Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2020, January - 2021, January - 2018, January - 2019, February - 2020, February - 2021, February - 2018, February - 2019, March - 2020, March - 2021, March - 2018, March - 2019, April - 2020, April - 2021, April - 2018, April - 2019, May - 2020, May - 2021, May - 2018, June - 2018, July - 2020, July - 2017, August - 2019, August - 2020, August - 2017, September - 2019, September - 2020, September - 2017, October - 2019, October - 2020, October - 2017, November - 2019, November - 2017, November - 2018, December - 2019, December - 2020, December - 2017, December - 2018,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1019
(OG)
150287-Improvement of Takht-e-Bhai Rajjar Road from Ghani Khan road to Saro Shah (14 Km), District Charsadda.
Charsadda
PKHA
30-11--1 30-11--1 - 30-11--1 - 1498.019 271.7 20 20 15 10 281.7 1206.319 19% 19%
December - 2018
Work in progress on 2 Nos culverts. Trees and stumps removed. 5 Nos culverts in progress.
No Image
Package-1 (Ghani Khan Road to Munaf Kali)
Package-2 (Munaf Kali to Ahmadabad)
Package-3 (Ahmadabad to Saro Shah Bridge)
1019
(OG)
150287-Improvement of Takht-e-Bhai Rajjar Road from Ghani Khan road to Saro Shah (14 Km), District Charsadda.
Charsadda
PKHA
30-11--1 30-11--1 - 30-11--1 - 1498.019 271.7 20 20 15 10 281.7 1206.319 19% 19%
November - 2018
Work in progress on 2 Nos culverts. Trees and stumps removed. 5 Nos culverts in progress.
No Image
Package-1 (Ghani Khan Road to Munaf Kali)
Package-2 (Munaf Kali to Ahmadabad)
Package-3 (Ahmadabad to Saro Shah Bridge)
1019
(OG)
150287-Improvement of Takht-e-Bhai Rajjar Road from Ghani Khan road to Saro Shah (14 Km), District Charsadda.
Charsadda
PKHA
30-11--1 30-11--1 - 30-11--1 - 1498.019 271.7 20 20 15 10 281.7 1206.319 19% 19%
November - 2018
Work in progress on 2 Nos culverts. Trees and stumps removed. 5 Nos culverts in progress.
No Image
Package-1 (Ghani Khan Road to Munaf Kali)
Package-2 (Munaf Kali to Ahmadabad)
Package-3 (Ahmadabad to Saro Shah Bridge)
1019
(OG)
150287-Improvement of Takht-e-Bhai Rajjar Road from Ghani Khan road to Saro Shah (14 Km), District Charsadda.
Charsadda
PKHA
30-11--1 30-11--1 - 30-11--1 - 1498.019 271.7 20 20 20 20 291.7 1206.319 19% 19%
April - 2019
Work in progress on 2 Nos culverts. Trees and stumps removed. 5 Nos culverts in progress. Work stopeed due paucity of funds.
No Image
Package-1 (Ghani Khan Road to Munaf Kali)
Package-2 (Munaf Kali to Ahmadabad)
Package-3 (Ahmadabad to Saro Shah Bridge)
1019
(OG)
150287-Improvement of Takht-e-Bhai Rajjar Road from Ghani Khan road to Saro Shah (14 Km), District Charsadda.
Charsadda
PKHA
30-11--1 30-11--1 - 30-11--1 - 1498.019 271.7 20 20 20 20 291.7 1206.319 19% 19%
March - 2019
Work in progress on 2 Nos culverts. Trees and stumps removed. 5 Nos culverts in progress. Work stopeed due paucity of funds
No Image
Package-1 (Ghani Khan Road to Munaf Kali)
Package-2 (Munaf Kali to Ahmadabad)
Package-3 (Ahmadabad to Saro Shah Bridge)
1019
(OG)
150287-Improvement of Takht-e-Bhai Rajjar Road from Ghani Khan road to Saro Shah (14 Km), District Charsadda.
