Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1017 (OG) |
120284-Dualization of Mardan Charsadda Road i/c Dargai Bypass and Rehabilitation of existing dual carriageway to Charsadda City Phase-II (14.5 Km), District Charsadda. |
Charsadda PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1394 | 1084.65 | 30 | 30 | 30 | 30 | 1114.65 | 279.35 | 80% |
80% December - 2018 |
10/14 Km completed, Dargai bypass (3 Km) in progress. |
No Image |
Package-1
Package-2
Package-3
Package-4
Package-5 | |||||||||||||||||||
1017 (OG) |
120284-Dualization of Mardan Charsadda Road i/c Dargai Bypass and Rehabilitation of existing dual carriageway to Charsadda City Phase-II (14.5 Km), District Charsadda. |
Charsadda PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1394 | 1084.65 | 30 | 30 | 30 | 30 | 1114.65 | 279.35 | 80% |
80% November - 2018 |
10/14 Km completed, Dargai bypass (3 Km) in progress. |
No Image |
Package-1
Package-2
Package-3
Package-4
Package-5 | |||||||||||||||||||
1017 (OG) |
120284-Dualization of Mardan Charsadda Road i/c Dargai Bypass and Rehabilitation of existing dual carriageway to Charsadda City Phase-II (14.5 Km), District Charsadda. |
Charsadda PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1394 | 1084.65 | 30 | 30 | 30 | 30 | 1114.65 | 279.35 | 80% |
80% November - 2018 |
10/14 Km completed, Dargai bypass (3 Km) in progress. |
No Image |
Package-1
Package-2
Package-3
Package-4
Package-5 | |||||||||||||||||||
1017 (OG) |
120284-Dualization of Mardan Charsadda Road i/c Dargai Bypass and Rehabilitation of existing dual carriageway to Charsadda City Phase-II (14.5 Km), District Charsadda. |
Charsadda PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1394 | 1084.65 | 30 | 30 | 30 | 30 | 1114.65 | 279.35 | 80% |
80% April - 2019 |
14/14 Km completed. Liability Rs.192 m. |
No Image |
Package-1
Package-2
Package-3
Package-4
Package-5 | |||||||||||||||||||
1017 (OG) |
120284-Dualization of Mardan Charsadda Road i/c Dargai Bypass and Rehabilitation of existing dual carriageway to Charsadda City Phase-II (14.5 Km), District Charsadda. |
Charsadda PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1394 | 1084.65 | 30 | 30 | 30 | 30 | 1114.65 | 279.35 | 80% |
80% March - 2019 |
14/14 Km completed. Liability Rs.192 m. |
No Image |
Package-1
Package-2
Package-3
Package-4
Package-5 | |||||||||||||||||||
1017 (OG) |
120284-Dualization of Mardan Charsadda Road i/c Dargai Bypass and Rehabilitation of existing dual carriageway to Charsadda City Phase-II (14.5 Km), District Charsadda. |
Charsadda PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1394 | 1084.65 | 30 | 30 | 30 | 30 | 1114.65 | 279.35 | 80% |
80% March - 2019 |
14/14 Km completed. Liability Rs.192 m. |
No Image |
Package-1
Package-2
Package-3
Package-4
Package-5 | |||||||||||||||||||
1017 (OG) |
120284-Dualization of Mardan Charsadda Road i/c Dargai Bypass and Rehabilitation of existing dual carriageway to Charsadda City Phase-II (14.5 Km), District Charsadda. |
Charsadda PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1394 | 1084.65 | 30 | 30 | 30 | 30 | 1114.65 | 279.35 | 80% |
80% February - 2019 |
14/14 Km completed. Liability Rs.192 m. |
No Image |
Package-1
Package-2
Package-3
Package-4
Package-5 | |||||||||||||||||||
1017 (OG) |
120284-Dualization of Mardan Charsadda Road i/c Dargai Bypass and Rehabilitation of existing dual carriageway to Charsadda City Phase-II (14.5 Km), District Charsadda. |
Charsadda PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1394 | 1084.65 | 30 | 30 | 30 | 30 | 1114.65 | 279.35 | 80% |
80% January - 2019 |
14/14 Km completed, Laibility rs. 192 M |
No Image |
Package-1
Package-2
Package-3
Package-4
Package-5 | |||||||||||||||||||
1017 (OG) |
