under trail prsioners Barrack - Completed
Convicted Prionsers Barrack - F/F slab laid
Condemned prisoners Barrack - G/F in progress
Staff residence apartment Block-I - plastering in progress
Staff residence apartment Block-II - F/F slab laid
Mosque Super Strcture in progress
Main Enterance/ Reception - 95% completed
Dev: work in progress |
No Image |
1. Civil Package-I
2. Civil Package-II
3. Consultancy
4. UET Peshawar
5. WAPDA | |||||||||||||||||||
1022 (OG) |
140132-Re-Construction of District Jail Swat. |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 707 | 334.399 | 150 | 190 | 190 | 108.434 | 442.833 | 222.601 | 69% |
63% February - 2021 |
Adminstration Block - Completed
Hospital Block - Completed
Head Wardan Office - Completed
Juvenile prisoners Block - Completed
Female prionser Block - Completed
Presioner Cock House - Completed
Class-12 prsioners Barrack - Completed
Under trail prsioners Barrack - Completed
Convicted Prionsers Barrack - F/F slab laid
Condemned prisoners Barrack - G/F in progress
Staff residence apartment Block-I - plastering in progress
Staff residence apartment Block-II - F/F slab laid
Mosque Super Strcture in progress
Main Enterance/ Reception - 95% completed
Dev: work in progress |
No Image |
1. Civil Package-I
2. Civil Package-II
3. Consultancy
4. UET Peshawar
5. WAPDA | |||||||||||||||||||
1022 (OG) |
140132-Re-Construction of District Jail Swat. |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 707 | 420.683 | 150 | 131.25 | 131.25 | 108.434 | 529.117 | 136.317 | 81% |
75% January - 2021 |
Main building - Plaster work completed.
Jail portion completion in December 2020.
Residential Portion completion - June 2021. |
No Image |
District Jail Swat | |||||||||||||||||||