Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1007 (New) |
170576-Improvement / Widening / Rehabilitation of road from main Hangu Thall road (Mamoo Banda to Dallan Gurguri Road 22 Km), District Hangu. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 349 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- December - 2018 |
PC-II for Rs.6.980 m approved on 10/08/2017. LOA issued to AA Associates. PC-I/DCE under preparation |
No Image |
Hangu | |||||||||||||||||||
1007 (New) |
170576-Improvement / Widening / Rehabilitation of road from main Hangu Thall road (Mamoo Banda to Dallan Gurguri Road 22 Km), District Hangu. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 349 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- November - 2018 |
PC-II for Rs.6.980 m approved on 10/08/2017. LOA issued to AA Associates. PC-I/DCE for Rs.485.432 m submitted to SOR on 16/05/2018. |
No Image |
Hangu | |||||||||||||||||||
1007 (New) |
170576-Improvement / Widening / Rehabilitation of road from main Hangu Thall road (Mamoo Banda to Dallan Gurguri Road 22 Km), District Hangu. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 349 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- November - 2018 |
PC-II for Rs.6.980 m approved on 10/08/2017. LOA issued to AA Associates. PC-I/DCE for Rs.485.432 m submitted to SOR on 16/05/2018. |
No Image |
Hangu | |||||||||||||||||||
1007 (New) |
170576-Improvement / Widening / Rehabilitation of road from main Hangu Thall road (Mamoo Banda to Dallan Gurguri Road 22 Km), District Hangu. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 349 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- April - 2019 |
PC-II for Rs.6.980 m approved on 10/08/2017. LOA issued to AA Associates. Pre-PDWP held. M&E report submitted. PC-I/DCE for Rs.377.151 m re-submitted to SOR in light of M&E reports. |
No Image |
Hangu | |||||||||||||||||||
1007 (New) |
170576-Improvement / Widening / Rehabilitation of road from main Hangu Thall road (Mamoo Banda to Dallan Gurguri Road 22 Km), District Hangu. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 349 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- March - 2019 |
PC-II for Rs.6.980 m approved on 10/08/2017. LOA issued to AA Associates. Pre-PDWP held. M&E report submitted. PC-I/DCE for Rs.377.151 m re-submitted to SO R in light of M&E reports |
No Image |
Hangu | |||||||||||||||||||
1007 (New) |
170576-Improvement / Widening / Rehabilitation of road from main Hangu Thall road (Mamoo Banda to Dallan Gurguri Road 22 Km), District Hangu. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 349 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- March - 2019 |
PC-II for Rs.6.980 m approved on 10/08/2017. LOA issued to AA Associates. Pre-PDWP held. M&E report submitted. PC-I/DCE for Rs.377.151 m re-submitted to SO R in light of M&E reports |
No Image |
Hangu | |||||||||||||||||||
1007 (New) |
170576-Improvement / Widening / Rehabilitation of road from main Hangu Thall road (Mamoo Banda to Dallan Gurguri Road 22 Km), District Hangu. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 349 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- February - 2019 |
PC-II for Rs.6.980 m approved on 10/08/2017. LOA issued to AA Associates. Pre-PDWP held. M&E report submitted. PC-I/DCE prepared. |
No Image |
Hangu | |||||||||||||||||||
1007 (New) |
170576-Improvement / Widening / Rehabilitation of road from main Hangu Thall road (Mamoo Banda to Dallan Gurguri Road 22 Km), District Hangu. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 349 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- January - 2019 |
PC-II for Rs.6.980 m approved on 10/08/2017. LOA issued to AA Associates. PC-I/DCE under preparation. |