150801-(a) Improvement / Rehabilitation of service roads from Northern bypass upto Akbar Pura and Jaba Daudzai village PK-09 to PK-13 (b) Const/Rehab. of Mian Gujar to Charsadda road via Damne Afgani, Kharakay and Shakarpura etc road, Peshawar. |
Peshawar HW |
18-03-16 | - | - | 03-11-16 | - | 200 | 88 | 50 | 42.75 | 30.25 | 27.172 | 115.172 | 62 | 69% |
58% December - 2017 |
Length 17 Km - 8.2 Km asphalt completed and on remaining structure work, base course work in progress. |
No Image |
1017 (OG) |
150801-(a) Improvement / Rehabilitation of service roads from Northern bypass upto Akbar Pura and Jaba Daudzai village PK-09 to PK-13 (b) Const/Rehab. of Mian Gujar to Charsadda road via Damne Afgani, Kharakay and Shakarpura etc road, Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 88 | 50 | 50 | 30.25 | 20.75 | 108.75 | 62 | 69% |
54% November - 2017 |
Length 17 Km - 8.2 Km asphalt completed and on remaining structure work, base course work in progress. |
No Image |
1017 (OG) |
150801-(a) Improvement / Rehabilitation of service roads from Northern bypass upto Akbar Pura and Jaba Daudzai village PK-09 to PK-13 (b) Const/Rehab. of Mian Gujar to Charsadda road via Damne Afgani, Kharakay and Shakarpura etc road, Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 88 | 50 | 50 | 30.25 | 17.75 | 105.75 | 62 | 69% |
53% October - 2017 |
Length 17 Km - 8.2 Km asphalt completed and on remaining structure work, base course work in progress. |
No Image |
1017 (OG) |
150801-(a) Improvement / Rehabilitation of service roads from Northern bypass upto Akbar Pura and Jaba Daudzai village PK-09 to PK-13 (b) Const/Rehab. of Mian Gujar to Charsadda road via Damne Afgani, Kharakay and Shakarpura etc road, Peshawar. |
Peshawar HW |
18-03-16 | - | - | 03-11-16 | - | 200 | 88 | 50 | 50 | 17.75 | 17.75 | 105.75 | 62 | 69% |
53% September - 2017 |
Length 17 Km - 8.2 Km asphalt completed and on remaining structure work, base course work in progress. |
No Image |
1017 (OG) |
150801-(a) Improvement / Rehabilitation of service roads from Northern bypass upto Akbar Pura and Jaba Daudzai village PK-09 to PK-13 (b) Const/Rehab. of Mian Gujar to Charsadda road via Damne Afgani, Kharakay and Shakarpura etc road, Peshawar. |
Peshawar HW |
18-03-16 | - | - | 03-11-16 | - | 200 | 88 | 50 | 50 | 17.75 | 17.75 | 105.75 | 62 | 69% |
53% August - 2017 |
Length 17 Km - 8.2 Km asphalt completed and on remaining structure work, base course work in progress. |
No Image |
1017 (OG) |
150801-(a) Improvement / Rehabilitation of service roads from Northern bypass upto Akbar Pura and Jaba Daudzai village PK-09 to PK-13 (b) Const/Rehab. of Mian Gujar to Charsadda road via Damne Afgani, Kharakay and Shakarpura etc road, Peshawar. |
Peshawar HW |
18-03-16 | - | - | 03-11-16 | - | 200 | 88 | 50 | 50 | 17.75 | 0 | 88 | 62 | 69% |
44% July - 2017 |
Length 17 Km - 5 Km asphalt, 7 Km base course completed and on remaining structure work, base course work in progress. |
No Image |
1017 (OG) |
150801-(a) Improvement / Rehabilitation of service roads from Northern bypass upto Akbar Pura and Jaba Daudzai village PK-09 to PK-13 (b) Const/Rehab. of Mian Gujar to Charsadda road via Damne Afgani, Kharakay and Shakarpura etc road, Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 88 | 50 | 75.318 | 75.318 | 75.318 | 163.318 | 62 | 69% |
82% June - 2018 |
Length 17 Km - 13 Km asphalt completed and only 3 Km premix remaining in balance portion of service road. |
No Image |
1017 (OG) |
150801-(a) Improvement / Rehabilitation of service roads from Northern bypass upto Akbar Pura and Jaba Daudzai village PK-09 to PK-13 (b) Const/Rehab. of Mian Gujar to Charsadda road via Damne Afgani, Kharakay and Shakarpura etc road, Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 88 | 50 | 75.318 | 75.318 | 75.318 | 163.318 | 62 | 69% |
