Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2020, January - 2021, January - 2018, January - 2019, February - 2020, February - 2021, February - 2018, February - 2019, March - 2020, March - 2021, March - 2018, March - 2019, April - 2020, April - 2021, April - 2018, April - 2019, May - 2020, May - 2021, May - 2018, June - 2018, July - 2020, July - 2017, August - 2019, August - 2020, August - 2017, September - 2019, September - 2020, September - 2017, October - 2019, October - 2020, October - 2017, November - 2019, November - 2017, November - 2018, December - 2019, December - 2020, December - 2017, December - 2018,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
102
(OG)
120870-Continuing Professional Development of Engineers.
Peshawar
CS
- 30-06-18 - 04-07-12 - 2.23 2.808 0.878 0.878 0.395 0 2.808 0 100% 100%
December - 2017
Work in progress.
No Image
102
(OG)
120870-Continuing Professional Development of Engineers.
Peshawar
CS
30-11--1 30-11--1 - 30-11--1 - 2.23 2.808 0.878 0.878 0.395 0 2.808 0 100% 100%
November - 2017
Work in progress.
No Image
102
(OG)
120870-Continuing Professional Development of Engineers.
Peshawar
CS
30-11--1 30-11--1 - 30-11--1 - 2.23 2.808 0.878 0.878 0.395 0 2.808 0 100% 100%
October - 2017
Work in progress.
No Image
102
(OG)
120870-Continuing Professional Development of Engineers.
Peshawar
CS
- 30-06-18 - 04-07-12 - 2.23 2.808 0.878 0.878 0.395 0 2.808 0 100% 100%
September - 2017
Work in progress.
No Image
102
(OG)
120870-Continuing Professional Development of Engineers.
Peshawar
CS
- 30-06-18 - 04-07-12 - 2.23 2.808 0.878 0.878 0.395 0 2.808 0 100% 100%
August - 2017
Work in progress.
No Image
102
(OG)
120870-Continuing Professional Development of Engineers.
Peshawar
CS
- 30-06-18 - 04-07-12 - 2.23 2.808 0.878 0.878 0.395 0 2.808 0 100% 100%
July - 2017
Work in progress.
No Image
102
(OG)
120870-Continuing Professional Development of Engineers.
Peshawar
CS
30-11--1 30-11--1 - 30-11--1 - 2.23 2.808 0.878 0.878 0.395 0 2.808 0 100% 100%
June - 2018
Work in progress.
No Image
102
(OG)
120870-Continuing Professional Development of Engineers.
Peshawar
CS
30-11--1 30-11--1 - 30-11--1 - 2.23 2.808 0.878 0.878 0.395 0 2.808 0 100% 100%
May - 2018
Work in progress.
No Image
102
(OG)
120870-Continuing Professional Development of Engineers.
Peshawar
CS
30-11--1 30-11--1 - 30-11--1 - 2.23 2.808 0.878 0.878 0.395 0 2.808 0 100% 100%
April - 2018
Work in progress.
No Image
102
(OG)
120870-Continuing Professional Development of Engineers.
Peshawar
CS
30-11--1 30-11--1 - 30-11--1 - 2.23 2.808 0.878 0.878 0.395 0 2.808 0 100% 100%
March - 2018
Work in progress.
No Image
102
(OG)
120870-Continuing Professional Development of Engineers.
Peshawar
CS
30-11--1 30-11--1 - 30-11--1 - 2.23 2.808 0.878 0.878 0.395 0 2.808 0 100% 100%
February - 2018
Work in progress.
No Image
102
(OG)
120870-Continuing Professional Development of Engineers.
Peshawar
CS
30-11--1 30-11--1 - 30-11--1 - 2.23 2.808 0.878 0.878 0.395 0 2.808 0 100% 100%
January - 2018
Work in progress.
No Image
102
(OG)
140750-F/S, Design for rehabilitation and Emergent Nature works in Governor?s House Peshawar and Governor?s House Nathiagali.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 183.194 160.406 28.566 28.566 28.566 12.154 172.56 0 100% 94%
December - 2018
Governor House Peshawar - police baraks renovation completed, 48 Nos quarters renovation completed, controller office finisihing in progress. Governor House Nathiagali - repair and reterofitting completed, RW, ADC house foundation in progress.
No Image
1) Governor House Peshawar (rehabilitation works, Comptroller House, office building)
2) Governor House Nathiagali (rehabilitaion works, ADC house, store rehabilitation)
102
(OG)
140750-F/S, Design for rehabilitation and Emergent Nature works in Governor?s House Peshawar and Governor?s House Nathiagali.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 183.194 160.406 28.566 28.566 28.566 12.154 172.56 0 100% 94%
November - 2018
Governor House Peshawar - police baraks renovation completed, 48 Nos quarters renovation completed, controller office finisihing in progress. Governor House Nathiagali - repair and reterofitting completed, RW, ADC house foundation in progress.
