Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1012 (OG) |
140627-Improvement, Widening and Rehabilitation of Road from Bannu Kohat Road to Indus Highway via Garrison College/Dhoda Golf Club, Kohat (6 Km). |
Kohat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 294.598 | 272.949 | 49 | 47.775 | 35.525 | 24.5 | 297.449 | 0 | 100% |
100% December - 2018 |
Length 6 Km - NGC embankment, sub grade, sub base (1+300 to 2+600) completed. Structure work (6 Nos slab culverts) in progress. |
No Image |
1012 (OG) |
140627-Improvement, Widening and Rehabilitation of Road from Bannu Kohat Road to Indus Highway via Garrison College/Dhoda Golf Club, Kohat (6 Km). |
Kohat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 294.598 | 272.949 | 49 | 47.775 | 35.525 | 24.5 | 297.449 | 0 | 100% |
100% November - 2018 |
Length 6 Km - NGC embankment, sub grade, sub base (1+300 to 2+600) completed. Structure work (6 Nos slab culverts) in progress. |
No Image |
1012 (OG) |
140627-Improvement, Widening and Rehabilitation of Road from Bannu Kohat Road to Indus Highway via Garrison College/Dhoda Golf Club, Kohat (6 Km). |
Kohat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 294.598 | 272.949 | 49 | 47.775 | 35.525 | 24.5 | 297.449 | 0 | 100% |
100% November - 2018 |
Length 6 Km - NGC embankment, sub grade, sub base (1+300 to 2+600) completed. Structure work (6 Nos slab culverts) in progress. |
No Image |
1012 (OG) |
140627-Improvement, Widening and Rehabilitation of Road from Bannu Kohat Road to Indus Highway via Garrison College/Dhoda Golf Club, Kohat (6 Km). |
Kohat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 294.598 | 272.949 | 49 | 47.775 | 47.775 | 47.775 | 320.724 | 0 | 100% |
100% April - 2019 |
Length 6 Km - Physically completed. |
No Image |
1012 (OG) |
140627-Improvement, Widening and Rehabilitation of Road from Bannu Kohat Road to Indus Highway via Garrison College/Dhoda Golf Club, Kohat (6 Km). |
Kohat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 294.598 | 272.949 | 49 | 47.775 | 47.775 | 47.775 | 320.724 | 0 | 100% |
100% March - 2019 |
Length 6 Km - Physically complte |
No Image |
1012 (OG) |
140627-Improvement, Widening and Rehabilitation of Road from Bannu Kohat Road to Indus Highway via Garrison College/Dhoda Golf Club, Kohat (6 Km). |
Kohat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 294.598 | 272.949 | 49 | 47.775 | 47.775 | 47.775 | 320.724 | 0 | 100% |
100% March - 2019 |
Length 6 Km - Physically complte |
No Image |
1012 (OG) |
140627-Improvement, Widening and Rehabilitation of Road from Bannu Kohat Road to Indus Highway via Garrison College/Dhoda Golf Club, Kohat (6 Km). |
Kohat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 294.598 | 272.949 | 49 | 47.775 | 47.775 | 47.775 | 320.724 | 0 | 100% |
100% February - 2019 |
Length 6 Km - NGC embankment, sub grade, sub base (1+300 to 2+600) completed. Structure work (6 Nos slab culverts) in progress. |
No Image |
1012 (OG) |
140627-Improvement, Widening and Rehabilitation of Road from Bannu Kohat Road to Indus Highway via Garrison College/Dhoda Golf Club, Kohat (6 Km). |
Kohat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 294.598 | 272.949 | 49 | 47.775 | 35.525 | 35.525 | 308.474 | 0 | 100% |
100% January - 2019 |
Length 6 Km - NGC embankment, sub grade, sub base (1+300 to 2+600) completed. Structure work (6 Nos slab culverts) in progress. |
No Image |
1012 (OG) |
