Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, January - 2018, January - 2019, January - 2020, February - 2021, February - 2018, February - 2019, February - 2020, March - 2021, March - 2018, March - 2019, March - 2020, April - 2020, April - 2021, April - 2018, April - 2019, May - 2020, May - 2021, May - 2018, June - 2018, July - 2020, July - 2017, August - 2020, August - 2017, August - 2019, September - 2020, September - 2017, September - 2019, October - 2020, October - 2017, October - 2019, November - 2017, November - 2018, November - 2019, December - 2020, December - 2017, December - 2018, December - 2019,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1011
(OG)
140626-Construction of road from Amberi Killa to Daratang Phase-II SH: Km 17 to Km 35 District Karak (19 Km).
Karak
PKHA
30-11--1 30-11--1 - 30-11--1 - 798.06 443.2 20 20 20 20 463.2 334.86 58% 58%
December - 2018
Length 19.925 Km - road work, embankement, subm base, WBM, WC, structure work, pipe culverts, box culverts, causeway in progress.
No Image
1) Package-1 (7 Km)
2) Package-2 (7 Km)
3) Package-3 (5.925 Km)
1011
(OG)
140626-Construction of road from Amberi Killa to Daratang Phase-II SH: Km 17 to Km 35 District Karak (19 Km).
Karak
PKHA
30-11--1 30-11--1 - 30-11--1 - 798.06 443.2 20 20 20 20 463.2 334.86 58% 58%
November - 2018
Length 19.925 Km - road work, embankement, subm base, WBM, WC, structure work, pipe culverts, box culverts, causeway in progress.
No Image
1) Package-1 (7 Km)
2) Package-2 (7 Km)
3) Package-3 (5.925 Km)
1011
(OG)
140626-Construction of road from Amberi Killa to Daratang Phase-II SH: Km 17 to Km 35 District Karak (19 Km).
Karak
PKHA
30-11--1 30-11--1 - 30-11--1 - 798.06 443.2 20 20 20 20 463.2 334.86 58% 58%
November - 2018
Length 19.925 Km - road work, embankement, subm base, WBM, WC, structure work, pipe culverts, box culverts, causeway in progress.
No Image
1) Package-1 (7 Km)
2) Package-2 (7 Km)
3) Package-3 (5.925 Km)
1011
(OG)
140626-Construction of road from Amberi Killa to Daratang Phase-II SH: Km 17 to Km 35 District Karak (19 Km).
Karak
PKHA
30-11--1 30-11--1 - 30-11--1 - 798.06 443.2 20 20 20 20 463.2 334.86 58% 58%
April - 2019
Length 19.925 Km - subtantially completed. Rs.200 m demanded for completion.
No Image
1) Package-1 (7 Km)
2) Package-2 (7 Km)
3) Package-3 (5.925 Km)
1011
(OG)
140626-Construction of road from Amberi Killa to Daratang Phase-II SH: Km 17 to Km 35 District Karak (19 Km).
Karak
PKHA
30-11--1 30-11--1 - 30-11--1 - 798.06 443.2 20 20 20 20 463.2 334.86 58% 58%
March - 2019
Length 19.925 Km - subtantially completed. Rs.200 m demanded for completion.
No Image
1) Package-1 (7 Km)
2) Package-2 (7 Km)
3) Package-3 (5.925 Km)
1011
(OG)
140626-Construction of road from Amberi Killa to Daratang Phase-II SH: Km 17 to Km 35 District Karak (19 Km).
Karak
PKHA
30-11--1 30-11--1 - 30-11--1 - 798.06 443.2 20 20 20 20 463.2 334.86 58% 58%
March - 2019
Length 19.925 Km - subtantially completed. Rs.200 m demanded for completion.
No Image
1) Package-1 (7 Km)
2) Package-2 (7 Km)
3) Package-3 (5.925 Km)
1011
(OG)
140626-Construction of road from Amberi Killa to Daratang Phase-II SH: Km 17 to Km 35 District Karak (19 Km).
Karak
PKHA
30-11--1 30-11--1 - 30-11--1 - 798.06 443.2 20 20 20 20 463.2 334.86 58% 58%
February - 2019
Length 19.925 Km - subtantially completed. Rs.200 m for completion.
No Image
1) Package-1 (7 Km)
2) Package-2 (7 Km)
3) Package-3 (5.925 Km)
1011
(OG)
140626-Construction of road from Amberi Killa to Daratang Phase-II SH: Km 17 to Km 35 District Karak (19 Km).