No Image |
Hangu | |||||||||||||||||||
1007 (OG) |
140950-F/S, Design and Dualization of 16 Km Road from Jamil Chowk (Ring Road) towards Urmar Payan Peshawar. |
Peshawar HW |
05-06-15 | - | - | 19-02-15 | - | 1046 | 397.815 | 100 | 85.5 | 85.5 | 85.5 | 483.315 | 548.185 | 48% |
46% December - 2017 |
8 Km asphaltic base completed, 3/4 bridges in progress. |
No Image |
1007 (OG) |
140950-F/S, Design and Dualization of 16 Km Road from Jamil Chowk (Ring Road) towards Urmar Payan Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1046 | 397.815 | 100 | 85.5 | 85.5 | 85.5 | 483.315 | 548.185 | 48% |
46% November - 2017 |
8 Km asphaltic base completed, 3/4 bridges in progress. |
No Image |
1007 (OG) |
140950-F/S, Design and Dualization of 16 Km Road from Jamil Chowk (Ring Road) towards Urmar Payan Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1046 | 397.815 | 100 | 100 | 85.5 | 85.5 | 483.315 | 548.185 | 48% |
46% October - 2017 |
7 Km asphaltic base completed, 3/4 bridges in progress. |
No Image |
1007 (OG) |
140950-F/S, Design and Dualization of 16 Km Road from Jamil Chowk (Ring Road) towards Urmar Payan Peshawar. |
Peshawar HW |
05-06-15 | - | - | 19-02-15 | - | 1046 | 397.815 | 100 | 100 | 85.5 | 85.5 | 483.315 | 548.185 | 48% |
46% September - 2017 |
7 Km asphaltic base completed, 3/4 bridges in progress. |
No Image |
1007 (OG) |
140950-F/S, Design and Dualization of 16 Km Road from Jamil Chowk (Ring Road) towards Urmar Payan Peshawar. |
Peshawar HW |
05-06-15 | - | - | 19-02-15 | - | 1046 | 397.815 | 100 | 100 | 35.5 | 35.5 | 433.315 | 548.185 | 48% |
41% August - 2017 |
7 Km asphaltic base completed, 3/4 bridges in progress. |
No Image |
1007 (OG) |
140950-F/S, Design and Dualization of 16 Km Road from Jamil Chowk (Ring Road) towards Urmar Payan Peshawar. |
Peshawar HW |
05-06-15 | - | - | 19-02-15 | - | 1046 | 397.815 | 100 | 100 | 35.5 | 35.5 | 433.315 | 548.185 | 48% |
41% July - 2017 |
7 Km asphaltic base completed, 4 Km base course in progress, 3/4 bridges in progress. |
No Image |
1007 (OG) |
140950-F/S, Design and Dualization of 16 Km Road from Jamil Chowk (Ring Road) towards Urmar Payan Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1046 | 397.815 | 100 | 177.235 | 177.235 | 177.235 | 575.05 | 548.185 | 48% |
55% June - 2018 |
8 Km asphaltic base completed and on 4 Nos bridges and surfacing in progress. |
No Image |
Package-1
Package-2
Bridge-1 at RD
Bridge-2 at RD | |||||||||||||||||||
1007 (OG) |
140950-F/S, Design and Dualization of 16 Km Road from Jamil Chowk (Ring Road) towards Urmar Payan Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1046 | 397.815 | 100 | 177.235 | 177.235 | 177.235 | 575.05 | 548.185 | 48% |
55% May - 2018 |
8 Km asphaltic base completed and on 4 Nos bridges in progress. Rs.80 m demanded for tempo of work. |
No Image |
Package-1
Package-2
Bridge-1 at RD
Bridge-2 at RD | |||||||||||||||||||
1007 (OG) |
140950-F/S, Design and Dualization of 16 Km Road from Jamil Chowk (Ring Road) towards Urmar Payan Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1046 | 397.815 | 100 | 177.235 | 177.235 | 127.625 | 525.44 | 548.185 | 48% |
50% April - 2018 |
8 Km asphaltic base completed and on 4 Nos bridges in progress. Rs.130 m demanded for tempo of work. |
No Image |
Package-1
Package-2
Bridge-1 at RD
Bridge-2 at RD | |||||||||||||||||||
1007 (OG) |
140950-F/S, Design and Dualization of 16 Km Road from Jamil Chowk (Ring Road) towards Urmar Payan Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1046 | 397.815 | 100 | 110.845 | 110.845 | 105.885 | 503.7 | 548.185 | 48% |
48% March - 2018 |
8 Km asphaltic base completed on 4 Nos bridges, in progress. Rs.150 m demanded for tempo of work. |
No Image |
Package-1
Package-2
Bridge-1 at RD
Bridge-2 at RD | |||||||||||||||||||
