Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, January - 2018, January - 2019, January - 2020, February - 2020, February - 2021, February - 2018, February - 2019, March - 2020, March - 2021, March - 2018, March - 2019, April - 2020, April - 2021, April - 2018, April - 2019, May - 2020, May - 2021, May - 2018, June - 2018, July - 2020, July - 2017, August - 2020, August - 2017, August - 2019, September - 2020, September - 2017, September - 2019, October - 2020, October - 2017, October - 2019, November - 2017, November - 2018, November - 2019, December - 2020, December - 2017, December - 2018, December - 2019,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1013
(OG)
140879-Improvement & Rehabilitation of road from Gulshanabad to Janana Mill via Hangu Pattak and Dualization of Old Bannu Road from Janana Mill to Kohat University (Indus Highway Junction) (17.90 Km) i/c Construction of New Bridge of Jerma, District Kohat.
Kohat
PKHA
30-11--1 30-11--1 - 30-11--1 - 1403.483 882.148 50 50 50 50 932.148 471.335 66% 66%
December - 2018
Pack-1 - sub base, sub grade, NGC, embankment completed (Km-2 to 3). Pack-2 - embankment, sub grade in progress. Pack-3 - embankment, sub grade, sub base (shoulder portion) in progress. Pack-4 - pile load test at Jerma bridge completed, NGC, embankment in progress.
No Image
1) Package-1 (Gulshan Chowk to Hangu Phatak)
2) Package-2 (Hangu Phatak to Saif CNG)
3) Package-3 (Saif CNG to Jerma Bridge Start Point)
4) Package-4 (Jerma Bridge via KUST to Main Indus Highway)
1013
(OG)
140879-Improvement & Rehabilitation of road from Gulshanabad to Janana Mill via Hangu Pattak and Dualization of Old Bannu Road from Janana Mill to Kohat University (Indus Highway Junction) (17.90 Km) i/c Construction of New Bridge of Jerma, District Kohat.
Kohat
PKHA
30-11--1 30-11--1 - 30-11--1 - 1403.483 882.148 50 50 50 50 932.148 471.335 66% 66%
November - 2018
Pack-1 - sub base, sub grade, NGC, embankment completed (Km-2 to 3). Pack-2 - embankment, sub grade in progress. Pack-3 - embankment, sub grade, sub base (shoulder portion) in progress. Pack-4 - pile load test at Jerma bridge completed, NGC, embankment in progress.
No Image
1) Package-1 (Gulshan Chowk to Hangu Phatak)
2) Package-2 (Hangu Phatak to Saif CNG)
3) Package-3 (Saif CNG to Jerma Bridge Start Point)
4) Package-4 (Jerma Bridge via KUST to Main Indus Highway)
1013
(OG)
140879-Improvement & Rehabilitation of road from Gulshanabad to Janana Mill via Hangu Pattak and Dualization of Old Bannu Road from Janana Mill to Kohat University (Indus Highway Junction) (17.90 Km) i/c Construction of New Bridge of Jerma, District Kohat.
Kohat
PKHA
30-11--1 30-11--1 - 30-11--1 - 1403.483 882.148 50 50 50 50 932.148 471.335 66% 66%
November - 2018
Pack-1 - sub base, sub grade, NGC, embankment completed (Km-2 to 3). Pack-2 - embankment, sub grade in progress. Pack-3 - embankment, sub grade, sub base (shoulder portion) in progress. Pack-4 - pile load test at Jerma bridge completed, NGC, embankment in progress.
No Image
1) Package-1 (Gulshan Chowk to Hangu Phatak)
2) Package-2 (Hangu Phatak to Saif CNG)
3) Package-3 (Saif CNG to Jerma Bridge Start Point)
4) Package-4 (Jerma Bridge via KUST to Main Indus Highway)
1013
(OG)
140879-Improvement & Rehabilitation of road from Gulshanabad to Janana Mill via Hangu Pattak and Dualization of Old Bannu Road from Janana Mill to Kohat University (Indus Highway Junction) (17.90 Km) i/c Construction of New Bridge of Jerma, District Kohat.
Kohat
PKHA
30-11--1 30-11--1 - 30-11--1 - 1403.483 882.148 50 50 50 50 932.148 471.335 66% 66%
April - 2019
Pack-1 - sub base, sub grade, NGC, embankment completed (Km-2 to 3). Pack-2 - embankment, sub grade in progress. Pack-3 - embankment, sub grade, sub base (shoulder portion) in progress. Pack-4 - pile load test at Jerma bridge completed, NGC, embankment in progress. Substanially completed. Rs.427 m required for completion.