Karak
PKHA
30-11--1 30-11--1 - 30-11--1 - 798.06 443.2 20 20 20 20 463.2 334.86 58% 58%
January - 2019
Length 19.925 Km - subtantially complted Rs. 200 M for completion .
No Image
1) Package-1 (7 Km)
2) Package-2 (7 Km)
3) Package-3 (5.925 Km)
1011
(OG)
150779-Construction / Improvement of Hasanghari Sheri Jahngi road, Khalsa 2 and surrounding areas road Peshawar.
Peshawar
HW
01-06-16 - - 10-09-15 - 150 9.5 10 8.55 3.55 3.55 13.05 130.5 13% 9%
December - 2017
Length 10 Km - 1.7 Km WB completed.
No Image
1011
(OG)
150779-Construction / Improvement of Hasanghari Sheri Jahngi road, Khalsa 2 and surrounding areas road Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 150 9.5 10 8.55 3.55 3.55 13.05 130.5 13% 9%
November - 2017
Length 10 Km - 1.7 Km WB completed.
No Image
1011
(OG)
150779-Construction / Improvement of Hasanghari Sheri Jahngi road, Khalsa 2 and surrounding areas road Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 150 9.5 10 10 3.55 0 9.5 130.5 13% 6%
October - 2017
Length 10 Km - 1 Km asphalt completed and further work stopped.
No Image
1011
(OG)
150779-Construction / Improvement of Hasanghari Sheri Jahngi road, Khalsa 2 and surrounding areas road Peshawar.
Peshawar
HW
01-06-16 - - 10-09-15 - 150 9.5 10 10 3.55 0 9.5 130.5 13% 6%
September - 2017
Length 10 Km - 1 Km asphalt completed and further work stopped.
No Image
1011
(OG)
150779-Construction / Improvement of Hasanghari Sheri Jahngi road, Khalsa 2 and surrounding areas road Peshawar.
Peshawar
HW
01-06-16 - - 10-09-15 - 150 9.5 10 10 3.55 0 9.5 130.5 13% 6%
August - 2017
Length 10 Km - 1 Km asphalt completed and further work stopped.
No Image
1011
(OG)
150779-Construction / Improvement of Hasanghari Sheri Jahngi road, Khalsa 2 and surrounding areas road Peshawar.
Peshawar
HW
01-06-16 - - 10-09-15 - 150 9.5 10 10 3.55 0 9.5 130.5 13% 6%
July - 2017
Length 10 Km - 1.5 Km asphalt completed and sub base, base course in progress.
No Image
1011
(OG)
150779-Construction / Improvement of Hasanghari Sheri Jahngi road, Khalsa 2 and surrounding areas road Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 150 9.5 10 21.484 21.484 21.484 30.984 130.5 13% 21%
June - 2018
Length 10 Km - 2.3 Km road work completed.
No Image
PK-04 Peshawar
1011
(OG)
150779-Construction / Improvement of Hasanghari Sheri Jahngi road, Khalsa 2 and surrounding areas road Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 150 9.5 10 21.484 21.484 21.484 30.984 130.5 13% 21%
May - 2018
Length 10 Km - 2.3 Km road work completed. Rs.60 m demanded for tempo of work.
No Image
PK-04 Peshawar
1011
(OG)
150779-Construction / Improvement of Hasanghari Sheri Jahngi road, Khalsa 2 and surrounding areas road Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 150 9.5 10 21.484 21.484 19.801 29.301 130.5 13% 20%
April - 2018
Length 10 Km - 2.3 Km road work completed. Rs.30 m demanded for tempo of work.
No Image
PK-04 Peshawar
1011
(OG)
150779-Construction / Improvement of Hasanghari Sheri Jahngi road, Khalsa 2 and surrounding areas road Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 150 9.5 10 21.484 21.484 18.794 28.294 130.5 13% 19%
March - 2018
Length 10 Km - 2.5 Km asphalt completed. Rs.30 m demanded for tempo of work.
No Image
PK-04 Peshawar
1011
(OG)
150779-Construction / Improvement of Hasanghari Sheri Jahngi road, Khalsa 2 and surrounding areas road Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 150 9.5 10 18.794 18.794 15 24.5 130.5 13% 16%
February - 2018
Length 10 Km - 1.7 Km WB completed. Rs.60 m demanded for tempo of work.