150791-Construction / Widening / BT of internal roads of UC-31, UC-32, UC-33, UC-34, UC-35, UC-36 District Peshawar. |
Peshawar HW |
03-07-16 | - | - | 02-11-15 | - | 99.882 | 28.405 | 10 | 8.55 | 6.05 | 6.05 | 34.455 | 61.477 | 38% |
34% December - 2017 |
Length 10 Km - 4 Km asphalt completed and remaining base course, structure work in progress. |
No Image |
1012 (OG) |
150791-Construction / Widening / BT of internal roads of UC-31, UC-32, UC-33, UC-34, UC-35, UC-36 District Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.882 | 28.405 | 10 | 9 | 6.05 | 3.55 | 31.955 | 61.477 | 38% |
32% November - 2017 |
Length 10 Km - 4 Km asphalt completed and remaining base course, structure work in progress. |
No Image |
1012 (OG) |
150791-Construction / Widening / BT of internal roads of UC-31, UC-32, UC-33, UC-34, UC-35, UC-36 District Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.882 | 28.405 | 10 | 10 | 6.05 | 3.55 | 31.955 | 61.477 | 38% |
32% October - 2017 |
Length 10 Km - 4 Km asphalt completed and remaining base course, structure work in progress. |
No Image |
1012 (OG) |
150791-Construction / Widening / BT of internal roads of UC-31, UC-32, UC-33, UC-34, UC-35, UC-36 District Peshawar. |
Peshawar HW |
01-05-16 | - | - | 02-11-15 | - | 99.882 | 28.405 | 10 | 10 | 3.55 | 3.55 | 31.955 | 61.477 | 38% |
32% September - 2017 |
Length 10 Km - 4 Km asphalt completed and remaining base course, structure work in progress. |
No Image |
1012 (OG) |
150791-Construction / Widening / BT of internal roads of UC-31, UC-32, UC-33, UC-34, UC-35, UC-36 District Peshawar. |
Peshawar HW |
01-05-16 | - | - | 02-11-15 | - | 99.882 | 28.405 | 10 | 10 | 3.55 | 3.55 | 31.955 | 61.477 | 38% |
32% August - 2017 |
Length 10 Km - 4 Km asphalt completed and remaining base course, structure work in progress. |
No Image |
1012 (OG) |
150791-Construction / Widening / BT of internal roads of UC-31, UC-32, UC-33, UC-34, UC-35, UC-36 District Peshawar. |
Peshawar HW |
01-05-16 | - | - | 02-11-15 | - | 99.882 | 28.405 | 10 | 10 | 3.55 | 3.55 | 31.955 | 61.477 | 38% |
32% July - 2017 |
Length 10 Km - 4 Km asphalt completed and remaining base course, structure work in progress. |
No Image |
1012 (OG) |
150791-Construction / Widening / BT of internal roads of UC-31, UC-32, UC-33, UC-34, UC-35, UC-36 District Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.882 | 28.405 | 10 | 16.362 | 16.362 | 16.362 | 44.767 | 61.477 | 38% |
45% June - 2018 |
Length 10 Km - 2.5 Km asphalt completed, all packages in progress. |
No Image |
PK-04 Peshawar | |||||||||||||||||||
1012 (OG) |
150791-Construction / Widening / BT of internal roads of UC-31, UC-32, UC-33, UC-34, UC-35, UC-36 District Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.882 | 28.405 | 10 | 16.362 | 16.362 | 16.362 | 44.767 | 61.477 | 38% |
45% May - 2018 |
Length 10 Km - 2.5 Km asphalt completed, drain work on all packages in progress. Rs.55 m demanded for tempo of work. |
No Image |
PK-04 Peshawar | |||||||||||||||||||
1012 (OG) |
150791-Construction / Widening / BT of internal roads of UC-31, UC-32, UC-33, UC-34, UC-35, UC-36 District Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.882 | 28.405 | 10 | 16.362 | 16.362 | 13.672 | 42.077 | 61.477 | 38% |
42% April - 2018 |
Length 10 Km - 2.5 Km asphalt completed, drain work on all packages in progress. Rs.55 m demanded for tempo of work. |
No Image |
PK-04 Peshawar | |||||||||||||||||||
1012 (OG) |
