1154
Construction of Black topping of roads from (a) Darband to Kandgran (b) sekhi bala to sokal U/C Darra Shanaya District Mansehra
35.00
09-06-2016
1159
Feasibility study design and constrction of raod i/c 03 No. bridges along right bank of river Jehlum from Phalair to kohala 35 Km District Abbottabad jehlum from phalair to kohala 35 Km District Abbo
48.250
27-04-2016
1167
Provision of Publicity campaign of C&W Project During 2016-17
10.00
23-02-2017
1169
Construction of abutments and lunching of Canadian steel Bridges provided to pak Army fro khyber Pakhtunkhwa (CIDA Assisted)
316.644
20-01-2017
1170
Administrative approval for the scheme F/S Design and rehabilitation of C&W roads in KPK ADP 1170/160622 (2016-17)SH: construction of drain pavement of street & internal roads at village meraji khers
49.783
23-02-2017
1177
Construction of RCC over Dhoor at Mohra Mumdu District Haripur
173.524
29-02-2016
1186
Widening and Rehabilitation of Road from Mufti Mehmood Flyover to Old Budni Bridge on Provincial Highway S-I including re-construction of old budni bridge changed to widening and rehabilitation of ro
1119.959
29-04-2016
1209
Jica Assisted Khyber Pakhtunkhwa Emergency Rural SH: Rehabilitation and improvement of Peeple chok to ghazi baba road in District Mardan
132.307
29-02-2016
1213
PC-II for feasibility study detalied designing and supervision of vrious roads of C&W SH: construction of road from Kalam to Mahodand lake 27 KM District Swat only for design
16.20
29-02-2016
1215
Improvement rehabilitation and up -gradation of 300 KM roads in KPK SH: 05 No roads in PK -92 (4.30 KM) District Dir Upper
543.280
08-02-2016
1218
Construction widening improvement rehabilitation of roads and bridges on need basis in Khyber Pakhtunkhwa SH: Construction of 04 No.Roads in PK-48 district Abbottabad.
55.00
15-01-2016
1234
ddd
32
15-10-2019
1337
">
">