Charsadda
PKHA
30-11--1 30-11--1 - 30-11--1 - 1498.019 271.7 20 20 20 20 291.7 1206.319 19% 19%
March - 2019
Work in progress on 2 Nos culverts. Trees and stumps removed. 5 Nos culverts in progress. Work stopeed due paucity of funds
No Image
Package-1 (Ghani Khan Road to Munaf Kali)
Package-2 (Munaf Kali to Ahmadabad)
Package-3 (Ahmadabad to Saro Shah Bridge)
1019
(OG)
150287-Improvement of Takht-e-Bhai Rajjar Road from Ghani Khan road to Saro Shah (14 Km), District Charsadda.
Charsadda
PKHA
30-11--1 30-11--1 - 30-11--1 - 1498.019 271.7 20 20 20 20 291.7 1206.319 19% 19%
February - 2019
Work in progress on 2 Nos culverts. Trees and stumps removed. 5 Nos culverts in progress.
No Image
Package-1 (Ghani Khan Road to Munaf Kali)
Package-2 (Munaf Kali to Ahmadabad)
Package-3 (Ahmadabad to Saro Shah Bridge)
1019
(OG)
150287-Improvement of Takht-e-Bhai Rajjar Road from Ghani Khan road to Saro Shah (14 Km), District Charsadda.
Charsadda
PKHA
30-11--1 30-11--1 - 30-11--1 - 1498.019 271.7 20 20 15 15 286.7 1206.319 19% 19%
January - 2019
Work in progress on 2 Nos culverts. Trees and stumps removed. 5 Nos culverts in progress.
No Image
Package-1 (Ghani Khan Road to Munaf Kali)
Package-2 (Munaf Kali to Ahmadabad)
Package-3 (Ahmadabad to Saro Shah Bridge)
1019
(OG)
150272-Feasibilty Study and Construction of Central Prison D.I.Khan on existing Site (Phase-II)
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 812.996 260.474 100 100 50 27.173 287.647 452.522 44% 35%
December - 2020
Male section, female section, common building in progress. Demanded Rs. 100 M for The tempo of the work
No Image
DI.Khan
1019
(OG)
150272-Feasibilty Study and Construction of Central Prison D.I.Khan on existing Site (Phase-II)
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 812.996 260.474 100 100 50 27.173 287.647 452.522 44% 35%
December - 2020
Male section, female section, common building in progress. Demanded Rs. 100 M for The tempo of the work
No Image
DI.Khan
1019
(OG)
150272-Feasibilty Study and Construction of Central Prison D.I.Khan on existing Site (Phase-II)
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 812.996 260.474 100 100 25 17.814 278.288 452.522 44% 34%
October - 2020
Male section, female section, common building in progress. Demanded Rs. 100 M for The tempo of the work
No Image
DI.Khan
1019
(OG)
150272-Feasibilty Study and Construction of Central Prison D.I.Khan on existing Site (Phase-II)
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 812.996 260.474 100 100 25 17.1184 277.5924 452.522 44% 34%
September - 2020
Male section, female section, common building in progress. Demanded Rs. 100 M for The tempo of the work
No Image
DI.Khan
1019
(OG)
150272-Feasibilty Study and Construction of Central Prison D.I.Khan on existing Site (Phase-II)
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 812.996 260.474 100 0 0 0 260.474 452.522 44% 32%
July - 2020
Male section, female section, common building - in
No Image
DI.Khan
1019
(OG)
150272-Feasibilty Study and Construction of Central Prison D.I.Khan on existing Site (Phase-II)
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 812.996 0 100 50 50 28.537 0 0
May - 2021
Male section, female section, common building in progress. Demanded Rs. 100 M for The tempo of the work
No Image
DI.Khan
1019
(OG)
150272-Feasibilty Study and Construction of Central Prison D.I.Khan on existing Site (Phase-II)
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 812.996 0 100 50 50 28.537 0 0
April - 2021
Male section, female section, common building in progress. Demanded Rs. 100 M for The tempo of the work
No Image
DI.Khan
1019
(OG)
150272-Feasibilty Study and Construction of Central Prison D.I.Khan on existing Site (Phase-II)
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 812.996 0 100 50 50 27.173 0 0
March - 2021
Male section, female section, common building in progress. Demanded Rs. 100 M for The tempo of the work
No Image
DI.Khan
1019
(OG)
150272-Feasibilty Study and Construction of Central Prison D.I.Khan on existing Site (Phase-II)
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 812.996 0 100 50 50 27.173 0 0
February - 2021
Male section, female section, common building in progress. Demanded Rs. 100 M for The tempo of the work
No Image
DI.Khan
1019
(OG)
150272-Feasibilty Study and Construction of Central Prison D.I.Khan on existing Site (Phase-II)
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 812.996 260.474 100 100 50 27.173 287.647 452.522 44% 35%
January - 2021
Male section, female section, common building in progress. Demanded Rs. 100 M for The tempo of the work
No Image
DI.Khan
1019
(OG)
150272-Feasibilty Study and Construction of Central Prison D.I.Khan on existing Site (Phase-II)
DI.Khan
30-11--1 30-11--1 - 30-11--1 - 812.996 260.474 100 100 25 0 260.474 452.522 44% 32%
August - 2020
Male section, female section, common building - in? funds to the tune of Rs.100.000 (m) is required dtt?04/09/2020.