150791-Construction / Widening / BT of internal roads of UC-31, UC-32, UC-33, UC-34, UC-35, UC-36 District Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.882 | 28.405 | 10 | 16.362 | 16.362 | 13.672 | 42.077 | 61.477 | 38% |
42% March - 2018 |
Length 10 Km - 4.4 Km asphalt completed, drain work on all packages in progress. Rs.20 m demanded for tempo of work. |
No Image |
PK-04 Peshawar | |||||||||||||||||||
1012 (OG) |
150791-Construction / Widening / BT of internal roads of UC-31, UC-32, UC-33, UC-34, UC-35, UC-36 District Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.882 | 28.405 | 10 | 13.672 | 13.672 | 13.672 | 42.077 | 61.477 | 38% |
42% February - 2018 |
Length 10 Km - 1.4 Km asphalt completed, drain work on all packages in progress. Rs.55 m demanded for tempo of work. |
No Image |
PK-04 Peshawar | |||||||||||||||||||
1012 (OG) |
150791-Construction / Widening / BT of internal roads of UC-31, UC-32, UC-33, UC-34, UC-35, UC-36 District Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.882 | 28.405 | 10 | 13.672 | 13.672 | 13.672 | 42.077 | 61.477 | 38% |
42% January - 2018 |
Length 10 Km - 1.4 Km asphalt completed, drain work on all packages in progress. Rs.65 m demanded for tempo of work. |
No Image |
1012 (OG) |
160133-F/S and Strenthening of Police Infrastructure in Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 425.02 | 82.686 | 55 | 55 | 0 | 0 | 82.686 | 0 | - |
- December - 2020 |
PC-II for Rs.30 m approved in DDWP on 07/09/2016. |
No Image |
1012 (OG) |
160133-F/S and Strenthening of Police Infrastructure in Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 425.02 | 82.686 | 55 | 55 | 0 | 0 | 82.686 | 0 | - |
- December - 2020 |
PC-II for Rs.30 m approved in DDWP on 07/09/2016. |
No Image |
1012 (OG) |
160133-F/S and Strenthening of Police Infrastructure in Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 425.02 | 82.686 | 55 | 55 | 0 | 0 | 82.686 | 0 | - |
- October - 2020 |
PC-II for Rs.30 m approved in DDWP on 07/09/2016. |
No Image |
1012 (OG) |
160133-F/S and Strenthening of Police Infrastructure in Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 425.02 | 82.686 | 55 | 55 | 0 | 0 | 82.686 | 0 | - |
- September - 2020 |
PC-II for Rs.30 m approved in DDWP on 07/09/2016. |
No Image |
1012 (OG) |
160133-F/S and Strenthening of Police Infrastructure in Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 425.02 | 82.686 | 55 | 55 | 0 | 0 | 82.686 | 0 | - |
- August - 2020 |
PC-II for Rs.30 m approved in DDWP on 07/09/2016. |
No Image |
1012 (OG) |
160133-F/S and Strenthening of Police Infrastructure in Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 425.02 | 82.686 | 55 | 0 | 0 | 0 | 82.686 | 0 | - |
- July - 2020 |
PC-II for Rs.30 m approved in DDWP on 07/09/2016. |
No Image |
1012 (OG) |
160133-F/S and Strenthening of Police Infrastructure in Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 425.02 | 82.686 | 55 | 55 | 0 | 0 | 82.686 | 0 | - |
- May - 2021 |
PC-II for Rs.30 m approved in DDWP on 07/09/2016. |
No Image |
1012 (OG) |
160133-F/S and Strenthening of Police Infrastructure in Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 425.02 | 82.686 | 55 | 55 | 0 | 0 | 82.686 | 0 | - |
- April - 2021 |
PC-II for Rs.30 m approved in DDWP on 07/09/2016. |
No Image |
1012 (OG) |
160133-F/S and Strenthening of Police Infrastructure in Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 425.02 | 82.686 | 55 | 55 | 0 | 0 | 82.686 | 0 | - |
- March - 2021 |
PC-II for Rs.30 m approved in DDWP on 07/09/2016. |
No Image |
1012 (OG) |