No Image
PK-04 Peshawar
1011
(OG)
150779-Construction / Improvement of Hasanghari Sheri Jahngi road, Khalsa 2 and surrounding areas road Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 150 9.5 10 18.794 18.794 3.55 13.05 130.5 13% 9%
January - 2018
Length 10 Km - 1.7 Km WB completed. Rs.60 m demanded for tempo of work.
No Image
1011
(OG)
140807-F/S and Dev. of Police Infrastructure in Khyber Pakhtunkhwa (Police Station at Kabalgram, Chauga, Olandar, Dandai District Shangla,Swari at District Buner, Gawaleri and Gat-Poechar at District Swat, Kuz Paro at District Kohistan)
Provincial
30-11--1 30-11--1 - 30-11--1 - 345 197.43 55 55 0 0 197.43 0 - -
December - 2020
No Image
1011
(OG)
140807-F/S and Dev. of Police Infrastructure in Khyber Pakhtunkhwa (Police Station at Kabalgram, Chauga, Olandar, Dandai District Shangla,Swari at District Buner, Gawaleri and Gat-Poechar at District Swat, Kuz Paro at District Kohistan)
Provincial
30-11--1 30-11--1 - 30-11--1 - 345 197.43 55 55 0 0 197.43 0 - -
December - 2020
No Image
1011
(OG)
140807-F/S and Dev. of Police Infrastructure in Khyber Pakhtunkhwa (Police Station at Kabalgram, Chauga, Olandar, Dandai District Shangla,Swari at District Buner, Gawaleri and Gat-Poechar at District Swat, Kuz Paro at District Kohistan)
Provincial
30-11--1 30-11--1 - 30-11--1 - 345 197.43 55 55 0 0 197.43 0 - -
October - 2020
No Image
1011
(OG)
140807-F/S and Dev. of Police Infrastructure in Khyber Pakhtunkhwa (Police Station at Kabalgram, Chauga, Olandar, Dandai District Shangla,Swari at District Buner, Gawaleri and Gat-Poechar at District Swat, Kuz Paro at District Kohistan)
Provincial
30-11--1 30-11--1 - 30-11--1 - 345 197.43 55 55 0 0 197.43 0 - -
September - 2020
No Image
1011
(OG)
140807-F/S and Dev. of Police Infrastructure in Khyber Pakhtunkhwa (Police Station at Kabalgram, Chauga, Olandar, Dandai District Shangla,Swari at District Buner, Gawaleri and Gat-Poechar at District Swat, Kuz Paro at District Kohistan)
Provincial
30-11--1 30-11--1 - 30-11--1 - 345 197.43 55 55 0 0 197.43 0 - -
August - 2020
No Image
1011
(OG)
140807-F/S and Dev. of Police Infrastructure in Khyber Pakhtunkhwa (Police Station at Kabalgram, Chauga, Olandar, Dandai District Shangla,Swari at District Buner, Gawaleri and Gat-Poechar at District Swat, Kuz Paro at District Kohistan)
Provincial
30-11--1 30-11--1 - 30-11--1 - 345 197.43 55 0 0 0 197.43 0 - -
July - 2020
No Image
1011
(OG)
140807-F/S and Dev. of Police Infrastructure in Khyber Pakhtunkhwa (Police Station at Kabalgram, Chauga, Olandar, Dandai District Shangla,Swari at District Buner, Gawaleri and Gat-Poechar at District Swat, Kuz Paro at District Kohistan)
Provincial
30-11--1 30-11--1 - 30-11--1 - 345 197.43 55 55 0 0 197.43 0 - -
May - 2021
No Image
1011
(OG)
140807-F/S and Dev. of Police Infrastructure in Khyber Pakhtunkhwa (Police Station at Kabalgram, Chauga, Olandar, Dandai District Shangla,Swari at District Buner, Gawaleri and Gat-Poechar at District Swat, Kuz Paro at District Kohistan)
Provincial
30-11--1 30-11--1 - 30-11--1 - 345 197.43 55 55 0 0 197.43 0 - -
April - 2021
No Image
1011
(OG)
140807-F/S and Dev. of Police Infrastructure in Khyber Pakhtunkhwa (Police Station at Kabalgram, Chauga, Olandar, Dandai District Shangla,Swari at District Buner, Gawaleri and Gat-Poechar at District Swat, Kuz Paro at District Kohistan)
Provincial
30-11--1 30-11--1 - 30-11--1 - 345 197.43 55 55 0 0 197.43 0 - -
March - 2021
No Image
1011
(OG)
140807-F/S and Dev. of Police Infrastructure in Khyber Pakhtunkhwa (Police Station at Kabalgram, Chauga, Olandar, Dandai District Shangla,Swari at District Buner, Gawaleri and Gat-Poechar at District Swat, Kuz Paro at District Kohistan)
Provincial
30-11--1 30-11--1 - 30-11--1 - 345 197.43 55 55 0 0 197.43 0 - -
February - 2021
No Image
1011
(OG)
140807-F/S and Dev. of Police Infrastructure in Khyber Pakhtunkhwa (Police Station at Kabalgram, Chauga, Olandar, Dandai District Shangla,Swari at District Buner, Gawaleri and Gat-Poechar at District Swat, Kuz Paro at District Kohistan)
Provincial
30-11--1 30-11--1 - 30-11--1 - 345 197.43 55 55 0 0 197.43 0 - -
January - 2021
No Image
1011
(OG)
160248-Project Implementation Unit (PIU) ADB Assisted " Provincial Road Rehabilitation Project".