No Image
1) Package-1 (Gulshan Chowk to Hangu Phatak)
2) Package-2 (Hangu Phatak to Saif CNG)
3) Package-3 (Saif CNG to Jerma Bridge Start Point)
4) Package-4 (Jerma Bridge via KUST to Main Indus Highway)
1013
(OG)
140879-Improvement & Rehabilitation of road from Gulshanabad to Janana Mill via Hangu Pattak and Dualization of Old Bannu Road from Janana Mill to Kohat University (Indus Highway Junction) (17.90 Km) i/c Construction of New Bridge of Jerma, District Kohat.
Kohat
PKHA
30-11--1 30-11--1 - 30-11--1 - 1403.483 882.148 50 50 50 50 932.148 471.335 66% 66%
March - 2019
Pack-1 - sub base, sub grade, NGC, embankment completed (Km-2 to 3). Pack-2 - embankment, sub grade in progress. Pack-3 - embankment, sub grade, sub base (shoulder portion) in progress. Pack-4 - pile load test at Jerma bridge completed, NGC, embankment in progress. Substanially completed. Rs.427 m required for completion.
No Image
1) Package-1 (Gulshan Chowk to Hangu Phatak)
2) Package-2 (Hangu Phatak to Saif CNG)
3) Package-3 (Saif CNG to Jerma Bridge Start Point)
4) Package-4 (Jerma Bridge via KUST to Main Indus Highway)
1013
(OG)
140879-Improvement & Rehabilitation of road from Gulshanabad to Janana Mill via Hangu Pattak and Dualization of Old Bannu Road from Janana Mill to Kohat University (Indus Highway Junction) (17.90 Km) i/c Construction of New Bridge of Jerma, District Kohat.
Kohat
PKHA
30-11--1 30-11--1 - 30-11--1 - 1403.483 882.148 50 50 50 50 932.148 471.335 66% 66%
March - 2019
Pack-1 - sub base, sub grade, NGC, embankment completed (Km-2 to 3). Pack-2 - embankment, sub grade in progress. Pack-3 - embankment, sub grade, sub base (shoulder portion) in progress. Pack-4 - pile load test at Jerma bridge completed, NGC, embankment in progress. Substanially completed. Rs.427 m required for completion.
No Image
1) Package-1 (Gulshan Chowk to Hangu Phatak)
2) Package-2 (Hangu Phatak to Saif CNG)
3) Package-3 (Saif CNG to Jerma Bridge Start Point)
4) Package-4 (Jerma Bridge via KUST to Main Indus Highway)
1013
(OG)
140879-Improvement & Rehabilitation of road from Gulshanabad to Janana Mill via Hangu Pattak and Dualization of Old Bannu Road from Janana Mill to Kohat University (Indus Highway Junction) (17.90 Km) i/c Construction of New Bridge of Jerma, District Kohat.
Kohat
PKHA
30-11--1 30-11--1 - 30-11--1 - 1403.483 882.148 50 50 50 50 932.148 471.335 66% 66%
February - 2019
Pack-1 - sub base, sub grade, NGC, embankment completed (Km-2 to 3). Pack-2 - embankment, sub grade in progress. Pack-3 - embankment, sub grade, sub base (shoulder portion) in progress. Pack-4 - pile load test at Jerma bridge completed, NGC, embankment in progress. Substanially completed. Rs.427 m required for completion.
No Image
1) Package-1 (Gulshan Chowk to Hangu Phatak)
2) Package-2 (Hangu Phatak to Saif CNG)
3) Package-3 (Saif CNG to Jerma Bridge Start Point)
4) Package-4 (Jerma Bridge via KUST to Main Indus Highway)
1013
(OG)
140879-Improvement & Rehabilitation of road from Gulshanabad to Janana Mill via Hangu Pattak and Dualization of Old Bannu Road from Janana Mill to Kohat University (Indus Highway Junction) (17.90 Km) i/c Construction of New Bridge of Jerma, District Kohat.
Kohat
PKHA
30-11--1 30-11--1 - 30-11--1 - 1403.483 882.148 50 50 50 50 932.148 471.335 66% 66%
January - 2019
Pack-1 - sub base, sub grade, NGC, embankment completed (Km-2 to 3). Pack-2 - embankment, sub grade in progress. Pack-3 - embankment, sub grade, sub base (shoulder portion) in progress. Pack-4 - pile load test at Jerma bridge completed, NGC, embankment in progress. Substanially complted. Rs. 427 M required for completion .