No Image
1) Governor House Peshawar (rehabilitation works, Comptroller House, office building)
2) Governor House Nathiagali (rehabilitaion works, ADC house, store rehabilitation)
102
(OG)
140750-F/S, Design for rehabilitation and Emergent Nature works in Governor?s House Peshawar and Governor?s House Nathiagali.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 183.194 160.406 28.566 28.566 28.566 12.154 172.56 0 100% 94%
November - 2018
Governor House Peshawar - police baraks renovation completed, 48 Nos quarters renovation completed, controller office finisihing in progress. Governor House Nathiagali - repair and reterofitting completed, RW, ADC house foundation in progress.
No Image
1) Governor House Peshawar (rehabilitation works, Comptroller House, office building)
2) Governor House Nathiagali (rehabilitaion works, ADC house, store rehabilitation)
102
(OG)
140750-F/S, Design for rehabilitation and Emergent Nature works in Governor?s House Peshawar and Governor?s House Nathiagali.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 183.194 160.406 28.566 28.566 28.566 12.154 172.56 0 100% 94%
April - 2019
Governor House Peshawar - police baraks renovation completed, 48 Nos quarters renovation completed, controller office finisihing in progress. Governor House Nathiagali - repair and reterofitting completed, RW, ADC house foundation in progress.
No Image
1) Governor House Peshawar (rehabilitation works, Comptroller House, office building)
2) Governor House Nathiagali (rehabilitaion works, ADC house, store rehabilitation)
102
(OG)
140750-F/S, Design for rehabilitation and Emergent Nature works in Governor?s House Peshawar and Governor?s House Nathiagali.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 183.194 160.406 28.566 28.566 28.566 12.154 172.56 0 100% 94%
March - 2019
Governor House Peshawar - police baraks renovation completed, 48 Nos quarters renovation completed, controller office finisihing in progress. Governor House Nathiagali - repair and reterofitting completed, RW, ADC house foundation in progress.
No Image
1) Governor House Peshawar (rehabilitation works, Comptroller House, office building)
2) Governor House Nathiagali (rehabilitaion works, ADC house, store rehabilitation)
102
(OG)
140750-F/S, Design for rehabilitation and Emergent Nature works in Governor?s House Peshawar and Governor?s House Nathiagali.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 183.194 160.406 28.566 28.566 28.566 12.154 172.56 0 100% 94%
March - 2019
Governor House Peshawar - police baraks renovation completed, 48 Nos quarters renovation completed, controller office finisihing in progress. Governor House Nathiagali - repair and reterofitting completed, RW, ADC house foundation in progress.
No Image
1) Governor House Peshawar (rehabilitation works, Comptroller House, office building)
2) Governor House Nathiagali (rehabilitaion works, ADC house, store rehabilitation)
102
(OG)
140750-F/S, Design for rehabilitation and Emergent Nature works in Governor?s House Peshawar and Governor?s House Nathiagali.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 183.194 160.406 28.566 28.566 28.566 12.154 172.56 0 100% 94%
February - 2019
Governor House Peshawar - police baraks renovation completed, 48 Nos quarters renovation completed, controller office finisihing in progress. Governor House Nathiagali - repair and reterofitting completed, RW, ADC house foundation in progress.
No Image
1) Governor House Peshawar (rehabilitation works, Comptroller House, office building)
2) Governor House Nathiagali (rehabilitaion works, ADC house, store rehabilitation)
102
(OG)
140750-F/S, Design for rehabilitation and Emergent Nature works in Governor?s House Peshawar and Governor?s House Nathiagali.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 183.194 160.406 28.566 28.566 28.566 12.154 172.56 0 100% 94%
January - 2019
Governor House Peshawar - police baraks renovation completed, 48 Nos quarters renovation completed, controller office finisihing in progress. Governor House Nathiagali - repair and reterofitting completed, RW, ADC house foundation in progress.
No Image
1) Governor House Peshawar (rehabilitation works, Comptroller House, office building)
2) Governor House Nathiagali (rehabilitaion works, ADC house, store rehabilitation)
102
(OG)
140651-Construction of office Building for Chief Engineer PHED.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 153.268 126.577 26.691 26.691 26.691 7.214 133.791 0 100% 87%
December - 2019
1st floor/2nd floor - interior finishing in progress. Balance work -50% Work completed.
No Image
Hayatabad Peshawar
102
(OG)
140651-Construction of office Building for Chief Engineer PHED.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 153.268 126.577 26.691 26.691 6.673 6.475 133.052 0 100% 87%
November - 2019
1st floor/2nd floor - interior finishing in progress. Balance work -50% Work completed.