No Image
DI.Khan
1019
(OG)
150804-Construction / Rehabilitation of Chua Gujar road, Musazai Main road, Adda road Musazai, Sheikhan road Musazai, Eidgah road Musazai Faqirabad Chowk Towards Aziz Market, Warsak Canal & Frontier road, Afridi Abad road Sheikhan, Sheikhan Main road, Peshawar.
Peshawar
HW
11-02-16 30-06-18 - 28-08-15 - 50 13.962 35.788 35.788 35.788 27.344 41.306 0.25 100% 83%
December - 2017
Completed (4.5 Km).
No Image
1019
(OG)
150804-Construction / Rehabilitation of Chua Gujar road, Musazai Main road, Adda road Musazai, Sheikhan road Musazai, Eidgah road Musazai Faqirabad Chowk Towards Aziz Market, Warsak Canal & Frontier road, Afridi Abad road Sheikhan, Sheikhan Main road, Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 50 13.962 35.788 35.788 35.788 27.344 41.306 0.25 100% 83%
November - 2017
Completed (4.5 Km).
No Image
1019
(OG)
150804-Construction / Rehabilitation of Chua Gujar road, Musazai Main road, Adda road Musazai, Sheikhan road Musazai, Eidgah road Musazai Faqirabad Chowk Towards Aziz Market, Warsak Canal & Frontier road, Afridi Abad road Sheikhan, Sheikhan Main road, Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 50 13.962 35.788 35.788 35.788 27.344 41.306 0.25 100% 83%
October - 2017
Length 4.5 Km - 3 Km asphalt completed, remaining base course in progress.
No Image
1019
(OG)
150804-Construction / Rehabilitation of Chua Gujar road, Musazai Main road, Adda road Musazai, Sheikhan road Musazai, Eidgah road Musazai Faqirabad Chowk Towards Aziz Market, Warsak Canal & Frontier road, Afridi Abad road Sheikhan, Sheikhan Main road, Peshawar.
Peshawar
HW
11-02-16 30-06-18 - 28-08-15 - 50 13.962 35.788 35.788 35.788 21.47 35.432 0.25 100% 71%
September - 2017
Length 4.5 Km - 3 Km asphalt completed, remaining base course in progress.
No Image
1019
(OG)
150804-Construction / Rehabilitation of Chua Gujar road, Musazai Main road, Adda road Musazai, Sheikhan road Musazai, Eidgah road Musazai Faqirabad Chowk Towards Aziz Market, Warsak Canal & Frontier road, Afridi Abad road Sheikhan, Sheikhan Main road, Peshawar.
Peshawar
HW
11-02-16 30-06-18 - 28-08-15 - 50 13.962 35.788 35.788 17.894 12.705 26.667 0.25 100% 53%
August - 2017
Length 4.5 Km - 3 Km asphalt completed, remaining base course in progress.