No Image
1) Package-1 (Gulshan Chowk to Hangu Phatak)
2) Package-2 (Hangu Phatak to Saif CNG)
3) Package-3 (Saif CNG to Jerma Bridge Start Point)
4) Package-4 (Jerma Bridge via KUST to Main Indus Highway)
1013
(OG)
150792-Construction / Rehabilitation of internal roads of UC-Tehkal, UC Shaheen Town, University Town, Malkandher District Peshawar.
Peshawar
HW
20-04-16 - - 02-11-15 - 99.736 59.998 10 8.55 6.05 6.05 66.048 29.738 70% 66%
December - 2017
Length 10 Km - 8 Km asphalt completed and structure work in progress.
No Image
1013
(OG)
150792-Construction / Rehabilitation of internal roads of UC-Tehkal, UC Shaheen Town, University Town, Malkandher District Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 99.736 59.998 10 10 6.05 6.05 66.048 29.738 70% 66%
November - 2017
Length 10 Km - 8 Km asphalt completed and structure work in progress.
No Image
1013
(OG)
150792-Construction / Rehabilitation of internal roads of UC-Tehkal, UC Shaheen Town, University Town, Malkandher District Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 99.736 59.998 10 10 6.05 3.55 63.548 29.738 70% 64%
October - 2017
Length 10 Km - 6 Km asphalt completed and structure work in progress.
No Image
1013
(OG)
150792-Construction / Rehabilitation of internal roads of UC-Tehkal, UC Shaheen Town, University Town, Malkandher District Peshawar.
Peshawar
HW
20-04-16 - - 02-11-15 - 99.736 59.998 10 10 3.55 3.55 63.548 29.738 70% 64%
September - 2017
Length 10 Km - 6 Km asphalt completed and structure work in progress.
No Image
1013
(OG)
150792-Construction / Rehabilitation of internal roads of UC-Tehkal, UC Shaheen Town, University Town, Malkandher District Peshawar.
Peshawar
HW
20-04-16 - - 02-11-15 - 99.736 59.998 10 10 3.55 3.55 63.548 29.738 70% 64%
August - 2017
Length 10 Km - 6 Km asphalt completed and structure work in progress.
No Image
1013
(OG)
150792-Construction / Rehabilitation of internal roads of UC-Tehkal, UC Shaheen Town, University Town, Malkandher District Peshawar.
Peshawar
HW
20-04-16 - - 02-11-15 - 99.736 59.998 10 10 3.55 3.55 63.548 29.738 70% 64%
July - 2017
Length 10 Km - 8 Km asphalt completed and structure work in progress.
No Image
1013
(OG)
150792-Construction / Rehabilitation of internal roads of UC-Tehkal, UC Shaheen Town, University Town, Malkandher District Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 99.736 59.998 10 35.794 35.794 35.794 95.792 29.738 70% 96%
June - 2018
Length 10 Km - 9 Km asphalt completed and structure work in progress.
No Image
1013
(OG)
150792-Construction / Rehabilitation of internal roads of UC-Tehkal, UC Shaheen Town, University Town, Malkandher District Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 99.736 59.998 10 39.355 39.355 14.438 74.436 29.738 70% 75%
May - 2018
Length 10 Km - 9 Km asphalt completed and structure work in progress.
No Image
1013
(OG)
150792-Construction / Rehabilitation of internal roads of UC-Tehkal, UC Shaheen Town, University Town, Malkandher District Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 99.736 59.998 10 39.355 39.355 21.355 81.353 29.738 70% 82%
April - 2018
Length 10 Km - 9 Km asphalt completed and structure work in progress.
No Image
1013
(OG)
150792-Construction / Rehabilitation of internal roads of UC-Tehkal, UC Shaheen Town, University Town, Malkandher District Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 99.736 59.998 10 39.355 39.355 21.355 81.353 29.738 70% 82%
March - 2018
Length 10 Km - 9 Km asphalt completed and structure work in progress.
No Image
1013
(OG)
150792-Construction / Rehabilitation of internal roads of UC-Tehkal, UC Shaheen Town, University Town, Malkandher District Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 99.736 59.998 10 21.355 21.355 21.355 81.353 29.738 70% 82%
February - 2018
Length 10 Km - 9 Km asphalt completed and structure work in progress. Rs.31 m demanded for tempo of work.
No Image
PK-05 Peshawar
1013
(OG)
150792-Construction / Rehabilitation of internal roads of UC-Tehkal, UC Shaheen Town, University Town, Malkandher District Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 99.736 59.998 10 21.355 21.355 6.05 66.048 29.738 70% 66%
January - 2018
Length 10 Km - 9 Km asphalt completed and structure work in progress. Rs.31 m demanded for tempo of work.