No Image
Hayatabad Peshawar
102
(OG)
140651-Construction of office Building for Chief Engineer PHED.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 153.268 126.577 26.691 26.691 6.673 6.475 133.052 0 100% 87%
October - 2019
1st floor/2nd floor - interior finishing in progress. Balance work -50% Work completed.
No Image
Hayatabad Peshawar
102
(OG)
140651-Construction of office Building for Chief Engineer PHED.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 153.268 126.577 26.691 26.691 6.673 0 126.577 0 100% 83%
September - 2019
1st floor/2nd floor - interior finishing in progress. Balance work -20% Work completed.
No Image
Hayatabad Peshawar
102
(OG)
140651-Construction of office Building for Chief Engineer PHED.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 153.268 126.577 26.691 26.691 26.691 8.423 135 0 100% 88%
May - 2020
1st floor/2nd floor - interior finishing in progress. Balance work -70% completed. Will be Completed
No Image
Hayatabad Peshawar
102
(OG)
140651-Construction of office Building for Chief Engineer PHED.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 153.268 126.577 26.691 26.691 26.691 8.423 135 0 100% 88%
April - 2020
1st floor/2nd floor - interior finishing in progress. Balance work -70% completed. Will be Completed
No Image
Hayatabad Peshawar
102
(OG)
140651-Construction of office Building for Chief Engineer PHED.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 153.268 126.577 26.691 26.691 26.691 8.423 135 0 100% 88%
March - 2020
1st floor/2nd floor - interior finishing in progress. Balance work -70% completed. Will be Completed
No Image
Hayatabad Peshawar
102
(OG)
140651-Construction of office Building for Chief Engineer PHED.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 153.268 126.577 26.691 26.691 26.691 8.423 135 0 100% 88%
February - 2020
1st floor/2nd floor - interior finishing in progress. Balance work -70% completed. Will be Completed
No Image
Hayatabad Peshawar
102
(OG)
140651-Construction of office Building for Chief Engineer PHED.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 153.268 126.577 26.691 26.691 26.691 7.214 133.791 0 100% 87%
January - 2020
1st floor/2nd floor - interior finishing in progress. Balance work -70% completed. Will be Completed
No Image
Hayatabad Peshawar
102
(OG)
191063-180065 - Evaluation of Livestock Sector Initiatives since 2002 through Academia(PC-V). [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 10 0 0 0 0 0 0 0 - -
December - 2020
No Image
102
(OG)
191063-180065 - Evaluation of Livestock Sector Initiatives since 2002 through Academia(PC-V). [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 10 0 0 0 0 0 0 0 - -
December - 2020
No Image
102
(OG)
191063-180065 - Evaluation of Livestock Sector Initiatives since 2002 through Academia(PC-V). [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 10 0 0 0 0 0 0 0 - -
October - 2020
No Image
102
(OG)
191063-180065 - Evaluation of Livestock Sector Initiatives since 2002 through Academia(PC-V). [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 10 0 0 0 0 0 0 0 - -
September - 2020
No Image
102
(OG)
191063-180065 - Evaluation of Livestock Sector Initiatives since 2002 through Academia(PC-V). [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 10 0 0 0 0 0 0 0 - -
August - 2020
No Image
102
(OG)
191063-180065 - Evaluation of Livestock Sector Initiatives since 2002 through Academia(PC-V). [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 10 0 0 0 0 0 0 0 - -
July - 2020
No Image
102
(OG)
191063-180065 - Evaluation of Livestock Sector Initiatives since 2002 through Academia(PC-V). [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 10 0 0 0 0 0 0 0 - -
May - 2021
No Image
102
(OG)
191063-180065 - Evaluation of Livestock Sector Initiatives since 2002 through Academia(PC-V). [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 10 0 0 0 0 0 0 0 - -
April - 2021
No Image
102
(OG)
191063-180065 - Evaluation of Livestock Sector Initiatives since 2002 through Academia(PC-V). [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 10 0 0 0 0 0 0 0 - -
March - 2021
No Image
102
(OG)
191063-180065 - Evaluation of Livestock Sector Initiatives since 2002 through Academia(PC-V). [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 10 0 0 0 0 0 0 0 - -
February - 2021
No Image
102
(OG)
191063-180065 - Evaluation of Livestock Sector Initiatives since 2002 through Academia(PC-V). [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 10 0 0 0 0 0 0 0 - -
January - 2021
No Image
102
(OG)
140651-Construction of office Building for Chief Engineer PHED.
Provincial
PBC-2
30-11--1 30-11--1 - 30-11--1 - 153.268 126.577 26.691 26.691 6.673 0 126.577 0 100% 83%
August - 2019
1st floor/2nd floor - interior finishing in progress. Balance work -tendered Technical evaluation in progress.
No Image
Hayatabad Peshawar
Pages : 1