1007 (OG) |
140950-F/S, Design and Dualization of 16 Km Road from Jamil Chowk (Ring Road) towards Urmar Payan Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1046 | 397.815 | 100 | 108 | 108 | 105.885 | 503.7 | 548.185 | 48% |
48% February - 2018 |
8 Km asphaltic base completed on 4 Nos bridges, in progress. Rs.150 m demanded for tempo of work. |
No Image |
Package-1
Package-2
Bridge-1 at RD
Bridge-2 at RD | |||||||||||||||||||
1007 (OG) |
140950-F/S, Design and Dualization of 16 Km Road from Jamil Chowk (Ring Road) towards Urmar Payan Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1046 | 397.815 | 100 | 99.585 | 99.585 | 99.585 | 497.4 | 548.185 | 48% |
48% January - 2018 |
8 Km asphaltic base completed on 4 Nos bridges, in progress. Rs.250 m demanded for tempo of work. |
No Image |
1007 (OG) |
120248-Special Development Support for Khyber Pakhtunkhwa Police (Tor Ghar = Rs. 400.00 M Phase-III) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2000 | 1331.053 | 100 | 100 | 0 | 0 | 1331.053 | 0 | - |
- December - 2020 |
No Image | |
1007 (OG) |
120248-Special Development Support for Khyber Pakhtunkhwa Police (Tor Ghar = Rs. 400.00 M Phase-III) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2000 | 1331.053 | 100 | 100 | 0 | 0 | 1331.053 | 0 | - |
- December - 2020 |
No Image | |
1007 (OG) |
120248-Special Development Support for Khyber Pakhtunkhwa Police (Tor Ghar = Rs. 400.00 M Phase-III) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2000 | 1331.053 | 100 | 100 | 0 | 0 | 1331.053 | 0 | - |
- October - 2020 |
No Image | |
1007 (OG) |
120248-Special Development Support for Khyber Pakhtunkhwa Police (Tor Ghar = Rs. 400.00 M Phase-III) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2000 | 1331.053 | 100 | 100 | 0 | 0 | 1331.053 | 0 | - |
- September - 2020 |
No Image | |
1007 (OG) |
120248-Special Development Support for Khyber Pakhtunkhwa Police (Tor Ghar = Rs. 400.00 M Phase-III) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2000 | 1331.053 | 100 | 100 | 0 | 0 | 1331.053 | 0 | - |
- August - 2020 |
No Image | |
1007 (OG) |
120248-Special Development Support for Khyber Pakhtunkhwa Police (Tor Ghar = Rs. 400.00 M Phase-III) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2000 | 1331.053 | 100 | 0 | 0 | 0 | 1331.053 | 0 | - |
- July - 2020 |
No Image | |
1007 (OG) |
120248-Special Development Support for Khyber Pakhtunkhwa Police (Tor Ghar = Rs. 400.00 M Phase-III) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2000 | 1331.053 | 100 | 100 | 0 | 0 | 1331.053 | 0 | - |
- May - 2021 |
No Image | |
1007 (OG) |
120248-Special Development Support for Khyber Pakhtunkhwa Police (Tor Ghar = Rs. 400.00 M Phase-III) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2000 | 1331.053 | 100 | 100 | 0 | 0 | 1331.053 | 0 | - |
- April - 2021 |
No Image | |
1007 (OG) |
120248-Special Development Support for Khyber Pakhtunkhwa Police (Tor Ghar = Rs. 400.00 M Phase-III) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2000 | 1331.053 | 100 | 100 | 0 | 0 | 1331.053 | 0 | - |
- March - 2021 |
No Image | |
1007 (OG) |
120248-Special Development Support for Khyber Pakhtunkhwa Police (Tor Ghar = Rs. 400.00 M Phase-III) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2000 | 1331.053 | 100 | 100 | 0 | 0 | 1331.053 | 0 | - |
- February - 2021 |
No Image | |
1007 (OG) |
120248-Special Development Support for Khyber Pakhtunkhwa Police (Tor Ghar = Rs. 400.00 M Phase-III) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2000 | 1331.053 | 100 | 100 | 0 | 0 | 1331.053 | 0 | - |
- January - 2021 |
No Image | |
1007 (OG) |
140624-Dualization of Sherkot Hangu Section of Provincial Highway S-7 (24 KM), District Kohat and Hangu |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2759.858 | 1161.508 | 150 | 143.625 | 143.625 | 143.625 | 1305.133 | 1448.35 | 48% |