No Image
1019
(OG)
150804-Construction / Rehabilitation of Chua Gujar road, Musazai Main road, Adda road Musazai, Sheikhan road Musazai, Eidgah road Musazai Faqirabad Chowk Towards Aziz Market, Warsak Canal & Frontier road, Afridi Abad road Sheikhan, Sheikhan Main road, Peshawar.
Peshawar
HW
11-02-16 30-06-18 - 28-08-15 - 50 13.962 35.788 35.788 12.705 12.705 26.667 0.25 100% 53%
July - 2017
Length 4.5 Km - 3 Km asphalt completed, remaining base course in progress.
No Image
1019
(OG)
150804-Construction / Rehabilitation of Chua Gujar road, Musazai Main road, Adda road Musazai, Sheikhan road Musazai, Eidgah road Musazai Faqirabad Chowk Towards Aziz Market, Warsak Canal & Frontier road, Afridi Abad road Sheikhan, Sheikhan Main road, Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 50 13.962 35.788 35.788 32.138 32.138 46.1 0.25 100% 92%
June - 2018
Completed (4.5 Km).
No Image
1) Sheikhano Main raod 1.1 Km
2) Khan Bahadar Mosque to Frontier road via Och W 1.9 Km
3) Masezai Canal road 1.3 Km
1019
(OG)
150804-Construction / Rehabilitation of Chua Gujar road, Musazai Main road, Adda road Musazai, Sheikhan road Musazai, Eidgah road Musazai Faqirabad Chowk Towards Aziz Market, Warsak Canal & Frontier road, Afridi Abad road Sheikhan, Sheikhan Main road, Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 50 13.962 35.788 35.788 32.138 32.138 46.1 0.25 100% 92%
May - 2018
Completed (4.5 Km).
No Image
1) Sheikhano Main raod 1.1 Km
2) Khan Bahadar Mosque to Frontier road via Och W 1.9 Km
3) Masezai Canal road 1.3 Km
1019
(OG)
150804-Construction / Rehabilitation of Chua Gujar road, Musazai Main road, Adda road Musazai, Sheikhan road Musazai, Eidgah road Musazai Faqirabad Chowk Towards Aziz Market, Warsak Canal & Frontier road, Afridi Abad road Sheikhan, Sheikhan Main road, Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 50 13.962 35.788 35.788 32.138 32.138 46.1 0.25 100% 92%
April - 2018
Completed (4.5 Km).
No Image
1) Sheikhano Main raod 1.1 Km
2) Khan Bahadar Mosque to Frontier road via Och W 1.9 Km
3) Masezai Canal road 1.3 Km
1019
(OG)
150804-Construction / Rehabilitation of Chua Gujar road, Musazai Main road, Adda road Musazai, Sheikhan road Musazai, Eidgah road Musazai Faqirabad Chowk Towards Aziz Market, Warsak Canal & Frontier road, Afridi Abad road Sheikhan, Sheikhan Main road, Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 50 13.962 35.788 35.788 32.138 32.138 46.1 0.25 100% 92%
March - 2018
Completed (4.5 Km).
No Image
1) Sheikhano Main raod 1.1 Km
2) Khan Bahadar Mosque to Frontier road via Och W 1.9 Km
3) Masezai Canal road 1.3 Km
1019
(OG)
150804-Construction / Rehabilitation of Chua Gujar road, Musazai Main road, Adda road Musazai, Sheikhan road Musazai, Eidgah road Musazai Faqirabad Chowk Towards Aziz Market, Warsak Canal & Frontier road, Afridi Abad road Sheikhan, Sheikhan Main road, Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 50 13.962 35.788 35.788 32.132 30.788 44.75 0.25 100% 90%
February - 2018
Completed (4.5 Km).
No Image
1) Sheikhano Main raod 1.1 Km
2) Khan Bahadar Mosque to Frontier road via Och W 1.9 Km
3) Masezai Canal road 1.3 Km
1019
(OG)
150804-Construction / Rehabilitation of Chua Gujar road, Musazai Main road, Adda road Musazai, Sheikhan road Musazai, Eidgah road Musazai Faqirabad Chowk Towards Aziz Market, Warsak Canal & Frontier road, Afridi Abad road Sheikhan, Sheikhan Main road, Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 50 13.962 35.788 35.788 35.788 30.786 44.748 0.25 100% 89%
January - 2018
Completed (4.5 Km).