No Image
1013
(New)
190551-Construction of Dual Carriageway from Chamkani to Badaber, Peshawar Sh: Peshawar Ring Road to Badaber via Surizai (15 Km) (Phase-I).
Peshawar
PKHA
30-11--1 30-11--1 - 30-11--1 - 4000 0 10 9.3625 9.3625 9.3625 9.3625 0 - -
December - 2019
PC-II Approved. PC-I/DCE under preparation based on new scope of work. Will be submitted within week time
No Image
1013
(New)
190551-Construction of Dual Carriageway from Chamkani to Badaber, Peshawar Sh: Peshawar Ring Road to Badaber via Surizai (15 Km) (Phase-I).
Peshawar
PKHA
30-11--1 30-11--1 - 30-11--1 - 4000 0 10 10 2.5 2.5 2.5 0 - -
November - 2019
PC-II Approved. PC-I/DCE under preparation based on new scope of work. Will be submitted within 30 days
No Image
1013
(New)
190551-Construction of Dual Carriageway from Chamkani to Badaber, Peshawar Sh: Peshawar Ring Road to Badaber via Surizai (15 Km) (Phase-I).
Peshawar
PKHA
30-11--1 30-11--1 - 30-11--1 - 4000 0 10 10 2.5 2.5 2.5 0 - -
October - 2019
PC-II Approved. PC-I/DCE under preparation based on new scope of work. Will be submitted within 30 days
No Image
1013
(New)
190551-Construction of Dual Carriageway from Chamkani to Badaber, Peshawar Sh: Peshawar Ring Road to Badaber via Surizai (15 Km) (Phase-I).
Peshawar
PKHA
30-11--1 30-11--1 - 30-11--1 - 4000 0 10 10 2.5 2.5 2.5 0 - -
September - 2019
PC-I/DCE under preparation based on new scope of work.
No Image
1013
(New)
190551-Construction of Dual Carriageway from Chamkani to Badaber, Peshawar Sh: Peshawar Ring Road to Badaber via Surizai (15 Km) (Phase-I).
Peshawar
PKHA
30-11--1 30-11--1 - 30-11--1 - 4000 0 10 10 2.5 2.5 2.5 0 - -
August - 2019
PC-I/DCE under preparation based on new scope of work.
No Image
1013
(New)
190551-Construction of Dual Carriageway from Chamkani to Badaber, Peshawar Sh: Peshawar Ring Road to Badaber via Surizai (15 Km) (Phase-I).
Peshawar
PKHA
30-11--1 30-11--1 - 30-11--1 - 4000 0 10 2.5 2.5 2.5 2.5 0 - -
May - 2020
PC- II submitted to P&D for additional scope of Phase II inclusion in the scope. Pc-I in progress on MRS-2019.
No Image
1013
(New)
190551-Construction of Dual Carriageway from Chamkani to Badaber, Peshawar Sh: Peshawar Ring Road to Badaber via Surizai (15 Km) (Phase-I).
Peshawar
PKHA
30-11--1 30-11--1 - 30-11--1 - 4000 0 10 9.3625 9.3625 9.3625 9.3625 0 - -
April - 2020
PC- II submitted to P&D for additional scope of Phase II inclusion in the scope
No Image
1013
(New)
190551-Construction of Dual Carriageway from Chamkani to Badaber, Peshawar Sh: Peshawar Ring Road to Badaber via Surizai (15 Km) (Phase-I).
Peshawar
PKHA
30-11--1 30-11--1 - 30-11--1 - 4000 0 10 9.3625 9.3625 9.3625 9.3625 0 - -
March - 2020
PC- II submitted to P&D for additional scope of Phase II inclusion in the scope
No Image
1013
(New)
190551-Construction of Dual Carriageway from Chamkani to Badaber, Peshawar Sh: Peshawar Ring Road to Badaber via Surizai (15 Km) (Phase-I).
Peshawar
PKHA
30-11--1 30-11--1 - 30-11--1 - 4000 0 10 9.3625 9.3625 9.3625 9.3625 0 - -
February - 2020
PC- II submitted to P&D for additional scope of Phase II inclusion in the scope
No Image
1013
(New)
190551-Construction of Dual Carriageway from Chamkani to Badaber, Peshawar Sh: Peshawar Ring Road to Badaber via Surizai (15 Km) (Phase-I).
Peshawar
PKHA
30-11--1 30-11--1 - 30-11--1 - 4000 0 10 9.3625 9.3625 9.3625 9.3625 0 - -
January - 2020
PC-II Approved. PC-I/DCE submitted to MD PKHA.