Provincial
PRIP
30-11--1 30-11--1 - 30-11--1 - 59.318 23.525 10 6.8625 6.8625 0 23.525 25.793 57% 40%
December - 2019
PIU setup, staff deputed.
No Image
1011
(OG)
160248-Project Implementation Unit (PIU) ADB Assisted " Provincial Road Rehabilitation Project".
Provincial
PRIP
30-11--1 30-11--1 - 30-11--1 - 59.318 23.525 10 10 2.5 0 23.525 25.793 57% 40%
November - 2019
PIU setup, staff deputed.
No Image
1011
(OG)
160248-Project Implementation Unit (PIU) ADB Assisted " Provincial Road Rehabilitation Project".
Provincial
PRIP
30-11--1 30-11--1 - 30-11--1 - 59.318 23.525 10 10 2.5 0 23.525 25.793 57% 40%
October - 2019
PIU setup, staff deputed.
No Image
1011
(OG)
160248-Project Implementation Unit (PIU) ADB Assisted " Provincial Road Rehabilitation Project".
Provincial
PRIP
30-11--1 30-11--1 - 30-11--1 - 59.318 23.525 10 10 2.5 0 23.525 25.793 57% 40%
September - 2019
PIU setup, staff deputed.
No Image
1011
(OG)
160248-Project Implementation Unit (PIU) ADB Assisted " Provincial Road Rehabilitation Project".
Provincial
PRIP
30-11--1 30-11--1 - 30-11--1 - 59.318 23.525 10 10 2.5 0 23.525 25.793 57% 40%
August - 2019
PIU setup, staff deputed.
No Image
1011
(OG)
160248-Project Implementation Unit (PIU) ADB Assisted " Provincial Road Rehabilitation Project".
Provincial
PRIP
30-11--1 30-11--1 - 30-11--1 - 59.318 23.525 10 6.8625 6.8625 0 23.525 25.793 57% 40%
May - 2020
PIU setup, staff deputed.
No Image
1011
(OG)
160248-Project Implementation Unit (PIU) ADB Assisted " Provincial Road Rehabilitation Project".
Provincial
PRIP
30-11--1 30-11--1 - 30-11--1 - 59.318 23.525 10 6.8625 6.8625 0 23.525 25.793 57% 40%
April - 2020
PIU setup, staff deputed.
No Image
1011
(OG)
160248-Project Implementation Unit (PIU) ADB Assisted " Provincial Road Rehabilitation Project".
Provincial
PRIP
30-11--1 30-11--1 - 30-11--1 - 59.318 23.525 10 6.8625 6.8625 0 23.525 25.793 57% 40%
March - 2020
PIU setup, staff deputed.
No Image
1011
(OG)
160248-Project Implementation Unit (PIU) ADB Assisted " Provincial Road Rehabilitation Project".
Provincial
PRIP
30-11--1 30-11--1 - 30-11--1 - 59.318 23.525 10 6.8625 6.8625 0 23.525 25.793 57% 40%
February - 2020
PIU setup, staff deputed.
No Image
1011
(OG)
160248-Project Implementation Unit (PIU) ADB Assisted " Provincial Road Rehabilitation Project".
Provincial
PRIP
30-11--1 30-11--1 - 30-11--1 - 59.318 23.525 10 6.8625 6.8625 0 23.525 25.793 57% 40%
January - 2020
PIU setup, staff deputed.
No Image
Pages : 1