160133-F/S and Strenthening of Police Infrastructure in Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 425.02 | 82.686 | 55 | 55 | 0 | 0 | 82.686 | 0 | - |
- February - 2021 |
PC-II for Rs.30 m approved in DDWP on 07/09/2016. |
No Image |
1012 (OG) |
160133-F/S and Strenthening of Police Infrastructure in Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 425.02 | 82.686 | 55 | 55 | 0 | 0 | 82.686 | 0 | - |
- January - 2021 |
PC-II for Rs.30 m approved in DDWP on 07/09/2016. |
No Image |
1012 (OG) |
180600-F/S, Design and Reconstruction of RCC Bridges (i) Pir Bala on Km-7, Peshawar, (ii) Kanawer Bridge on Charsadda Tangi Road additional 1.25 Km Charsadda Tangi road (from Tangi Bazar to Abazai), (iii) Elai Bridge on S-10 at Buner and (iv) Bridge on Haripur-Beer Section S-12 (Length-160 m). |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 668.596 | 0 | 50 | 50 | 50 | 50 | 50 | 618.596 | 7% |
7% December - 2019 |
4 Brdiges- Work in progress on all units |
No Image |
1012 (OG) |
180600-F/S, Design and Reconstruction of RCC Bridges (i) Pir Bala on Km-7, Peshawar, (ii) Kanawer Bridge on Charsadda Tangi Road additional 1.25 Km Charsadda Tangi road (from Tangi Bazar to Abazai), (iii) Elai Bridge on S-10 at Buner and (iv) Bridge on Haripur-Beer Section S-12 (Length-160 m). |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 668.596 | 0 | 50 | 50 | 50 | 50 | 50 | 618.596 | 7% |
7% November - 2019 |
4 Brdiges- Work in progress on all units |
No Image |
1012 (OG) |
180600-F/S, Design and Reconstruction of RCC Bridges (i) Pir Bala on Km-7, Peshawar, (ii) Kanawer Bridge on Charsadda Tangi Road additional 1.25 Km Charsadda Tangi road (from Tangi Bazar to Abazai), (iii) Elai Bridge on S-10 at Buner and (iv) Bridge on Haripur-Beer Section S-12 (Length-160 m). |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 668.596 | 0 | 50 | 50 | 50 | 50 | 50 | 618.596 | 7% |
7% October - 2019 |
4 Brdiges- Work in progress on all units |
No Image |
1012 (OG) |
180600-F/S, Design and Reconstruction of RCC Bridges (i) Pir Bala on Km-7, Peshawar, (ii) Kanawer Bridge on Charsadda Tangi Road additional 1.25 Km Charsadda Tangi road (from Tangi Bazar to Abazai), (iii) Elai Bridge on S-10 at Buner and (iv) Bridge on Haripur-Beer Section S-12 (Length-160 m). |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 668.596 | 0 | 50 | 50 | 50 | 50 | 50 | 618.596 | 7% |
7% September - 2019 |
4 Brdiges- Work in progress on all units |
No Image |
1012 (OG) |
180600-F/S, Design and Reconstruction of RCC Bridges (i) Pir Bala on Km-7, Peshawar, (ii) Kanawer Bridge on Charsadda Tangi Road additional 1.25 Km Charsadda Tangi road (from Tangi Bazar to Abazai), (iii) Elai Bridge on S-10 at Buner and (iv) Bridge on Haripur-Beer Section S-12 (Length-160 m). |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 668.596 | 0 | 50 | 50 | 12.5 | 12.5 | 12.5 | 618.596 | 7% |
2% August - 2019 |
LOA issued to contractor and consultants. |
No Image |
1012 (OG) |
180600-F/S, Design and Reconstruction of RCC Bridges (i) Pir Bala on Km-7, Peshawar, (ii) Kanawer Bridge on Charsadda Tangi Road additional 1.25 Km Charsadda Tangi road (from Tangi Bazar to Abazai), (iii) Elai Bridge on S-10 at Buner and (iv) Bridge on Haripur-Beer Section S-12 (Length-160 m). |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 668.596 | 0 | 50 | 50 | 50 | 50 | 50 | 618.596 | 7% |
7% May - 2020 |
1- Work order issued , work could not be stated due to paucity of funds.