No Image
1019
(New)
190560-Construction of BT road from Balakot on Malam Jabba-Manglawar road to Shangla Top (6 Km).
Shangla
PKHA
30-11--1 30-11--1 - 30-11--1 Line Deptt 390 0 10 10 0 0 0 0 - -
December - 2019
PC-II Approved. Awarded for F/S to NESPAK . Submitted to P&D . PDWP on 9/1/20
No Image
1019
(New)
190560-Construction of BT road from Balakot on Malam Jabba-Manglawar road to Shangla Top (6 Km).
Shangla
PKHA
30-11--1 30-11--1 - 30-11--1 Line Deptt 390 0 10 10 0 0 0 0 - -
November - 2019
PC-II Approved. Awarded for F/S to NESPAK . DCE submittd
No Image
1019
(New)
190560-Construction of BT road from Balakot on Malam Jabba-Manglawar road to Shangla Top (6 Km).
Shangla
PKHA
30-11--1 30-11--1 - 30-11--1 Line Deptt 390 0 10 10 0 0 0 0 - -
October - 2019
PC-II Approved. Awarded for F/S to NESPAK . DCE will be submittd within 30 days
No Image
1019
(New)
190560-Construction of BT road from Balakot on Malam Jabba-Manglawar road to Shangla Top (6 Km).
Shangla
PKHA
30-11--1 30-11--1 - 30-11--1 Line Deptt 390 0 10 10 0 0 0 0 - -
September - 2019
PC-II Approved. Awarded for F/S to NESPAK . DCE will be submittd within 45 days
No Image
1019
(New)
190560-Construction of BT road from Balakot on Malam Jabba-Manglawar road to Shangla Top (6 Km).
Shangla
PKHA
30-11--1 30-11--1 - 30-11--1 Line Deptt 390 0 10 10 0 0 0 0 - -
August - 2019
PC-II Approved. Awarded for F/S to NESPAK . DCE will be submittd within 45 days
No Image
1019
(New)
190560-Construction of BT road from Balakot on Malam Jabba-Manglawar road to Shangla Top (6 Km).
Shangla
PKHA
30-11--1 30-11--1 - 30-11--1 Line Deptt 390 0 10 10 0 0 0 0 - -
May - 2020
PC-II Approved. Awarded for F/S to NESPAK . Pre-qualificatio has been called on 25/02/2020.
No Image
1019
(New)
190560-Construction of BT road from Balakot on Malam Jabba-Manglawar road to Shangla Top (6 Km).
Shangla
PKHA
30-11--1 30-11--1 - 30-11--1 Line Deptt 390 0 10 10 0 0 0 0 - -
April - 2020
PC-II Approved. Awarded for F/S to NESPAK . Pre-qualificatio has been called on 25/02/2020.
No Image
1019
(New)
190560-Construction of BT road from Balakot on Malam Jabba-Manglawar road to Shangla Top (6 Km).
Shangla
PKHA
30-11--1 30-11--1 - 30-11--1 Line Deptt 390 0 10 10 0 0 0 0 - -
March - 2020
PC-II Approved. Awarded for F/S to NESPAK . Pre-qualificatio has been called on 25/02/2020.
No Image
1019
(New)
190560-Construction of BT road from Balakot on Malam Jabba-Manglawar road to Shangla Top (6 Km).
Shangla
PKHA
30-11--1 30-11--1 - 30-11--1 Line Deptt 390 0 10 10 0 0 0 0 - -
February - 2020
PC-II Approved. Awarded for F/S to NESPAK . Pre-qualificatio has been called on 25/02/2020.
No Image
1019
(New)
190560-Construction of BT road from Balakot on Malam Jabba-Manglawar road to Shangla Top (6 Km).
Shangla
PKHA
30-11--1 30-11--1 - 30-11--1 Line Deptt 390 0 10 10 0 0 0 0 - -
January - 2020
PC-II Approved. Awarded for F/S to NESPAK . Pre-qualificatio has been called on 25/02/2020.
No Image
Pages : 1