47% December - 2019 |
Pack-1 (6 Km) - embankment, in progress Km-1, 3, 4, 5, clearing/grubbing and NGC 90% completed. Pack-2 (6 Km) - Km-9, 10, 11 hillside cutting, RW in progress. Pack-3 (6 Km) - embankment in progress Km-16, 17, clearing/grubbing and NGC 80% completed. Pack-4 (6 Km) - clearing/grubbing Km-19, 20, embankment in progress. Pack-5 (4 bridges) - contractor machinery and staff mobilized on site. Design awaited for bridge pile from design consultant. Work stopped due to paucity of funds |
No Image |
1007 (OG) |
140624-Dualization of Sherkot Hangu Section of Provincial Highway S-7 (24 KM), District Kohat and Hangu |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2759.858 | 1161.508 | 150 | 150 | 37.5 | 37.5 | 1199.008 | 1448.35 | 48% |
43% November - 2019 |
Pack-1 (6 Km) - embankment, in progress Km-1, 3, 4, 5, clearing/grubbing and NGC 90% completed. Pack-2 (6 Km) - Km-9, 10, 11 hillside cutting, RW in progress. Pack-3 (6 Km) - embankment in progress Km-16, 17, clearing/grubbing and NGC 80% completed. Pack-4 (6 Km) - clearing/grubbing Km-19, 20, embankment in progress. Pack-5 (4 bridges) - contractor machinery and staff mobilized on site. Design awaited for bridge pile from design consultant. Work stopped due to paucity of funds |
No Image |
1007 (OG) |
140624-Dualization of Sherkot Hangu Section of Provincial Highway S-7 (24 KM), District Kohat and Hangu |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2759.858 | 1161.508 | 150 | 150 | 37.5 | 37.5 | 1199.008 | 1448.35 | 48% |
43% October - 2019 |
Pack-1 (6 Km) - embankment, in progress Km-1, 3, 4, 5, clearing/grubbing and NGC 90% completed. Pack-2 (6 Km) - Km-9, 10, 11 hillside cutting, RW in progress. Pack-3 (6 Km) - embankment in progress Km-16, 17, clearing/grubbing and NGC 80% completed. Pack-4 (6 Km) - clearing/grubbing Km-19, 20, embankment in progress. Pack-5 (4 bridges) - contractor machinery and staff mobilized on site. Design awaited for bridge pile from design consultant. Work stopped due to paucity of funds |
No Image |
1007 (OG) |
140624-Dualization of Sherkot Hangu Section of Provincial Highway S-7 (24 KM), District Kohat and Hangu |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2759.858 | 1161.508 | 150 | 150 | 37.5 | 37.5 | 1199.008 | 1448.35 | 48% |
43% September - 2019 |
Pack-1 (6 Km) - embankment, in progress Km-1, 3, 4, 5, clearing/grubbing and NGC 90% completed. Pack-2 (6 Km) - Km-9, 10, 11 hillside cutting, RW in progress. Pack-3 (6 Km) - embankment in progress Km-16, 17, clearing/grubbing and NGC 80% completed. Pack-4 (6 Km) - clearing/grubbing Km-19, 20, embankment in progress. Pack-5 (4 bridges) - contractor machinery and staff mobilized on site. Design awaited for bridge pile from design consultant. Work stopped due to paucity of funds |
No Image |
1007 (OG) |
140624-Dualization of Sherkot Hangu Section of Provincial Highway S-7 (24 KM), District Kohat and Hangu |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2759.858 | 1161.508 | 150 | 150 | 37.5 | 37.5 | 1199.008 | 1448.35 | 48% |
43% August - 2019 |
Pack-1 (6 Km) - embankment, in progress Km-1, 3, 4, 5, clearing/grubbing and NGC 90% completed. Pack-2 (6 Km) - Km-9, 10, 11 hillside cutting, RW in progress. Pack-3 (6 Km) - embankment in progress Km-16, 17, clearing/grubbing and NGC 80% completed. Pack-4 (6 Km) - clearing/grubbing Km-19, 20, embankment in progress. Pack-5 (4 bridges) - contractor machinery and staff mobilized on site. Design awaited for bridge pile from design consultant. Work stopped due to paucity of funds |
No Image |
1007 (OG) |