82% May - 2018 |
Length 17 Km - 13 Km asphalt completed and only 3 Km premix remaining in balance portion of service road. Rs.50 m demanded for tempo of work. |
No Image |
1017 (OG) |
150801-(a) Improvement / Rehabilitation of service roads from Northern bypass upto Akbar Pura and Jaba Daudzai village PK-09 to PK-13 (b) Const/Rehab. of Mian Gujar to Charsadda road via Damne Afgani, Kharakay and Shakarpura etc road, Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 88 | 50 | 75.318 | 75.318 | 75.318 | 163.318 | 62 | 69% |
82% April - 2018 |
Length 17 Km - 13 Km asphalt completed and on remaining structure work, base course work in progress. Rs.69.500 m demanded for tempo of work. |
No Image |
1017 (OG) |
150801-(a) Improvement / Rehabilitation of service roads from Northern bypass upto Akbar Pura and Jaba Daudzai village PK-09 to PK-13 (b) Const/Rehab. of Mian Gujar to Charsadda road via Damne Afgani, Kharakay and Shakarpura etc road, Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 88 | 50 | 75.318 | 75.318 | 75.318 | 163.318 | 62 | 69% |
82% March - 2018 |
Length 17 Km - 13 Km asphalt completed and on remaining structure work, base course work in progress. Rs.69.500 m demanded for tempo of work. |
No Image |
1017 (OG) |
150801-(a) Improvement / Rehabilitation of service roads from Northern bypass upto Akbar Pura and Jaba Daudzai village PK-09 to PK-13 (b) Const/Rehab. of Mian Gujar to Charsadda road via Damne Afgani, Kharakay and Shakarpura etc road, Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 88 | 50 | 72.628 | 72.628 | 46.58 | 134.58 | 62 | 69% |
67% February - 2018 |
Length 17 Km - 9 Km asphalt completed and on remaining structure work, base course work in progress. Rs.69.500 m demanded for tempo of work. |
No Image |
PK-09/PK-13 Peshawar | |||||||||||||||||||
1017 (OG) |
150801-(a) Improvement / Rehabilitation of service roads from Northern bypass upto Akbar Pura and Jaba Daudzai village PK-09 to PK-13 (b) Const/Rehab. of Mian Gujar to Charsadda road via Damne Afgani, Kharakay and Shakarpura etc road, Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 88 | 50 | 72.628 | 72.628 | 30.25 | 118.25 | 62 | 69% |
59% January - 2018 |
Length 17 Km - 9 Km asphalt completed and on remaining structure work, base course work in progress. Rs.69.500 m demanded for tempo of work. |
No Image |
1017 (New) |
190142-E-Enablement of Special Branch Phase-II |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 109.809 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
1017 (New) |
190142-E-Enablement of Special Branch Phase-II |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 109.809 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
1017 (New) |
190142-E-Enablement of Special Branch Phase-II |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 109.809 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
No Image | |
1017 (New) |
190142-E-Enablement of Special Branch Phase-II |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 109.809 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
No Image | |
1017 (New) |
190142-E-Enablement of Special Branch Phase-II |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 109.809 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- August - 2020 |
No Image | |
1017 (New) |
190142-E-Enablement of Special Branch Phase-II |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 109.809 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- July - 2020 |
No Image | |
1017 (New) |
190142-E-Enablement of Special Branch Phase-II |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 109.809 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
No Image | |
1017 (New) |