No Image
1013
(OG)
160542-F/S and Construction of Model Police Station at each Tehsil & Town Headquarter of Khyber Pakhtunkhwa (13 No.) (Phase-I).
Provincial
30-11--1 30-11--1 - 30-11--1 - 607.405 198.933 127.35 127.35 0 0 198.933 0 - -
December - 2020
PC-II for Rs.50 m approved in DDWP on 07/09/2016.
No Image
1013
(OG)
160542-F/S and Construction of Model Police Station at each Tehsil & Town Headquarter of Khyber Pakhtunkhwa (13 No.) (Phase-I).
Provincial
30-11--1 30-11--1 - 30-11--1 - 607.405 198.933 127.35 127.35 0 0 198.933 0 - -
December - 2020
PC-II for Rs.50 m approved in DDWP on 07/09/2016.
No Image
1013
(OG)
160542-F/S and Construction of Model Police Station at each Tehsil & Town Headquarter of Khyber Pakhtunkhwa (13 No.) (Phase-I).
Provincial
30-11--1 30-11--1 - 30-11--1 - 607.405 198.933 127.35 127.35 0 0 198.933 0 - -
October - 2020
PC-II for Rs.50 m approved in DDWP on 07/09/2016.
No Image
1013
(OG)
160542-F/S and Construction of Model Police Station at each Tehsil & Town Headquarter of Khyber Pakhtunkhwa (13 No.) (Phase-I).
Provincial
30-11--1 30-11--1 - 30-11--1 - 607.405 198.933 127.35 127.35 0 0 198.933 0 - -
September - 2020
PC-II for Rs.50 m approved in DDWP on 07/09/2016.
No Image
1013
(OG)
160542-F/S and Construction of Model Police Station at each Tehsil & Town Headquarter of Khyber Pakhtunkhwa (13 No.) (Phase-I).
Provincial
30-11--1 30-11--1 - 30-11--1 - 607.405 198.933 127.35 127.35 0 0 198.933 0 - -
August - 2020
PC-II for Rs.50 m approved in DDWP on 07/09/2016.
No Image
1013
(OG)
160542-F/S and Construction of Model Police Station at each Tehsil & Town Headquarter of Khyber Pakhtunkhwa (13 No.) (Phase-I).
Provincial
30-11--1 30-11--1 - 30-11--1 - 607.405 198.933 127.35 0 0 0 198.933 0 - -
July - 2020
PC-II for Rs.50 m approved in DDWP on 07/09/2016.
No Image
1013
(OG)
160542-F/S and Construction of Model Police Station at each Tehsil & Town Headquarter of Khyber Pakhtunkhwa (13 No.) (Phase-I).
Provincial
30-11--1 30-11--1 - 30-11--1 - 607.405 198.933 127.35 127.35 0 0 198.933 0 - -
May - 2021
PC-II for Rs.50 m approved in DDWP on 07/09/2016.
No Image
1013
(OG)
160542-F/S and Construction of Model Police Station at each Tehsil & Town Headquarter of Khyber Pakhtunkhwa (13 No.) (Phase-I).
Provincial
30-11--1 30-11--1 - 30-11--1 - 607.405 198.933 127.35 127.35 0 0 198.933 0 - -
April - 2021
PC-II for Rs.50 m approved in DDWP on 07/09/2016.
No Image
1013
(OG)
160542-F/S and Construction of Model Police Station at each Tehsil & Town Headquarter of Khyber Pakhtunkhwa (13 No.) (Phase-I).
Provincial
30-11--1 30-11--1 - 30-11--1 - 607.405 198.933 127.35 127.35 0 0 198.933 0 - -
March - 2021
PC-II for Rs.50 m approved in DDWP on 07/09/2016.
No Image
1013
(OG)
160542-F/S and Construction of Model Police Station at each Tehsil & Town Headquarter of Khyber Pakhtunkhwa (13 No.) (Phase-I).
Provincial
30-11--1 30-11--1 - 30-11--1 - 607.405 198.933 127.35 127.35 0 0 198.933 0 - -
February - 2021
PC-II for Rs.50 m approved in DDWP on 07/09/2016.
No Image
1013
(OG)
160542-F/S and Construction of Model Police Station at each Tehsil & Town Headquarter of Khyber Pakhtunkhwa (13 No.) (Phase-I).
Provincial
30-11--1 30-11--1 - 30-11--1 - 607.405 198.933 127.35 127.35 0 0 198.933 0 - -
January - 2021
PC-II for Rs.50 m approved in DDWP on 07/09/2016.
No Image
Pages : 1