140624-Dualization of Sherkot Hangu Section of Provincial Highway S-7 (24 KM), District Kohat and Hangu |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2759.858 | 1161.508 | 150 | 335.625 | 335.325 | 335.625 | 1497.133 | 1448.35 | 48% |
54% May - 2020 |
Pack-1 (6 Km) - embankment, in progress Km-1, 3, 4, 5, clearing/grubbing and NGC 90% completed. Pack-2 (6 Km) - Km-9, 10, 11 hillside cutting, RW in progress. Pack-3 (6 Km) - embankment in progress Km-16, 17, clearing/grubbing and NGC 80% completed. Pack-4 (6 Km) - clearing/grubbing Km-19, 20, embankment in progress. Pack-5 (4 bridges) - contractor machinery and staff mobilized on site. Design awaited for bridge pile from design consultant. Work stopped due to paucity of funds |
No Image |
1007 (OG) |
140624-Dualization of Sherkot Hangu Section of Provincial Highway S-7 (24 KM), District Kohat and Hangu |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2759.858 | 1161.508 | 150 | 243.625 | 243.625 | 243.625 | 1405.133 | 1448.35 | 48% |
51% April - 2020 |
Pack-1 (6 Km) - embankment, in progress Km-1, 3, 4, 5, clearing/grubbing and NGC 90% completed. Pack-2 (6 Km) - Km-9, 10, 11 hillside cutting, RW in progress. Pack-3 (6 Km) - embankment in progress Km-16, 17, clearing/grubbing and NGC 80% completed. Pack-4 (6 Km) - clearing/grubbing Km-19, 20, embankment in progress. Pack-5 (4 bridges) - contractor machinery and staff mobilized on site. Design awaited for bridge pile from design consultant. Work stopped due to paucity of funds |
No Image |
1007 (OG) |
140624-Dualization of Sherkot Hangu Section of Provincial Highway S-7 (24 KM), District Kohat and Hangu |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2759.858 | 1161.508 | 150 | 243.625 | 243.625 | 243.625 | 1405.133 | 1448.35 | 48% |
51% March - 2020 |
Pack-1 (6 Km) - embankment, in progress Km-1, 3, 4, 5, clearing/grubbing and NGC 90% completed. Pack-2 (6 Km) - Km-9, 10, 11 hillside cutting, RW in progress. Pack-3 (6 Km) - embankment in progress Km-16, 17, clearing/grubbing and NGC 80% completed. Pack-4 (6 Km) - clearing/grubbing Km-19, 20, embankment in progress. Pack-5 (4 bridges) - contractor machinery and staff mobilized on site. Design awaited for bridge pile from design consultant. Work stopped due to paucity of funds |
No Image |
1007 (OG) |
140624-Dualization of Sherkot Hangu Section of Provincial Highway S-7 (24 KM), District Kohat and Hangu |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2759.858 | 1161.508 | 150 | 243.625 | 243.625 | 243.625 | 1405.133 | 1448.35 | 48% |
51% February - 2020 |
Pack-1 (6 Km) - embankment, in progress Km-1, 3, 4, 5, clearing/grubbing and NGC 90% completed. Pack-2 (6 Km) - Km-9, 10, 11 hillside cutting, RW in progress. Pack-3 (6 Km) - embankment in progress Km-16, 17, clearing/grubbing and NGC 80% completed. Pack-4 (6 Km) - clearing/grubbing Km-19, 20, embankment in progress. Pack-5 (4 bridges) - contractor machinery and staff mobilized on site. Design awaited for bridge pile from design consultant. Work stopped due to paucity of funds |
No Image |
1007 (OG) |
140624-Dualization of Sherkot Hangu Section of Provincial Highway S-7 (24 KM), District Kohat and Hangu |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2759.858 | 1161.508 | 150 | 143.625 | 143.625 | 143.625 | 1305.133 | 1448.35 | 48% |
47% January - 2020 |
Pack-1 (6 Km) - embankment, in progress Km-1, 3, 4, 5, clearing/grubbing and NGC 90% completed. Pack-2 (6 Km) - Km-9, 10, 11 hillside cutting, RW in progress. Pack-3 (6 Km) - embankment in progress Km-16, 17, clearing/grubbing and NGC 80% completed. Pack-4 (6 Km) - clearing/grubbing Km-19, 20, embankment in progress. Pack-5 (4 bridges) - contractor machinery and staff mobilized on site. Design awaited for bridge pile from design consultant. Work stopped due to paucity of funds |
No Image |