190142-E-Enablement of Special Branch Phase-II |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 109.809 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- April - 2021 |
No Image | |
1017 (New) |
190142-E-Enablement of Special Branch Phase-II |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 109.809 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- March - 2021 |
No Image | |
1017 (New) |
190142-E-Enablement of Special Branch Phase-II |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 109.809 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- February - 2021 |
No Image | |
1017 (New) |
190142-E-Enablement of Special Branch Phase-II |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 109.809 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- January - 2021 |
No Image | |
1017 (New) |
190531-F/S, Detailed Engg and Construction of Swat Expressway from Chakdarra to Fatehpur (Phase-II) (IDA Assisted). |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- December - 2019 |
PC-II Approved . (M/S Pavron) PC-I/DCE under preparation. Alignment finalized by HCM. DCE Submitted to PKHA |
No Image |
1017 (New) |
190531-F/S, Detailed Engg and Construction of Swat Expressway from Chakdarra to Fatehpur (Phase-II) (IDA Assisted). |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- November - 2019 |
PC-II Approved . (M/S Pavron) PC-I/DCE under preparation. Alignment finalized by HCM. Will be presented for discussion in the JWG for financing. |
No Image |
1017 (New) |
190531-F/S, Detailed Engg and Construction of Swat Expressway from Chakdarra to Fatehpur (Phase-II) (IDA Assisted). |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- October - 2019 |
PC-II Approved . (M/S Pavron) PC-I/DCE under preparation. Alignment finalized by HCM. Will be presented for discussion in the JWG for financing. |
No Image |
1017 (New) |
190531-F/S, Detailed Engg and Construction of Swat Expressway from Chakdarra to Fatehpur (Phase-II) (IDA Assisted). |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- September - 2019 |
PC-I/DCE under preparation. Alignment finalized by HCM. Will be presented for discussion in the JWG for financing. |
No Image |
1017 (New) |
190531-F/S, Detailed Engg and Construction of Swat Expressway from Chakdarra to Fatehpur (Phase-II) (IDA Assisted). |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- August - 2019 |
PC-I/DCE under preparation. Alignment finalized by HCM. |
No Image |
1017 (New) |
190531-F/S, Detailed Engg and Construction of Swat Expressway from Chakdarra to Fatehpur (Phase-II) (IDA Assisted). |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- May - 2020 |
PC-I has been cleared by PDWP for approval of CDWP. |
No Image |
1017 (New) |
190531-F/S, Detailed Engg and Construction of Swat Expressway from Chakdarra to Fatehpur (Phase-II) (IDA Assisted). |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- April - 2020 |
PC-I has been cleared by PDWP for approval of CDWP. |
No Image |
1017 (New) |
190531-F/S, Detailed Engg and Construction of Swat Expressway from Chakdarra to Fatehpur (Phase-II) (IDA Assisted). |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- March - 2020 |
PC-I has been cleared by PDWP for approval of CDWP. |
No Image |
1017 (New) |
190531-F/S, Detailed Engg and Construction of Swat Expressway from Chakdarra to Fatehpur (Phase-II) (IDA Assisted). |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- February - 2020 |
PC-I has been cleared by PDWP for approval of CDWP. |
No Image |
1017 (New) |
190531-F/S, Detailed Engg and Construction of Swat Expressway from Chakdarra to Fatehpur (Phase-II) (IDA Assisted). |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- January - 2020 |
PC-II Approved . (M/S Pavron) PC-I recommended to CDWP. |
No Image |
Pages : 1 |