2- TF completed including testing dismantling of existing bridge completed.
3) work order issued but work not started due to funds problem.
4)- Work started Dismantling of existing bridge in progress. |
No Image |
1012 (OG) |
180600-F/S, Design and Reconstruction of RCC Bridges (i) Pir Bala on Km-7, Peshawar, (ii) Kanawer Bridge on Charsadda Tangi Road additional 1.25 Km Charsadda Tangi road (from Tangi Bazar to Abazai), (iii) Elai Bridge on S-10 at Buner and (iv) Bridge on Haripur-Beer Section S-12 (Length-160 m). |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 668.596 | 0 | 50 | 50 | 50 | 50 | 50 | 618.596 | 7% |
7% April - 2020 |
1- Work order issued , work could not be stated due to paucity of funds.
2- TF completed including testing dismantling of existing bridge completed.
3) work order issued but work not started due to funds problem.
4)- Work started Dismantling of existing bridge in progress. |
No Image |
1012 (OG) |
180600-F/S, Design and Reconstruction of RCC Bridges (i) Pir Bala on Km-7, Peshawar, (ii) Kanawer Bridge on Charsadda Tangi Road additional 1.25 Km Charsadda Tangi road (from Tangi Bazar to Abazai), (iii) Elai Bridge on S-10 at Buner and (iv) Bridge on Haripur-Beer Section S-12 (Length-160 m). |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 668.596 | 0 | 50 | 50 | 50 | 50 | 50 | 618.596 | 7% |
7% March - 2020 |
1- Work order issued , work could not be stated due to paucity of funds.
2- TF completed including testing dismantling of existing bridge completed.
3) work order issued but work not started due to funds problem.
4)- Work started Dismantling of existing bridge in progress. |
No Image |
1012 (OG) |
180600-F/S, Design and Reconstruction of RCC Bridges (i) Pir Bala on Km-7, Peshawar, (ii) Kanawer Bridge on Charsadda Tangi Road additional 1.25 Km Charsadda Tangi road (from Tangi Bazar to Abazai), (iii) Elai Bridge on S-10 at Buner and (iv) Bridge on Haripur-Beer Section S-12 (Length-160 m). |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 668.596 | 0 | 50 | 50 | 50 | 50 | 50 | 618.596 | 7% |
7% February - 2020 |
1- Work order issued , work could not be stated due to paucity of funds.
2- TF completed including testing dismantling of existing bridge completed.
3) work order issued but work not started due to funds problem.
4)- Work started Dismantling of existing bridge in progress. |
No Image |
1012 (OG) |
180600-F/S, Design and Reconstruction of RCC Bridges (i) Pir Bala on Km-7, Peshawar, (ii) Kanawer Bridge on Charsadda Tangi Road additional 1.25 Km Charsadda Tangi road (from Tangi Bazar to Abazai), (iii) Elai Bridge on S-10 at Buner and (iv) Bridge on Haripur-Beer Section S-12 (Length-160 m). |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 668.596 | 0 | 50 | 50 | 50 | 50 | 50 | 618.596 | 7% |
7% January - 2020 |
4 Brdiges- Work in progress on all units |
No Image |
Pages : 1 |